Construction Methodology Report - NZ Transport Agency

Technical Report 4 – Construction Methodology Report // Page 7 1.2.4. Bridge Construction Each bridge, whether a road crossing or stream/river crossing, will be constructed in the following sequence: 1) Preparation for ground improvements: a. Cut existing ground to level of base of abutment, where required. Temporary retaining