Exercise on Critical the Critical path of the following plan:Task Duration Dependency Task 1 4dTask 2 2d Task 34d2 Task 4 2d Deliverable A1, 3, 4 Task 6 6d 5 Task 7 2d 5 Deliverable B6, 7 Task 9 2d 1SS1/4 SolutionThe Critical path is the chain of activities which determines the project end date. Delay any activityin the Critical path by an arbitrarily small amount and the plan will be determination of the Critical path is based on the computation of the slack of each activity, computed by determining the earliest and latest starts (or ends) of each task in the plan. This data, infact, allows us to compute the slack of each activity. The Critical path is the path in which all activities have zero slack. The computation is performed starting from an AON representation of the first step is preprocessing the plan by: Transforming all dependencies into FS dependencies.
Solution The critical path is the chain of activities which determines the project end date. Delay any activity in the critical path by an arbitrarily small amount and the plan will be delayed. The determination of the critical path is based on the computation of the slack of each activity,
Domain:
Source:
Link to this page:
Please notify us if you found a problem with this document:
{{id}} {{{paragraph}}}
Critical Path Method Exercises, Critical path method, Critical Path, 12 Critical Path Analysis, Method, Critical, Lectures5&6&7 PM Scheduling IP ENCE603 ext instructor, Program Evaluation and Review Technique PERT, CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING, Path Method, Lecture 11 - critical chain, Lecture 11: Critical Chain, Path, DISCRETE MATHS Unit 2 Critical Path Analysis, PERT and Gantt, University of Arkansas at Little Rock