N60 Balla to Claremorris Issue date Road Realignment at 0 12/5/14. Heathlawn Scheme Method Statement: Drainage Ident No. MS-N60-05 Rev 0. Version Issue . Issue date Version Details Revised by 0 12/5/14 First Issue Acceptance / Approvals. Name Signature date Prepared by: M Blackweir 12/5/14. Reviewed by: A McGinley 12/5/14. Accepted by: D Meade 12/5/14. 1. date : 12/05/2014. N60 Balla to Claremorris Issue date Road Realignment at 0 12/5/14. Heathlawn Scheme Method Statement: Drainage Ident No. MS-N60-05 Rev 0. Title: Drainage Location: N60 Balla to Claremorris Road Realignment at Heathlawn Scheme Task at Hand This Method statement outlines the procedure and methodology for the installation of drainage. Timing of Task To be advised subject to Contractor appointment. Supervision of Task Name Contact Number Contracts Manager: TBC. Site Agent: TBC. Foreman: TBC. Site Engineer: TBC. Suitably Qualified Ecologist: TBC. Employees Involved Plant Operators Site Supervisor Pipe Layers General operatives Equipment to be used 20-30 Ton Excavator A20-30 Volvo Dump Trucks 5-9 ton dumpers Specific Training All site personnel shall have FAS Safe Pass certification.

N60 Balla to Claremorris Road Realignment at Heathlawn Scheme Method Statement: Drainage Issue 0 Date 12/5/14 Ident No. MS-N60-05 Rev 0 3 Date: 12/05/2014

Tags:

  Date, Methods, Issue, Testament, Balla, Claremorris, Method statement, Balla to claremorris issue date method statement

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of N60 Balla to Claremorris Issue Date Method Statement: …

1 N60 Balla to Claremorris Issue date Road Realignment at 0 12/5/14. Heathlawn Scheme Method Statement: Drainage Ident No. MS-N60-05 Rev 0. Version Issue . Issue date Version Details Revised by 0 12/5/14 First Issue Acceptance / Approvals. Name Signature date Prepared by: M Blackweir 12/5/14. Reviewed by: A McGinley 12/5/14. Accepted by: D Meade 12/5/14. 1. date : 12/05/2014. N60 Balla to Claremorris Issue date Road Realignment at 0 12/5/14. Heathlawn Scheme Method Statement: Drainage Ident No. MS-N60-05 Rev 0. Title: Drainage Location: N60 Balla to Claremorris Road Realignment at Heathlawn Scheme Task at Hand This Method statement outlines the procedure and methodology for the installation of drainage. Timing of Task To be advised subject to Contractor appointment. Supervision of Task Name Contact Number Contracts Manager: TBC. Site Agent: TBC. Foreman: TBC. Site Engineer: TBC. Suitably Qualified Ecologist: TBC. Employees Involved Plant Operators Site Supervisor Pipe Layers General operatives Equipment to be used 20-30 Ton Excavator A20-30 Volvo Dump Trucks 5-9 ton dumpers Specific Training All site personnel shall have FAS Safe Pass certification.

2 All Excavator & Dumper drivers shall have CSCS certification. CSCS certified representative in underground service location 2. date : 12/05/2014. N60 Balla to Claremorris Issue date Road Realignment at 0 12/5/14. Heathlawn Scheme Method Statement: Drainage Ident No. MS-N60-05 Rev 0. Personal Protective Equipment Safety Gloves Hearing Eye Respiratory Coveralls Other Protection Protection Protection Hi Vis- Vest Hard Hats Boots Yes Where required Yes Where required No Yes Methodology The design location of the proposed drainage is shown on detailed design drawings. The drains shall be installed to NRA details RCD/500/01 filter drains and RCD /500/2 for carrier drains. General All personnel entering the site shall have received a site safety induction and have attended a job toolbox talk. Before any excavations shall commence a permit to excavate shall be issued by the site engineer and all persons involved in the task shall be fully briefed Excavation The location of the proposed drainage will be set out on the ground by marking with spray paint and pegs at pit locations.

3 Where works are along edge of existing roadway traffic light or stop/go system shall be set up to carry out works. A trench will then be excavated between pits using an excavator with material loaded to dump truck. The trench width will vary depending on the size of the pipe. Installation Where drains are being installed a layer of geotextile material shall be placed along the outline of the trench and a layer of filter stone shall then be placed in base of trench to receive pipe work. The pipe work shall then be laid to the correct line and level by using a grade laser. 3. date : 12/05/2014. N60 Balla to Claremorris Issue date Road Realignment at 0 12/5/14. Heathlawn Scheme Method Statement: Drainage Ident No. MS-N60-05 Rev 0. Backfilling of Ducting The remaining stone shall then be placed by six ton dumper up to underside of capping where geotextile shall be turned out under capping layer. The remainder of the drain shall be topped up once surfacing works are carried out up to wearing course level.

4 Installation of layer of Geogrid shall also be carried out at this stage. All chambers on the drain lines shall be constructed with pre-cast concrete catch pits and shall be placed as pipeline proceeds. Petrol Interceptors Excavate a hole with sufficient length and width to accommodate the tank and a min of 300mm surround to a depth for the burial of the unit plus the base slab and haunch. Construct a suitable base. Pour no more than 300mm of depth of water into the unit, avoiding shock loads. For units with more than one chamber, add water to each chamber simultaneously. Do not overfill as units are not designed to hold water whilst unsupported. Backfill to approximately 300mm depth under and to the sides of the tank ensuring good compaction to remove voids. Continue adding backfill, simultaneously keeping the internal water level no more than 200mm above the backfill level at all times, until the backfill is just below the underside of the outlet drain, giving sufficient room to connect the inlet and outlet pipe work.

