Work Breakdown Structure Reference Guide - tarrani.net
Program/Project Management SeriesWork Breakdown StructureReference GuideNational Aeronautics and 2Work Breakdown Structure Reference GuideMay 1994Space Administration May 1994 May 1994Work Breakdown Structure Reference GuideTable of Contents iiiChapter 1: WBS Basic InformationDefinition 1WBS Types 2P
8 Work Breakdown Structure Reference Guide May 1994 Summary As previously discussed, a work breakdown structure defines all work to be performed for project completion. It is a product -oriented structure, not an organizational structure. To