Transcription of Installing and connecting service - Xcel Energy
1 Installing and connecting serviceScope of work, required permits and weather conditions can impact the time frame. Total project duration is typically three to six application and site plansApplication5% of project timeReview and process applicationContact customer to discuss projectDesign50% of project timeSite meetingEngineering review, if necessaryDesign projectObtain easements and/or permits, if necessaryCommunicate costs and provide agreementsPayment10% of project timeSend invoice, if necessarySubmit payment and signed agreementsSchedule project and inform customer of expected start dateScheduling10% of project timeMaintain site ready through constructionObtain inspections from city or countyConstructionConstruction and meter set25% of project timeInspection approval sent toXcel Energy by city or countyMeter is set and yourproject is completeCustomer responsibilityXcel Energy responsibilityShared | 2017 xcel Energy Inc.