5 Grass Surface Water Channel The verge shall be filled to top of capping layer with an acceptable fill material. After the Binder course is laid the shape of the verge is formed using an acceptable class 2 fill. In the areas where Narrow Filter Drain has been installed filter stone shall be topped up to top of capping level. This fill material shall be shaped, compacted and top-soiled to depth of 50mm as detailed in the Design. Specific grass mix to be utilised, specification to be developed with grass seed specialist. Swales & Soakaways The area will be cleared and leveled out to allow for the construction of the swale or soakaway. Excavations will be executed in accordance with the design. Once the area of the swale has been shaped & checked it will be backfilled with suitable fill and topsoiled as required. 4. date : 12/05/2014. N60 Balla to Claremorris Issue date Road Realignment at 0 12/5/14. Heathlawn Scheme Method Statement: Drainage Ident No.

6 MS-N60-05 Rev 0. Soakaway excavation shall be backfilled with clean stone and the terram lapped over top of soakway, in accordance with the design and completed to original ground with excavated material/topsoil. 5. date : 12/05/2014. N60 Balla to Claremorris Issue date Road Realignment at 0 12/5/14. Heathlawn Scheme Method Statement: Drainage Ident No. MS-N60-05 Rev 0. Potential Ecological / Environmental Impacts, including impacts on Balla Turlough cSAC and/ or other European sites NIS / EAR: Relevant Extracts: Potential Impacts (in the absence of below Mitigation): Potential Surface & groundwater contamination during construction. Potential decrease in groundwater supply to Turlough during construction. Potential Increase in run-off volumes to Turlough during construction. Pollution from Surface Water run-off during Construction. Mitigation: Construction works carried out in the vicinity of the Turloughs will be monitored by a suitably qualified ecologist.

7 To reduce potential increases in flows into the drainage system and downstream Turloughs during construction, the period of exposure of bare areas and uncontrolled runoff from new hardstanding areas will be limited. Early covering/seeding/planting of exposed surfaces will be undertaken. The grassed surface water channel, interceptor ditch and filter drain with 25m centre outfalls and petrol interceptor (as detailed in 32103901/PDD/Figure 01 &. included in Appendix A) between Ch1000 and Ch 1500 on the south western side of the carriageway, will be constructed and operating prior to excavation of Cutting 1 (Ch 1260 to 1340). These drainage features are adjacent to Balla Turlough SAC, to facilitate the controlled discharge of any intercepted groundwater back into the Turlough habitats in the case of the water being intercepted during excavations. The outfalls to the Turlough will be open during construction only, and closed during operation.

8 Material stockpiles will be kept to a minimum size, covered and located at least 10m from the drainage system and 100m from Turloughs. To prevent contaminated or silt-laden runoff from entering the Turloughs, a range of temporary measures will be implemented, including silt fences, cut-off ditches, silt traps, straw bales, entrapment matting and drainage to vegetated areas. Runoff will be controlled and, if required, directed to settlement ponds or sumps. Any temporary attenuation and treatment facilities will be designed and implemented in accordance with CIRIA C697 (2007). All temporary treatment systems will be regularly inspected and maintained. The extent of construction activities will be controlled to limit vegetation removal and the exposure and/or compaction of soils. Land surrounding the immediate construction area will be fenced off, or otherwise demarcated, to prevent inadvertent intrusion from construction plant.

9 6. date : 12/05/2014. N60 Balla to Claremorris Issue date Road Realignment at 0 12/5/14. Heathlawn Scheme Method Statement: Drainage Ident No. MS-N60-05 Rev 0. The scheme drainage system will be inspected daily, or after storm events, to check for blockages during construction. Construction works will be avoided during prolonged periods of very heavy rainfall adjacent to the Balla Turlough cSAC and Un-named Turlough. No construction plant or construction vehicles to enter the Balla Turlough cSAC. boundary other than where this boundary has already been generally encroached by the existing road. Refuelling of machinery shall be carried out off-site, or when on-site not within 100m of Turlough habitat. All fuels, oils, greases, hydraulic fluids and chemical storage areas will be stored in bunded compounds/areas on impermeable bases at least 10m from the proposed drainage system and 100m from the cSAC and Un-named Turlough.

10 Drip-trays shall be utilised for refueling of machinery, machine servicing, concrete- mixing, etc. No machinery to enter Turlough habitats, no temporary access or haul routes are located in Turlough habitats and no temporary storage areas, plant or other obstacles are located within Turlough habitats. Monitoring of turbidity (suspended solids) levels in Balla Turlough SAC and the Un- named Turlough will be undertaken on a monthly basis for a minimum of 6 months prior to construction and will include monitoring during the winter season when Turlough water levels are most likely to be present. Monitoring will also be undertaken on a weekly basis during construction for turbidity (suspended solids). In the event of suspended solids concentrations that are higher than the 95th %ile of those monitored during the pre-construction monitoring period, a review of the Sediment and Erosion Control measures and plan will be implemented and additional sediment control measures put in place as required.