DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS JAPAN INTERNATIONAL COOPERATION AGENCY TECHNICAL STANDARDS AND GUIDELINES FOR DESIGN OF FLOOD CONTROL STRUCTURES June 2010 Project for the Strengthening of Flood Management Function of the DPWH i TABLE OF CONTENTS Chapter 1 DIKE .. 1 Basic concept .. 1 Materials .. 1 Causes of Dike Damages and Proposed Countermeasures.. 2 Design Consideration .. 2 Alignment .. 3 Design Criteria .. 4 Parts of Dike .. 4 Height .. 4 Freeboard.
Dike construction may include new dike and widening or raising existing dike. 1) Design of New Dike The new dike shall be designed to protect the affected flood prone areas. In consideration of the stability of the structure, the dike alignment shall avoid unstable peat and muck, weak subsoil, and loose sand foundation to prevent settlement.