Transcription of Commissioning Checklists 05242010 - DYLAN MECHANICAL
1 DYLAN MECHANICAL CONSTRUCTION SERVICES, INC May 24, 2010 HVAC Commissioning Checklists BT COLLINS HIGH TECH RTS, SACRAMENTO, CA Harold Cullick PE DYLAN MECHANICAL Construction Services, Inc Commission Agent: Harold Cullick, PE May 24, 2010 BT Collins High Tech RTS, Sacramento, CA Page2 TABLE OF CONTENTS HVAC PRE Commissioning Checklists Page Chilled Water Piping system 3 Hot Water Piping system 4 Refrigerant Piping system 5 Ductwork Air handling Unit #1 6 variable Air volume Air handling Unit #1 7 variable Air volume Units 9-30 Air Cooled Condensing Unit and DX Fan Coil 31 Pumps 32-37 Packaged Air Cooled Chiller 38 Hot Water Boiler 39-40 Demarc Room Vent Fan 41 Exhaust Fan Restroom Exhaust 42 HVAC system Controls 43 HVAC FUNCTIONAL PERFORMANCE TEST Commissioning Checklists Pumps
2 44-51 variable Air volume Units 52-54 variable Air volume Air handling Unit #1 55-57 Packaged Air Cooled Chiller 58-59 Air Cooled Condensing Unit and DX Fan Coil 60-61 Hot Water Boiler 62-63 HVAC system Controls 64-65 DYLAN MECHANICAL Construction Services, Inc Commission Agent: Harold Cullick, PE May 24, 2010 BT Collins High Tech RTS, Sacramento, CA Page3 Pre- Commissioning checklist Piping For Chilled Water Piping system Checklist Item QA QC CA Installation a. Piping complete. ___ ___ ___ b. As-built shop drawings submitted. ___ ___ ___ c. Piping flushed and cleaned. ___ ___ ___ d.
3 Strainers cleaned. ___ ___ ___ e. Valves installed as required. ___ ___ ___ f. Piping insulated as required. ___ ___ ___ g. Thermometers and gauges installed as required. ___ ___ ___ h. Verify operation of valves. ___ ___ ___ i. Air vents installed as specified. ___ ___ ___ j. Flexible connectors installed as specified ___ ___ ___ k. Verify that piping has been labeled and valves identified as specified. ___ ___ ___ Testing, Adjusting, and Balancing (TAB) a. Hydrostatic test complete. ___ ___ ___ b. TAB operation complete. ___ ___ ___ DYLAN MECHANICAL Construction Services, Inc Commission Agent: Harold Cullick, PE May 24, 2010 BT Collins High Tech RTS, Sacramento, CA Page4 Pre- Commissioning checklist Piping For Hot Water Piping system Checklist Item QA QC CA Installation a.
4 Piping complete. ___ ___ ___ b. As-built shop drawings submitted. ___ ___ ___ c. Piping flushed and cleaned. ___ ___ ___ d. Strainers cleaned. ___ ___ ___ e. Valves installed as required. ___ ___ ___ f. Piping insulated as required. ___ ___ ___ g. Thermometers and gauges installed as required. ___ ___ ___ h. Verify operation of valves. ___ ___ ___ i. Air vents installed as specified. ___ ___ ___ j. Flexible connectors installed as specified ___ ___ ___ k. Verify that piping has been labeled and valves identified as specified. ___ ___ ___ Testing, Adjusting, and Balancing (TAB) a. Hydrostatic test complete. ___ ___ ___ b.
5 TAB operation complete. ___ ___ ___ DYLAN MECHANICAL Construction Services, Inc Commission Agent: Harold Cullick, PE May 24, 2010 BT Collins High Tech RTS, Sacramento, CA Page5 Pre- Commissioning checklist Piping For Refrigerant Piping system Checklist Item QA QC CA Installation a. Piping complete. ___ ___ ___ b. As-built shop drawings submitted. ___ ___ ___ c. Piping flushed and cleaned. ___ ___ ___ d. Strainers cleaned. ___ ___ ___ e. Valves installed as required. ___ ___ ___ f. Piping insulated as required. ___ ___ ___ g. Thermometers and gauges installed as required. ___ ___ ___ h. Verify operation of valves.
