5. External Wall Construction

External wall construction265. External Wall ERECTION OF External PRECAST WALLSThe erection of precast walls generally involves the following steps:a)moving the precast wall panels from delivery truck or site storage yard to the designated locations forinstallation;b)raising the precast panels to the required elevation (and rotating to correct orientation if necessary);c)fixing the precast panels in position; andd)casting the wet joints and/or grouting and applying : Erection of a precast wall1. Remove precast wall fromdelivery the precast wall to requiredheight and orientation3. Position compressiblewaterproofing strip at joint4. Apply non-shrink precast wall into position6. Adjust position of precast wall7. Install plumb(and adjust if necessary)9. Remove excess grout infill afterprecast wall is erectedFigure : Wet CASTING OF WET JOINTSThe use of wet joints is essential in minimising water seepage through the joint : Casting of wet joint connections1.

Concrete surfaces at the joint should be sound, smooth, clean and free from all mortar dust or other contaminants that may affect the adhesion of sealant to the surfaces. Some sealants may require a primer to improve the adhesion. In such cases, manufacturer’s advice should be sought to ensure compatibility of the sealant and primer. As shown

Loading..

Tags:

  Surfaces, Primer

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Spam in document Broken preview Other abuse

Transcription of 5. External Wall Construction

Related search queries