Example: tourism industry

BLUEBOOK - National Grid

BLUEBOOK SPECIFICATIONS AND REQUIREMENTS FOR GAS INSTALLATIONS NEW YORK CITY AND LONG ISLAND DECEMBER 2020 IMPORTANT NOTICE REGARDING National grid SPECIFICATIONS AND REQUIREMENTS FOR GAS INSTALLATIONS These Specifications and Requirements have been designed with great care so that, when followed consistently, they will ensure that a new installation will comply with New York State law, various codes and other safety requirements. Failure to comply may result in a code or safety violation and/or a job not being approved. Therefore, delays could result while the contractor corrects the changes at his/her expense. The specifications, construction standards and other requirements contained in this book represent National grid s commitment to the contracting community for quality and consistency of service. Any variation from the type of hardware used, connection point of service, service entrance or other details on a construction standard must be approved in advance by National grid in writing.

6.2 RESIDENTIAL, COMMERCIAL, INDUSTRIAL, MULTI-FAMILY . INSTALLATIONS IN NASSAU AND SUFFOLK COUNTIES..... 43 8. 6 .3 ALL PUBLIC AND PRIVATE SCHOOL BUILDINGS, ... safe and satisfactory utilization of natural gas by our customers. The information ... The contents of this book apply to installations connecting gas supply system to a customer's ...

Tags:

  Grid, Industrial, Installation, National, Natural, Natural gas, Bluebook, National grid

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Transcription of BLUEBOOK - National Grid

1 BLUEBOOK SPECIFICATIONS AND REQUIREMENTS FOR GAS INSTALLATIONS NEW YORK CITY AND LONG ISLAND DECEMBER 2020 IMPORTANT NOTICE REGARDING National grid SPECIFICATIONS AND REQUIREMENTS FOR GAS INSTALLATIONS These Specifications and Requirements have been designed with great care so that, when followed consistently, they will ensure that a new installation will comply with New York State law, various codes and other safety requirements. Failure to comply may result in a code or safety violation and/or a job not being approved. Therefore, delays could result while the contractor corrects the changes at his/her expense. The specifications, construction standards and other requirements contained in this book represent National grid s commitment to the contracting community for quality and consistency of service. Any variation from the type of hardware used, connection point of service, service entrance or other details on a construction standard must be approved in advance by National grid in writing.

2 We at National grid are always available to discuss your design concerns and to provide assistance to you. We encourage any questions regarding your problems on specific projects, please be sure to contact us for our input during the planning stages to avoid possible additional costs later in the job. Paul Gugliotta Materials & Standards/Gas Engineering Peter Polumbo Policy & Procedures Robert Zabielski - Gas Customer Meter Service Paul Brillantes - Gas Customer Meter Services Steven Massaro - Gas Customer Meter Services Richard Verderame - Gas Customer Meter Services Evan Schierwagen - Gas Customer Meter Services Joseph Scibelli Customer Gas Connections Daniel Lundon - Gas Customer Meter Services David Malone - Gas Customer Meter Services Louis Quaranta - Gas Customer Meter Services Jeffery Vinciguerra - Gas Customer Meter Services Revision 11, December 2020 Table of Contents P age 1 of 4 TABLE OF CONTENTS INTRODUCTION 1 PURPOSE.

3 1 SCOPE/REFERENCES .. 1 EXCLUSIONS; RETROACTIVITY .. 2 ALTERNATE MATERIALS, EQUIPMENT AND PROCEDURES .. 2 RESPONSIBILITY .. 2 DEFINITION OF TERMS .. 2- 8 GENERAL .. 9 AREA/GEOGRAPHICAL CONSIDERATIONS .. 9 9 MEANING OF "SHALL" IN THIS BOOK .. 9 STATE AND LOCAL CODES .. 10 RESPONSIBILITY FOR CODE APPLICABILITY .. 10 INSPECTIONS, CERTIFICATES, PERMITS .. 10 ACCESS TO CUSTOMERS' PREMISES .. 10 IDENTIFICATION OF EMPLOYEES .. 10 UNAUTHORIZED CONNECTIONS .. 10 SEALS AND TAMPERING DEVICES .. 11 DISCONNECTION OF 11 REACTIVATING GAS SERVICE FOLLOWING A WARNING TAG VIOLATION .. 11 National grid EQUIPMENT ON PRIVATE PROPERTY .. 11 DEMOLITION .. 11 INTERCONNECTIONS .. 11 BACK-PRESSURE AND SUCTION PROTECTION .. 12 PROTECTION WHEN COMPRESSED AIR OR OXYGEN CAN ENTER GAS PIPING .. 12 ADEQUACY AND SAFETY .. 12 CODE COMPLIANCE.

