Example: dental hygienist

Health and Safety Executive Heathrow Terminal 5 …

Heathrow Terminal 5 ProjectWorker engagement case study 2 This case study is part of a series of case studies, which giveexamples of best practice when engaging workers to improvehealth and Safety in the case study outlines the ways in which high standards ofworkforce consultation and engagement in Health and safetyare contributing to the exceptional Safety record beingachieved by the Terminal 5 Terminal 5 project presents a wide range of Health andsafety risks. All the normal civil engineering processes aretaking place, so transport movements, working at height,lifting operations, excavations and confined spaces are allcommon hazards on site. Innovative solutions are beingadopted, such as pre-fabricating sections of the terminalbuildings off site, and assembling the roof sections at low some sections of the project , up to 70% of constructionwork is carried out off order to achieve safe construction, the management teamrecognised from the start that the project would need topioneer and then sustain new industry standards of Health , Safety and security.

Heathrow Terminal 5 Project Worker engagement case study 2 This case study is part of a series of case studies, which give examples of best practice when engaging workers to …

Tags:

  Study, Project, Terminal, Heathrow, Heathrow terminal 5, Heathrow terminal 5 project

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of Health and Safety Executive Heathrow Terminal 5 …

1 Heathrow Terminal 5 ProjectWorker engagement case study 2 This case study is part of a series of case studies, which giveexamples of best practice when engaging workers to improvehealth and Safety in the case study outlines the ways in which high standards ofworkforce consultation and engagement in Health and safetyare contributing to the exceptional Safety record beingachieved by the Terminal 5 Terminal 5 project presents a wide range of Health andsafety risks. All the normal civil engineering processes aretaking place, so transport movements, working at height,lifting operations, excavations and confined spaces are allcommon hazards on site. Innovative solutions are beingadopted, such as pre-fabricating sections of the terminalbuildings off site, and assembling the roof sections at low some sections of the project , up to 70% of constructionwork is carried out off order to achieve safe construction, the management teamrecognised from the start that the project would need topioneer and then sustain new industry standards of Health , Safety and security.

2 This case study examines how one partof the project , the Terminal 5B (T5B) section, has developedeffective methods of ensuring workforce participation, andbecame the first section of the project to achieve one millionsafe working hours without a reportable Safety Committee The 5B project team is responsible for the construction of thesecond Terminal building, with the tunnels of the Track TransitSystem connecting T5B to the main Terminal ( Terminal 5,Concourse A). Around 400 workers are engaged inconstruction on 5B in January 2005, with completion of thissection scheduled for 2006. The 5B project team includes full-time Safety leader CliveJohnson, employed by BAA, together with other dedicatedsafety professionals from the 5B suppliers. The SafetyLeadership team meets monthly to discuss progress, and toHealth and Safety ExecutiveProject fact fileHeathrow s Terminal 5 is one of Europe s largestconstruction projects. Work started in 2002, and the firstpassengers are scheduled to use the Terminal in spring project includes three massive Terminal buildings, aswell as aircraft stands, bridges, km of road andrailway tunnels and associated infrastructure on the 251-hectare site.

3 Around 6000 people are involved in theconstruction work at any one time. The client for theproject is the British Airports Authority (BAA) and many ofthe UK s leading contractors are Terminal 5 project is broken down into 16 majorprojects, managed from open-plan offices on site,incorporating integrated management teams made up ofBAA staff with management teams from the key client, BAA, is working with all its suppliers in agroundbreaking partnership contract which allows fornon-adversarial joint working between all parties. There is a dedicated occupational Health team on site,who spend about two-thirds of their time onpreventative work, as well as providing a comprehensivetreatment and emergency response the outcomes of the fortnightly Safety Safety Committee consists of about 15 worker-representatives from the major suppliers and sections of theT5B project . Senior project managers from key suppliersattend, with BAA s Safety leader in an advisory role. The safetyleadership team includes a member of the Safety Committeeto ensure that the workforce is represented at all levels.

4 Figure 1 Electrician Phil Rayment, who chaired the SafetyCommittee meeting on 27 January 2005 One or two of the worker representatives are appointed andtrained by trades unions. The others are a mix of volunteersand representatives appointed by their own companies. Thecommittee is chaired in rotation by one of the workforce. The committee meeting dates and times are well advertisedaround the site by posters, giving advance opportunity forworkers to raise concerns with their representatives. Meetingsare minuted, so matters raised can be followed through toensure they are dealt 27 January 2005, it was the turn of electrician Phil meeting started at midday, lasting about an hour and ahalf, and was an opportunity for the 2004 project figures tobe reviewed: two periods of one million accident-free hours; a 12% reduction in reportable accidents in 2004 from 2003; a 45% reduction in minor injury rates, coupled withimproved near miss near-miss reporting system provides vital intelligence forthe committee.

5 Every time a significant near miss is reported, asafety alert is produced and distributed around the site within24 hours. This provides basic details about how the incidentwas caused, and what should have been done to prevent incidents were also discussed at the 27 Januarymeeting. These included a slip on one of the Terminal roofsections, resulting in a fractured elbow, and three minor eyeinjuries it was reported that these resulted from incorrect useof eye protection. Encouragingly, an incident was reportedfrom just before Christmas when three workers who wereadjacent to a concrete pump were showered with concretewhen a joint failed, but because they were wearing goggles,serious eye injuries were members of the committee contribute to the of welfare, housekeeping and Safety are all managers respond to the concerns raised and timescalesWorker engagement case study 2are set for action. The agenda includes the opportunity toraise any matters that concern committee on his experience of the committee, MichaelFirmin, an Amicus Safety Representative, said that he found it: satisfying, knowing that I can make a contribution to Safety , tokeeping my mates safe.

6 I am pleased that I can raise issueson this committee and know that they will be dealt with. The daily activity briefingOn T5B, one of the key methods of ensuring that all workersare engaged in the process of managing Health and safetyon site is the daily activity briefing (DAB). This is part of the Incident and Injury Free campaign adopted by the site. All team supervisors carry out a DAB before starting work. Thesupervisor goes through the method of work, and checks withindividual workers to make sure everyone understands how towork safely, and also how to control the risks to other gangswho may be working nearby. Every worker has the opportunityto question the supervisor or make suggestions to improve theworking benefits of a Safety culture There is a huge benefit in having the management team co-located and integrated with the client, designers and theworkforce. This is a truly collaborative environment. Theworkforce do raise their concerns and with support from themanagement team, we deal with their concerns andsuggestions.

7 Martin Quaid, Production Leader for T5 BTerminal 5 has reaped the benefits from this approach with: a Safety record four times better than the industry average; a working environment that attracts skilled workers; positive feedback from their insurers; and a project that is currently on budget and ahead online by the Health and Safety Executive 2/05 Figure 2 Workers attending a daily activity briefingFigure 3 Electricians at work, following the daily activity briefing