Page 1 of 42 Sharing of Inter State Transmission Charges and Losses Regulations, 2010 CENTRAL ELECTRICITY REGULATORY commission NEW delhi Dated: 15th June 2010 NOTIFICATION In exercise of the powers conferred under section 178 read with Part V of the ELECTRICITY Act, 2003 (36 of 2003), and all other powers enabling it in this behalf, and after previous publication, the CENTRAL ELECTRICITY REGULATORY commission hereby makes the following regulations: CHAPTER 1: PRELIMINARY 1. Short title, extent and commencement.

Page 1 of 42 Sharing of Inter State Transmission Charges and Losses Regulations, 2010 CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI No.L-1/44/2010-CERC Dated: 15th June 2010 NOTIFICATION

Tags:

  Commission, Regulatory, Delhi, Transmissions, Central, Electricity, Central electricity regulatory, Central electricity regulatory commission new delhi

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of CENTRAL ELECTRICITY REGULATORY …

1 Page 1 of 42 Sharing of Inter State Transmission Charges and Losses Regulations, 2010 CENTRAL ELECTRICITY REGULATORY commission NEW delhi Dated: 15th June 2010 NOTIFICATION In exercise of the powers conferred under section 178 read with Part V of the ELECTRICITY Act, 2003 (36 of 2003), and all other powers enabling it in this behalf, and after previous publication, the CENTRAL ELECTRICITY REGULATORY commission hereby makes the following regulations: CHAPTER 1: PRELIMINARY 1. Short title, extent and commencement.

2 (1) These regulations may be called the CENTRAL ELECTRICITY REGULATORY commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010. (2) These regulations shall apply to all Designated ISTS Customers, Inter State Transmission Licensees, NLDC, RLDC, SLDCs, and RPCs. (3) These regulations shall come into force from , and unless reviewed earlier or extended by the commission , shall remain in force for a period of 5 years from the date of commencement specified above. 2. Definitions. (1) In these Regulations, unless the context otherwise requires,:- (a) Act means the ELECTRICITY Act, 2003 (36 of 2003); (b) Application Period means the period of application of the charges determined as per these regulations and shall ordinarily be 12 (twelve) months coinciding with the Financial Year, which shall be further divided into multiple blocks of months representing the seasonal conditions and peak and other than peak conditions.

3 Page 2 of 42 Sharing of Inter State Transmission Charges and Losses Regulations, 2010 (c) Approved Injection means the injection in MW vetted by Implementing Agency (IA) for the Designated ISTS Customer for each representative block of months, peak and other than peak scenarios at the ex-bus of the generator or any other injection point of the Designated ISTS Customer into the ISTS, and determined based on the generation data submitted by the Designated ISTS Customers incorporating total injection into the grid, considering the long term and medium term contracts.

4 (d) Approved Additional Medium Term Injection means the additional injection, as per the Medium Term Open Access approved by CTU after submission of data to NLDC by the Designated ISTS Customer over and above the Approved Injection for the Designated ISTS Customer for each representative block of months, peak and off-peak scenarios at the ex-bus of the generator or any other injection point of the Designated ISTS Customer into the ISTS; (e) Approved Short Term Injection means the injection, as per the Short Term Open Access approved by RLDC / NLDC such injection including all injections cleared on the power exchange.

5 (f) Approved Withdrawal means the simultaneous withdrawal in MW vetted by Implementing Agency for any Designated ISTS Customer in a control area aggregated from all nodes of ISTS to which Designated ISTS Customer is connected for each representative block of months, peak and other than peak scenarios at the interface point with ISTS, and where the Approved Withdrawal shall be determined based on the demand data submitted by the Designated ISTS Customers. incorporating long term and medium term transactions; (g) Approved Additional Medium Term Withdrawal means additional withdrawal, as per the Medium Term Open Access approved by CTU after submission of data to NLDC by the Designated ISTS Customer over and above Approved Withdrawal for Designated ISTS Customer s aggregated from all nodes of ISTS for each representative block of months, peak and other than peak scenarios at the interface point with the ISTS.