6 ___ ___ ___ i. Air vents installed as specified. ___ ___ ___ j. Flexible connectors installed as specified ___ ___ ___ k. Verify that piping has been labeled and valves identified as specified. ___ ___ ___ Testing, Adjusting, and Balancing (TAB) a. Hydrostatic test complete. ___ ___ ___ b. TAB operation complete. ___ ___ ___ DYLAN MECHANICAL Construction Services, Inc Commission Agent: Harold Cullick, PE May 24, 2010 BT Collins High Tech RTS, Sacramento, CA Page6 Pre- Commissioning Checklist Ductwork For Air Handler: AHU #1 Checklist Item QA QC CA Installation a. Ductwork complete. ___ ___ ___ b.
7 As-built shop drawings submitted. ___ ___ ___ c. Ductwork leak test complete. ___ ___ ___ d. Fire dampers, smoke dampers, and access doors installed as required. ___ ___ ___ e. Ductwork insulated as required. ___ ___ ___ f. Thermometers and gauges installed as required. ___ ___ ___ g. Verify open/closed status of dampers. ___ ___ ___ h. Verify smoke dampers operation. ___ ___ ___ i. Flexible connectors installed as specified ___ ___ ___ Testing, Adjusting, and Balancing (TAB) a. TAB operation complete. ___ ___ ___ DYLAN MECHANICAL Construction Services, Inc Commission Agent: Harold Cullick, PE May 24, 2010 BT Collins High Tech RTS, Sacramento, CA Page7 Pre- Commissioning Checklist - variable volume Air handling Unit For Air handling Unit: AHU #1 Checklist Item QA QC CA Installation a.
8 Vibration isolation devices installed. ___ ___ ___ b. Inspection and access doors are operable and sealed. ___ ___ ___ c. Casing undamaged. ___ ___ ___ d. Insulation undamaged. ___ ___ ___ e. Condensate drainage is unobstructed. (Visually verify drainage by pouring a cup of water into drain pan.) ___ ___ ___ f. Fan belt adjusted. ___ ___ ___ g. Manufacturer's required maintenance clearance provided. ___ ___ ___ Electrical a. Power available to unit disconnect. ___ ___ ___ b. Power available to unit control panel. ___ ___ ___ c. Proper motor rotation verified. ___ ___ ___ d. Verify that power disconnect is located within sight of the unit it controls.
9 ___ ___ ___ e. Power available to humidifier. ___ ___ ___ Coils a. Chilled water piping properly connected. ___ ___ ___ b. Chilled water piping pressure tested. ___ ___ ___ c. Hot water piping properly connected. ___ ___ ___ d. Hot water piping pressure tested. ___ ___ ___ e. Air vents installed on water coils with shutoff valves as specified. ___ ___ ___ f. Any damage to coil fins has been repaired. ___ ___ ___ Heat Recovery Unit a. Controls operable. ___ ___ ___ b. Power connected and rotation check. ___ ___ ___ DYLAN MECHANICAL Construction Services, Inc Commission Agent: Harold Cullick, PE May 24, 2010 BT Collins High Tech RTS, Sacramento, CA Page8 c.
10 Bypass dampers operable. ___ ___ ___ Controls a. Control valves/actuators properly installed. ___ ___ ___ b. Control valves/actuators operable. ___ ___ ___ c. Dampers/actuators properly installed. ___ ___ ___ d. Dampers/actuators operable. ___ ___ ___ e. Verify proper location, installation and calibration of duct static pressure sensor. ___ ___ ___ f. Fan air volume controller operable. ___ ___ ___ g. Air handler controls system operational. ___ ___ ___ Testing, Adjusting, and Balancing (TAB) a. Construction filters removed and replaced. ___ ___ ___ b. TAB report submitted. ___ ___ ___ c. TAB results within +10%/-0% of L/s cfm shown on drawings ___ ___ ___ d.