RMC Project Management, Inc. Extra Exercises on Network DiagramsCopyright 2018 RMC Publications, All rights Bren Road East Minnetonka, Minnesota (952) 846-4484 The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use 2018 RMC Publications, All rights Bren Road East Minnetonka, Minnesota (952) 846-4484 The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use 1 Using the table below, draw the Network diagram and answer the questions. When you have completed answering the ques-tions, do a forward/backward pass.
Using the table below, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass. 1. How many paths are in the network, and what are they? There are seven paths. See the details on the next page. 2. What is the critical path and its duration? Start, C, A, R, End 16 weeks 3.
Domain:
Source:
Link to this page:
Please notify us if you found a problem with this document:
{{id}} {{{paragraph}}}