Transcription of SAMPLE PMP PREPARATORY QUESTIONS AND …
{{id}} {{{paragraph}}}
SAMPLE PMP PREPARATORY QUESTIONS AND ANSWERS 160 Free PMP Exam Prep QUESTIONS (Obtained from PM Connection: ) 1. Regarding management and leadership all of the following are true except A. On a project, particularly a larger project, the project manager is generally expected to be the project's leader as well. B. Technical leadership is of primary importance in project management C. Managing is primarily concerned with consistently producing key results expected by stakeholders D. Leading involves establishing direction, aligning people, motivating and inspiring Answer: B 2. A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same project would take 9 months and would cost $250,000. The first project is a process optimization which would result in a cost reduction of $120,000 per benefit would be achieved immediately after the end of the project.
A. Scope Planning. B. Activity Duration Estimating. C. Scope Definition. D. Scope Verification. Answer: C 8. Which of the following Tools and Techniques are part of …
Domain:
Source:
Link to this page:
Please notify us if you found a problem with this document:
{{id}} {{{paragraph}}}