Performing critical path analysis technical tips and tricks
Performing critical path analysis Document author: Andy Jessop Produced by: Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart way to learn Microsoft Project. For further information, please go to: More useful tips and tricks can be found on the Project Learning blog: Related document(s): Displaying a critical path technical tips and tricks Project Learning International Limited PO Box 41-143, Lower Hutt 5047, New Zealand Performing critical path analysis Introduction A basic understanding of how a project's schedule is calculated can provide a much clearer understanding of what should happen when. At the heart of Microsoft Project is an algorithm that uses critical path analysis (CPA) to calculate a project s schedule. Most Microsoft Project users are either unaware of the CPA algorithm at all, or they are unsure as to how it performs its calculations.
Performing critical path analysis What critical path analysis calculates Critical path analysis (CPA) is a mathematical procedure that calculates a
Download Performing critical path analysis technical tips and tricks
Information
Domain:
Source:
Link to this page:
Please notify us if you found a problem with this document:
Related search queries
ANALYSIS AND DESIGN OF LIQUID-COOLING SYSTEMS, Technical, AACE Recommended Practice for Forensic Schedule Analysis, Recommended Practice for Forensic Schedule Analysis, Organizational Planning Process, Delay and Delay Analysis, Sample maintenance audit report, And Rod C. Carter, CCP, PSP, Analysis, Role’s Key Accountabilities: Laying, Role’s Key Accountabilities: Laying a Foundation, Displaying a Critical Path technical, Displaying a Critical Path