Energy Corporation of NSW. Central- West Orana Renewable Energy Zone Project Overview February 2022. Message from The Hon. Matt Kean MP. Treasurer and Minister for Energy The Central-West Orana Renewable and will attract around $ billion of will lead the development process, Energy Zone will be a game changer private investment into the Central-West including community and stakeholder for NSW. Orana region by 2030, and support engagement, property negotiations, around 3,900 peak construction jobs and environmental assessments and This modern day power station will 500 ongoing jobs. coordination of new generation. revolutionise the way Energy is generated and transmitted across the The NSW Government is committed to EnergyCo will also lead a competitive State and set the benchmark for future preserving the State's social licence process to appoint a Network Operator Renewable Energy zones (REZs) across through a safe, environmentally to design, build, finance, operate the country.

Central-West Orana Renewable Energy Zone. 4. The State’s five existing coal fired power stations will progressively close, starting with Liddell in 2022-23. These power stations currently provide around three quarters of NSW’s electricity supply and two thirds of the firm capacity required during summer heat waves.

Tags:

  Heat, Zones

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Transcription of Central-West Orana Renewable Energy Zone

1 Energy Corporation of NSW. Central- West Orana Renewable Energy Zone Project Overview February 2022. Message from The Hon. Matt Kean MP. Treasurer and Minister for Energy The Central-West Orana Renewable and will attract around $ billion of will lead the development process, Energy Zone will be a game changer private investment into the Central-West including community and stakeholder for NSW. Orana region by 2030, and support engagement, property negotiations, around 3,900 peak construction jobs and environmental assessments and This modern day power station will 500 ongoing jobs. coordination of new generation. revolutionise the way Energy is generated and transmitted across the The NSW Government is committed to EnergyCo will also lead a competitive State and set the benchmark for future preserving the State's social licence process to appoint a Network Operator Renewable Energy zones (REZs) across through a safe, environmentally to design, build, finance, operate the country.

2 Responsible and culturally respectful and maintain the new transmission approach, and engagement with the infrastructure in the REZ. The NSW Government is leading the way community and stakeholders will be in reducing emissions and transforming a primary focus as we deliver this This is an exciting time for Renewable our electricity system into one that pilot REZ. Energy in NSW, and I look forward to is cheap, clean and reliable through hearing the results of the stakeholder the Electricity Strategy and Electricity The NSW Government has appointed the and community engagement process. Infrastructure Roadmap. Energy Corporation of NSW (EnergyCo). as the Infrastructure Planner for the Matt Kean MP. The Central-West Orana REZ will be Central-West Orana REZ.

3 EnergyCo Treasurer and Minister for Energy the first of five new REZs across NSW. Central-West Orana Renewable Energy Zone 2. Contents The Energy transformation 4. Renewable Energy zones 5. EnergyCo 6. The Central-West Orana REZ 7. REZ network infrastructure 8. Route selection process 9. Study area 10. Environmental planning 11. Working with landowners 12. Property acquisition 13. Community & stakeholder consultation 14. Central-West Orana Renewable Energy Zone 3. The Energy transformation The State's five existing coal fired power stations will progressively close, starting with Liddell in 2022-23. These power stations currently provide around three quarters of NSW's electricity supply and two thirds of the firm capacity required during summer heat waves.

4 The NSW Government is taking action to lead investment in new Renewable generation to ensure an orderly transition away from coal. With some of the best Renewable Energy resources in the world, NSW is in a unique position to benefit from emerging low-cost technologies like wind, solar, batteries and pumped hydro. The NSW Government has published the Electricity Infrastructure Roadmap. For more information about the Roadmap please scan the QR code to visit the online interactive portal. Central-West Orana Renewable Energy Zone 4. Renewable Energy zones Renewable Energy zones are modern-day power stations, connecting new clean generation and storage to electricity consumers across the State. Wind Solar Storage The NSW Government is leading the development of Renewable Energy zones Renewable Energy (REZs) across NSW.

