draft EIS and draft Section 4(f) Evaluation 3-1 June 2017 Chapter 3: Construction Methods and Activities INTRODUCTION This Chapter describes the Construction Methods and Activities for the Hudson Tunnel Project s Preferred Alternative. The Preferred Alternative has two overarching components: (1) the Construction of a new trans-Hudson tunnel (the Hudson River Tunnel) and associated surface and rail system improvements; and (2) the rehabilitation of the existing North River Tunnel.
Information presented in this chapter and analyzed throughout this Environmental Impact Statement (EIS) is based on conceptual engineering (10 percent design) and is likely to evolve as the Project team advances the engineering. Accordingly, the preliminary sequencing plan and ... Draft EIS and Dr aft Section 4(f) Evaluation 3-3 June 2017