4 12 REVISIONS OF THIS BOOK .. 12 NEW GAS SERVICE installation PROCESS .. 13 GENERAL .. 13 REQUIREMENTS FOR HAVING A NEW RESIDENTIAL AND SMALL COMMERCIAL GAS SERVICE INSTALLED .. 20 RUD AND CIPUD SERVICE .. 21 GAS SERVICE LINE(S) .. 25 GAS SERVICE LINE(S) TO A BUILDING OR OTHER GAS USAGE .. 25 LOCATION OF GAS SERVICE LINE(S)/LATERAL(S) .. 25 Revision 11, December 2020 Table of Contents Page 2 of 4 SERVICE 26 CONNECTION POINT OF SERVICE, BROOKLYN UNION/CUSTOMER CONNECTION POINT OF GAS SERVICE .. 26 RESTORATION ON PRIVATE PROPERTY .. 26 ADDITIONAL METERS OR SERVICES .. 26 GAS PRESSURE .. 26 NOMINAL METER OUTLET PRESSURE WHEN SERVED FROM BROOKLYN UNION'S HIGH PRESSURE DISTRIBUTION 27 METER OUTLET PRESSURE WHEN SERVED FROM National grid S LOW PRESSURE DISTRIBUTION SYSTEM.

5 27 PRESSURE AND CONTRACTOR'S PIPING ..27 ELEVATED METER OUTLET PRESSURE ON HIGH PRESSURE DISTRIBUTION SYSTEM .. 27 ELEVATED METER OUTLET PRESSURE ON LOW PRESSURE DISTRIBUTION SYSTEM .. 29 LOCAL CODES RELATING TO ELEVATED GAS PRESSURES .. 29 METERS AND REGULATORS .. 29 PREREQUISITES AND NOTIFICATIONS FOR NEW GAS METERS .. 29 METER SET LOCATION REQUIREMENTS .. 30 installation AND INTERCONNECTION REQUIREMENTS .. 32 INDOOR METER SET 32 INDOOR METER SET REQUIREMENTS FOR LARGE INSTALLATIONS .. 32 MULTIPLE METER HEADER REQUIREMENTS .. 33 METER SET PROTECTION REQUIREMENTS .. 34 METER HEADER PAD REQUIREMENTS FOR LARGE GAS INSTALLATIONS .. 34 WALLS TO SUPPORT METER HEADER REQUIREMENTS .. 34 RELOCATION OF GAS METER SETS .. 35 GAS SERVICE REGULATOR AND VENTING REQUIREMENTS .. 35 METER BYPASS TELEMETERING installation REQUIREMENTS.

6 36 METER installation , PURGING AND RELIGHTING .. 36 PILOT GAS SUPPLY FOR INTERRUPTIBLE RATE CUSTOMERS .. 37 CUSTOMER-OWNED GAS PIPING 37 GENERAL .. 37 PIPE SIZING .. 38 PIPING DRAWING .. 39 GAS PIPING MATERIALS .. 39 GENERAL .. 39 GAS PIPING MATERIALS, INDOORS .. 39 GAS PIPING MATERIALS, OUTDOORS, ABOVE GROUND .. 40 GAS PIPING MATERIALS, BELOW GROUND, GENERAL .. 40 GAS PIPING BELOW GROUND, STEEL PIPE OPTION .. 41 GAS PIPING BELOW GROUND, PLASTIC PIPE OPTION .. 41 GAS "PIPING" BELOW GROUND, COPPER TUBING OPTION .. 42 .. 42 STEEL GAS PIPING, WELDING REQUIREMENTS .. 43 Revision 11, December 2020 Page 3 of 4 Table of Contents RESIDENTIAL, COMMERCIAL, industrial , MULTI-FAMILY INSTALLATIONS IN NASSAU AND SUFFOLK COUNTIES .. 43 ALL PUBLIC AND PRIVATE SCHOOL BUILDINGS, INCLUDING COLLEGES ..44 TESTING REQUIREMENTS OF PIPING AFTER THE STANDARDS FOR NON MERCURY WELDER GAS PIPING (INDOORS AND OUTDOORS) ABOVE GROUND, installation REQUIREMENTS, GENERAL.