5 REZs will deliver wind and solar generation and storage such as Zone locations batteries in a planned way where there is Five REZs have been announced in NSW. community support. The first REZ declared was Central-West Orana and the second was New England. The Energy The REZs will be serviced by new high- South West, Hunter and Illawarra REZs will Hub capacity transmission infrastructure to be declared in due course. deliver Energy to the homes, businesses and industries that need it. This will achieve economies of scale for cheap, clean and reliable electricity. Benefits for communities Transmission line The REZ is expected to bring in more than Factors considered when planning a $5 billion of new investment to the region REZ include: and more than 3,900 jobs in construction.

6 Availability of wind and solar resources The Government has legislated funding land uses impacts, including strategic for community purposes in declared REZs agricultural land funded by new generators. environmental values population and dwelling density distance to existing high voltage New Renewable generation Existing transmission network transmission lines. New REZ infrastructure Energy users Central-West Orana Renewable Energy Zone 5. EnergyCo EnergyCo is a NSW Government The Consumer Trustee statutory authority responsible AEMO Services has been appointed as the for the delivery of the Electricity Consumer Trustee. The Consumer Trustee Infrastructure Roadmap. acts independently to protect the long term financial interests of Energy consumers and The NSW Government has appointed the hence the affordability of electricity.

7 Energy Corporation of NSW (EnergyCo) as the Infrastructure Planner responsible for If appropriate, the Consumer Trustee will delivering the Central-West Orana REZ. approve the infrastructure solution proposed by EnergyCo and authorise the Network This recognises the critical importance of Operator for the Central-West Orana REZ. The the Energy transition to our State's economy Consumer Trustee will also run an auction and the need to engage with a wide range process to award access rights to developers of stakeholders. of wind and solar generation projects. Further information about AEMO Services EnergyCo has responsibilities including: and its role as the Consumer Trustee is available at working with developers of proposed wind, solar and storage projects to understand their needs and plan for efficient solutions that minimise cumulative impacts on Australian Energy the community Regulator (AER).

8 Leading engagement with the community Once a Network Operator is selected, the AER. and stakeholders will review the overall costs of the project developing the Reference Scope for to ensure that they are prudent, efficient the project and reasonable. acquiring land and easements required for the REZ network infrastructure Transgrid developing and overseeing the Transgrid operates and maintains the Environmental Impact Statement existing NSW high voltage transmission processes network. Transgrid will undertake upgrades running a competitive tender process to to its network to connect to the Central-West appoint a Network Operator to design, Orana REZ. build, finance, operate and maintain the REZ network infrastructure.

9 Central-West Orana Renewable Energy Zone 6. The Central-West Orana REZ. Why the Central-West What has happened Central-West Orana REZ declared area Orana region? so far? The Central-West Orana region has a In November 2021, the Central-West strong mix of Energy resources and Orana REZ was formally declared significant investor interest. It also by the Minister for Energy and benefits from lower transmission Environment and EnergyCo was build costs due to its proximity to the appointed as the Infrastructure Planner. existing high voltage network. A community feedback report was prepared by Transgrid following What is planned? consultation carried out in late 2020. and 2021. Stage 1 of the REZ is planned to unlock at least 3,000 megawatts (MW) of new network capacity by the mid-2020s, What are the enough to power million homes.

10 Economic benefits? Following a registration of interest The Central-West Orana REZ will process in 2020, EnergyCo is now deliver over $5 billion of new engaging with developers to coordinate investment in the region and over 3,900. the approach for developing the first jobs during construction. stage of the REZ. EnergyCo will develop plans Where is the REZ? for additional Energy Hubs and The Central-West Orana REZ is transmission lines in the REZ to approximately 20,000 square respond to further development of kilometres centred by Dubbo and Renewable Energy projects. Dunedoo, on the land of the Wiradjuri, Wailwan and Kamilaroi people. Central-West Orana Renewable Energy Zone 7. REZ network infrastructure Energy Hubs Transmission Lines Energy Hubs The three Energy Hubs proposed The Central-West Orana REZ requires for Stage 1 of the Central-West new high voltage transmission lines to Orana REZ will collect electricity transfer Renewable Energy from the from Renewable Energy generators REZ to electricity consumers.