Example: dental hygienist

INSTRUCTIONS ON INSTALLATION OPERATION …

INSTRUCTIONS ON. INSTALLATION . OPERATION AND. maintenance FOR. KIRLOSKAR PUMP. TYPE DSM (STANDARD). KIRLOSKAR BROTHERS LIMITED. UDYOG BHAVAN, TILAK ROAD, PUNE - 411 002. KIRLOSKAR BROTHERS LIMITED. Udyog Bhavan, Tilak Road, Pune 411 002 (India). WARRANTY. We warrant that the pump supplied by us is free from defective material and faulty workmanship. This warranty holds good for a period of 12 months from the date of commissioning of the equipment or 18 months from the date of despatch from our factory, whichever is earlier. Our liability in respect of any complaint is limited to replacing part/parts free of charge ex-works or repairs of the defective part/parts only to the extent that such replacement / repairs are attributable to or arise solely from faulty workmanship or defective material.

instructions on installation operation and maintenance for kirloskar pump type dsm (standard) kirloskar brothers limited udyog bhavan, tilak road, pune - 411 002

Tags:

  Operations, Installation, Maintenance, Instructions, Instructions on installation operation, Instructions on installation operation and maintenance for

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of INSTRUCTIONS ON INSTALLATION OPERATION …

1 INSTRUCTIONS ON. INSTALLATION . OPERATION AND. maintenance FOR. KIRLOSKAR PUMP. TYPE DSM (STANDARD). KIRLOSKAR BROTHERS LIMITED. UDYOG BHAVAN, TILAK ROAD, PUNE - 411 002. KIRLOSKAR BROTHERS LIMITED. Udyog Bhavan, Tilak Road, Pune 411 002 (India). WARRANTY. We warrant that the pump supplied by us is free from defective material and faulty workmanship. This warranty holds good for a period of 12 months from the date of commissioning of the equipment or 18 months from the date of despatch from our factory, whichever is earlier. Our liability in respect of any complaint is limited to replacing part/parts free of charge ex-works or repairs of the defective part/parts only to the extent that such replacement / repairs are attributable to or arise solely from faulty workmanship or defective material.

2 The warranty holds good only for the products manufactured by us. KIRLOSKAR BROTHERS LIMITED. IOM/DB/005/01 Issue Date: 25/09/2000. Page: 1/12 Last revision date: CONTENTS. 1. GENERAL. 2. INSTALLATION . 3. OPERATION . 4. TECHNICAL DATA. 5. maintenance . 6. OVERHAULING. 7. SPARE PARTS LIST AND CROSS-SECTIONAL DRAWINGS. PLEASE FURNISH COMPLETE NAMEPLATE DETAILS, NAME OF THE PARTS, PART. NOS. AND MATERIAL OF CONSTRUCTION WHILE ORDERING SPARE PARTS FOR. THE PUMPS. - 2- 1. GENERAL: The booklet covers INSTRUCTIONS for following models of DSM pumps. Type of pump: DSM-1E. DSM-2E.

3 65-DSM, 315M. DSM-3. DSM-3ME. DSM-4RM, RSM-4RN, DSM-4RR. DSM-5B. DSM6-15 , DSM6-30 . DSM-150-45. These are Horizontal split Casing type, two stage pumps. This construction enables to remove the rotating unit without disturbing pipe connections and alignment. Pumps when properly installed and given due attention in OPERATION and maintenance should operate satisfactorily for a long period. When the pump is received, sometime before the actual use of pump, it should be inspected and stored in dry place. The coupling should be rotated once in a month to prevent pitting of bearing surfaces.

4 2 INSTALLATION : For location, preparing foundation, INSTALLATION , alignment, general maintenance , trouble shooting etc., the INSTRUCTIONS given in our publication General INSTRUCTIONS for INSTALLATION , OPERATION & maintenance of Kirloskar Centrifugal Pumps. which is also printed alongwith this booklet must be followed carefully. The sealing connection piping to the pump stuffing box must be made after installing and before commissioning the pump. This piping is supplied only for 65 DSM 315M, DSM-4RM, DSM-4RN, DSM-4RR, DSM-5B, DSM- 6 and DSM 150-45 pumps. For other pumps, sealing connection is integral.

5 Put gland packing and lantern ring, if it is sent separately along with the pump. For DSM-3, 65 DSM 315M also DSM 1E, DSM 2E, DSM 3ME and DSM-4RM, DSM-4RN, DSM-4RR pumps, stuffing boxes are packed with packing before despatch. For balance pumps gland packings and lantern rings are sent separately along with the pumps. 3. OPERATION : Before starting the pump. Check the following: The pump rotates freely by hand. Sealing connection provided is properly tightened and adjusted. Fill in the grease for bearings, if not done earlier. The direction of rotation of motor corresponds to the direction of rotation of the pump.

6 The pump and the suction pipe is fully primed with the liquid. - 3- Valve on the delivery side is closed. Stuffing box packing is properly tightened. The cock for the pressure gauge connection is closed. Starting the pump Start the pump. Let the prime mover pick up its full speed. Open the valve on delivery side slowly. Open the cock for pressure gauge connection. During running the pump The pump is running smooth. The flow of sealing liquid water is uninterrupted. Leakage through stuffing box is normal. There should be leakage is 60 to 80 drops/ min. The bearings are not getting heated up excessively.

7 Head and capacity developed by the pump is as specified. Power consumption is within the limit. Ensure that there is no mechanical friction in the pump. Stop the pump immediately, if any defects are noticed. Do not start the pump unless the defects are rectified. Report immediately to the supplier if it is not possible to rectify the defects. During stopping the pump: Close the valve on delivery side. Stop the motor. If the pump is not required to be operated for a long time, then drain the casing completely. 4. TECHNICAL DATA: Direction of rotation The standard direction of rotation is anticlockwise when viewed from driving end.

8 The pump suitable for clockwise rotation can also be supplied against specific requirements. Rotational speed Normally the pumps are supplied suitable for speed of 1450 rpm. Please contact supplier if the pump is to be used for higher speeds. Bearings The shaft is supplied with antifriction ball bearings at driving end and non- driving end. The details of the bearings are given in the technical data chart. The designations of bearings are as per SKF catalogue. However, equivalent bearings in type, capacity and dimensions are also used. - 4- Lubrication Type of lubricant The bearings are grease lubricated.

9 Quantity of grease Please refer to Technical Data chart. Refilling period After 1000 hours of running. Bearing temperature The permissible bearing temperature rise is 40 C. above ambient temperature. Grades of recommended grease Following grades of grease of their equivalents available in the market are suitable for bearing lubrication. INDIAN OIL - SERVOGEM - 3. CALTEX - STARFAK -3. HINDUSTAN PETROLEUM NATRA- 3 OR LITHON - 3. Stuffing box Stuffing box The stuffing boxes are extra deep to reduce the leakage. Stuffing box sealing Lantern ring provided for sealing purpose is used only in first stage stuffing box.

10 Normally clear cold self liquid only is used for sealing. Grease Sealing/ External sealing can be provided against specific request. Stuffing box packing Champion Style 3316 Graphited Cotton Grease packing is used in the pump as a standard supply. However, stuffing box packing suitable for liquid handled is supplied against specific requirements. For DSM-3, 65 DSM-315 M, DSM 1E, DSM 2E, DSM 3ME, DSM-4RM, DSM-4RN, DSM-4RR pumps the stuffing box packing is sent duly packed in the pump. For other pumps the packing and lantern ring are sent separately alongwith the pump.


Related search queries