7 46 GAS PIPING OUTDOORS, BELOW GROUND, installation REQUIREMENTS .. 47 STEEL GAS PIPING , CORROSION PROTECTION REQUIREMENTS, COATING AND WRAPPING .. 49 STEEL GAS PIPING, CORROSION PROTECTION REQUIREMENTS, INSULATING JOINTS .. 49 STEEL GAS PIPING, CORROSION PROTECTION REQUIREMENTS, MAGNESIUM ANODES .. 49 PLASTIC PIPING, installation REQUIREMENTS ..50 COPPER TUBING installation REQUIREMENTS .. 51 GAS PIPING THROUGH BUILDING WALLS, ABOVE OR BELOW GROUND, installation 52 PRESSURE TESTING OF GAS PIPING .. 52 GAS UTILIZATION EQUIPMENT .. 52 GENERAL .. 52 APPLIANCES, ACCESSORIES AND EQUIPMENT APPROVAL .. 52 INSTALLING CONTRACTOR'S RESPONSIBILITIES .. 52 CO ALARMS .. 53 ASSEMBLY OF EQUIPMENT .. 52 GAS UTILIZATION EQUIPMENT INSTALLED IN RESIDENTIAL National grid natural GAS PRESSURE, IGNITION & DRAFT TEST.

8 53 GENERAL REQUIREMENTS, SPACE AND WATER HEATING EQUIPMENT INSTALLATIONS .. 53 COMBUSTION, DILUTION AND VENTILATION AIR (FRESH AIR) REQUIREMENTS .. 53 VENTING OF CATEGORY I GAS UTILIZATION EQUIPMENT ONLY .. 54 VENTING OF GAS UTILIZATION EQUIPMENT - CATEGORIIES II, III AND IV .. 54 CHIMNEYS .. 54 SPILL SWITCH REQUIREMENTS .. 55 installation OF HEAT PRODUCING EQUIPMENT IN FLAMMABLE OR CORROSIVE ATMOSPHERES ..55 Revision 11, December 2020 Table of Contents Page 4 of 4 GAS CONVERSIONS AND CONVERSION BURNER REQUIREMENTS .. 56 GAS FIREPLACES (VENTED DECORATIVE GAS APPLIANCES) .. 57 ILLIMINATING DEVICES .. 57 natural GAS COMBUSTION ENGINES .. 58 COMPRESSED natural GAS (CNG) STATIONS .. 58 UNVENTED ROOM HEATERS .. 58 OTHER EQUIPMEMNT .. 58 COMBO WATER 58 APPENDICES APPENDIX A SERVICE REGULATOR VENT PIPING REQUIREMENTS APPENDIX B CHOOSING A FURNACE OR BOILER APPENDIX C National grid S NEW METER SET HOTLINE APPENDIX D GAS PIPING SYSTEM PRESSURE TESTING REQUIREMENTS AND INSTRUCTIONS APPENDIX E CUSTOMER OWNER GAS PIPING INSPECTION CERTIFICATE APPENDIX F CORRIGATED ATAINLESS STEEL TUBING APPENDIX G NEW YORK STATE CO ALARM LAW RULE APPENDIX H PROPERTIES OF natural GAS APPENDIX I METER SIZES AND DIMENSIONS APPENDIX J FREQUENTLY USED STANDARDS APPENDIX K LINKS TO MANUFACTURERS APPENDIX L ODOR FADE Blue Book PART II Temperature Controlled Specifications Revision 11.

9 December 2020 Page 1 of 58 33 1 INTRODUCTION PURPOSE This book presents specifications and requirements relating to the connection and use of natural gas supplied from the National grid Gas System. It contains the minimum acceptable standards for gas piping and gas appliance installation necessary to ensure the safe and satisfactory utilization of natural gas by our customers. The information contained herein is intended primarily to assist the installer in the new gas installation process, but it is also intended for use by our customers, by architects and engineers, and finally, by people in various departments at National grid . It shall be used when a customer's gas installation is new, when a customer is increasing gas usage from a smaller capacity, or when any changes are made from the original installation . It represents a collection of information which will provide for a safe, properly conceived, accurately sized and cost effective installation that will give long lasting, satisfactory service to our customers.

10 The operation of the head of service valve or meter valve is restricted to National grid s Operator Qualified personnel. National grid s jurisdictional ends at the outlet of the National grid meter. SCOPE/REFERENCES The contents of this book apply to installations connecting gas supply system to a customer's premises. We have made it as comprehensive as is practical, within the limits of the intended overview of the subject matter it addresses. The intent of the book is to provide a framework for the subject, not a collection of specific information from various sources. Generally, it refers to several primary documents which form its basis: a. The National Fuel Gas Code (NFPA 54/ANSI ), latest revision, referred to in the book as NFPA 54. (COVERS CUSTOMER OWNED PIPING AFTER THE GAS METER) b. The New York State Codes, Rules and Regulations Title 19 (16 NYCRR 255 and 261), latest revision, referred to in the book as NYCRR.


Related search queries