Transcription of Meter Pole Requirements - caec.coop
1 Meter pole Requirements for Central Al. Electric Cooperative pole Must be 20' Long, Treated, & 6"x6" Sq. or 6" Round Materials Required Weatherhead-- Recommended but 100 AMP. not Required Service Entrance Cable Sizes Aluminum---#2. Copper--#4. 100 AMP Meter Socket Service Entrance Cable 100 AMP Main Breaker Panel 11/4" Pipe Nipple 16' 2" Conduit Min. Waterproof Connector #4 Solid Bare Copper Ground Wire 5/8"x8' Galvanized or Copper Ground Rod Meter Socket Furnished by CAEC. 200 AMP. Service Entrance Cable Sizes Galvanized Aluminum---#4/0. Pipe Nipple Copper--#2/0. 200 AMP Meter Socket Main Breaker Panel 200 AMP Main Breaker Panel 2" Pipe Nipple Ground Wire 2" Conduit 2' Conduit Min.
2 #4 Solid Bare Copper Ground Wire 5/8"x8' Galvanized or Copper Ground Rod 18" Ground Rod &. Min. Clamp 4' 8' Schedule appointment with Min. staking engineer for location of Meter pole before installing Entrance cable to Mobile Hom