hvac TESTING AND BALANCING ( commissioning not included) DOCUMENT NUMBER: 15305 APPLICATION: ELEMENTARY, MIDDLE AND HIGH SCHOOL DATE OF ISSUE: 12-05-14 - Miscellaneous clarifications, incl. revised design deviation tolerances 05-04-11 - Miscellaneous clarifications and requirements for additional equipment 11-08-10 - Revised Paragraph 01-12-10 - First Issue NOTES: The Contractor is to provide a final TESTING and BALANCING Report in accordance with the attached specification upon or before achieving Substantial Completion of the project or phase of the project (refer to paragraph ).
HVAC TESTING AND BALANCING SPECIFICATION 12-05-2014 . Testing and Balancing of HVAC Systems . 3/10 . 1.3 BALANCER QUALIFICATIONS . A. The Balancer shall be a member in good standing with The Associated Air Balance