6 (h) Approved Short Term Withdrawal means withdrawal, as per the Short Term Open Access approved by RLDC/NLDC and where such Withdrawal includes all withdrawals cleared on the power exchange; Page 3 of 42 Sharing of Inter State Transmission Charges and Losses Regulations, 2010 (i) Basic Network shall mean the power system of the country at voltage levels 132 kV and above and 110 kV where generators are connected, HVDC transmission network and all Generator and loads connected to it; (j) Bulk Power Transmission Agreement (BPTA) means the agreements between the ISTS licensees and the Designated ISTS Customers of the ISTS under the pre-existing arrangements for ISTS development and operations; (k) Deemed Inter State Transmission System (Deemed ISTS) means such transmission system which has REGULATORY approval of the commission as being used for interstate transmission of power and qualified as ISTS for the purpose of these Regulations unless otherwise specified.

7 (l) Designated ISTS Customers ( DIC s) means the users of any segments/elements of the ISTS and shall include all generators, state transmission utilities, SEBs or load serving entities directly connected to the ISTS including Bulk Consumer and any other entity/person; (m) Hybrid Methodology shall mean the hybrid of the Marginal Participation Method and the Average Participation method detailed in Chapter-3 of these regulations and in Annexure - I hereto. (n) Implementing Agency (IA) shall mean the agency designated by the commission to undertake the estimation of allocation of transmission charges and transmission losses at various nodes/zones for the Application Period along with other functions as per [Chapter-4, Chapter-5, Chapter-6, Chapter-7 and Chapter-8] of these regulations; (o) Loss Allocation Factor of a bus measures the losses attributed to that node and shall be computed as explained in the Annexure - I of these regulations.

8 (p) Monthly Transmission Charge means the transmission charges (inclusive of incentives) payable for each calendar month as given in the Terms and Conditions of Tariff Regulations in force; (q) Node shall mean a sub-station or a switchyard of a generator; (r) Point of Connection (PoC) Charging Method shall mean the methodology of computation of sharing of ISTS charges and losses amongst Designated ISTS Customers, which depends on the location of the node in the grid and is calculated in accordance with Regulation 7(1(q)) and 7(1(s)) of chapter 4 of these regulations; (s) Point of Connection (PoC) transmission charges are the nodal / zonal charges determined using the Point of Connection charging method.

9 Page 4 of 42 Sharing of Inter State Transmission Charges and Losses Regulations, 2010 (t) Participation Factor of a node in any transmission line means the percentage usage of that line by a node, whether a generator node or a demand node as explained in Annexure - I of these regulations. (u) Transmission Service Agreement (TSA) shall mean the agreement to be entered into between the Designated ISTS Customer(s) and ISTS Licensee(s) in terms of Chapter 6; (v) Uniform Charge means the charge determined by dividing the Yearly Transmission Charge of the ISTS Licensees by the sum of the Approved Injection and Approved Withdrawal from the grid alternatively referred to as the postage stamp charge.

10 (w) Uniform Charge Sharing Mechanism means the mechanism for determination of Uniform Charges; (x) Uniform Loss means the energy loss and shall be accounted for by providing a differential between schedules at the points of supply, inter-utility transfer and drawal of ELECTRICITY and shall be computed as the percentage of energy lost in the grid. Explanation - Uniform shall mean that such percentage loss is applied uniformly to all Designated ISTS Customers in a region irrespective of their location in the grid. (y) Yearly Transmission Charge (YTC) means the Annual Transmission Charges for existing lines determined by the commission in accordance with the Terms and Conditions of Tariff Regulations or adopted in the case of tariff based competitive bidding in accordance with the Transmission License Regulations as specified by the commission and as in force from time to time and for new lines based on benchmarked capital costs.