Example: air traffic controller

Overview of Control Area / Balancing Authority …

1 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSO verview of Control area / Balancing AuthorityFunctional RequirementsMatt WolfManager Operations SupportMay 5, 20102 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSO utline of Presentation Importance of Balancing power production with powerdemand. Overview of Balancing Authorities (BAs). Describe how an EAI Balancing area is projected to look asa stand-alone Balancing Authority . Overview of the cost of establishing a BA. Implications for EAI generation 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSG eneral For purposes of this presentation the following terms areinterchangeable: Control area -(old terminology) Balancing area -(generators, loads, transmission within a metered boundary) Balancing Authority -(responsible entity) This presentation is focused on generation operation aspects of abalancing area .

1 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT – WORK IN PROGRESS Overview of Control Area / Balancing Authority Functional Requirements Matt Wolf

Tags:

  Area, Control, Requirements, Functional, Authority, Balancing, Control area balancing authority, Control area balancing authority functional requirements

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Transcription of Overview of Control Area / Balancing Authority …

1 1 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSO verview of Control area / Balancing AuthorityFunctional RequirementsMatt WolfManager Operations SupportMay 5, 20102 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSO utline of Presentation Importance of Balancing power production with powerdemand. Overview of Balancing Authorities (BAs). Describe how an EAI Balancing area is projected to look asa stand-alone Balancing Authority . Overview of the cost of establishing a BA. Implications for EAI generation 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSG eneral For purposes of this presentation the following terms areinterchangeable: Control area -(old terminology) Balancing area -(generators, loads, transmission within a metered boundary) Balancing Authority -(responsible entity) This presentation is focused on generation operation aspects of abalancing area .

2 It is not addressing the transmission operations aspects of thebalancing area . The information specific to the Entergy Arkansas area presentedbelow is preliminary and based on current historical sources ofinformation and current NERC 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSThe Importance of Balancing Maintain Interconnection Frequency The power grids in the US and Canada are designed tooperate at or near 60 Hz. If there is more generation than demand, frequency goes up. If there is less generation than demand, frequency goesdown. Control the flow of power. Avoided overloading transmission lines. Avoided the inadvertent exchange of 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSM ajor US Interconnections 172,000 MW610,000 MW64,000 MW6 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSNERC Balancing Authorities7 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSE ntergy area Balancing Authorities Over 100 Balancing authoritiesin the US and Canada Largest: 136,000 MW Peak Smallest: 38 MW Peak The load on the Entergytransmission system iscurrently served byapproximately 12 differentbalancing 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSWhat is a Balancing Authority ?

3 NERC definition of Balancing Authority One of the regional functions contributing to the reliable planningand operation of the bulk power system. The Balancing Authorityintegrates resource plans ahead of time, and maintains in real timethe balance of electricity resources and electricity demand. Basically, what does a Balancing Authority do? balances the Control area s net scheduledinterchange with its actual interchange by dispatching generationunits used for the entire Interconnection regulate and stabilize thealternating current 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSE ntergy Arkansas EAI is currently in the Entergy Electric System (EES) Balancing Authority (BA). EAI must provide a BA solution by December 19, 2013.

4 One strategy EAI is considering for post-2013operations would require it to operate in a new BA thatis separate from the EES BA. EAI plans to explore other alternatives for providing BAfunctions over the next year. The schedule and risk of other alternatives such as theSPP consolidated BA will be considered. Regardless of the final decision, EAI s generation planshould provide resources that are capable of serving itsload as if it operated a Balancing 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSE ntergy Electric System BA Configuration TodayCNWYLEPALAGNOMPLNLRBUBAWMUCPUPPAECI EDEOGEAEPCLECOLAFAMISOTVABBASMESOCOSPAEE S BAPLUMDERS11 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSHow the BA arrangement might look in 2013 if EAI Operates its Own BA CNWYLEPALAGNOMPLNLRBUBAWMUCPUPPAECIEDEOG EAEPCLECOLAFAMISOTVABBASMESOCOSPAEAI BAEES (EMI,ELI,EGSL,ETI,ENO)

5 PLUMDERS12 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSKey pointCNWYLEPALAGNOMPLNLRBUBAWMUCPUPPEAI BAEES (EMI,ELI,EGSL,ETI,ENO)Single OATTPLUMDERSIf EAI continues tooperate under the ETROATT, EAItransmission facilitieswould be planned andoperated under theETR OATT and ICTalong with thetransmission facilitiesof the other ETRO perating Companies13 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSSPP OptionLEPALAGNEES (EMI,ELI,EGSL,ETI,ENO)ETR OATTCNWYOMPLNLRBUBAWMUCPUPPEAI BAPLUMDERSIf EAI moves to theSPP OATT, EAItransmission facilitieswould be planned andoperated under theSPP OATT along withthe transmissionfacilities of the otherSPP EAI BA may justbecome a BalancingZone in the SPPC onsolidate OATT14 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSWhat would it take to set up an EAI BA?

6 Preliminary estimates were developed in 2008 and 2009. Conservative assumptions were used in order to bound the cost. Build and equip a new building. Duplicate almost all functions that are currently being conducted by the SystemPlanning and Operations department in Entergy Services, Inc. Buy and install a new generation management system. Upgrade some tie line meters. Results ($ 2009)Startup Cost: $23 MMRun Cost: $14 MM/yearLess ESI Charges: ($ 6) MM/year================================= ===========Net Run Cost: $8 MM/yearEmployees: 64 FTEs The implementation of this plan for EAI self provision of BA functions is expected totake approximately two 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSI mplications for Generation Supply16 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSArea Control Error or ACE Dispatchers have a single real-time measure that tells themhow well they are doing.

7 It incorporates both balance and frequency Control . The goal of a generation dispatcher is to maintain ACE asclose to zero as 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESST hree key NERC Metrics based on ACE Control Performance Standard 1 or CPS1 Uses1 minute averagesof ACE in the calculation. Measure whether a BA is doing their part to help Control frequency over the long-term. Control Performance Standard 2 or CPS 2 Uses10 minute averagesof ACE in the calculation. Measure how well a BA is Balancing over a period of a month. 90% of the ten minute periods in a month must be within a certain tolerance. Disturbance Control Standard or DCS Uses two ACE readings (before and after).

8 Measures how well a BA or a group of BAs respond to sudden loss of supply. Basically, a BA or reserve sharing group has 15 minutes to replace the sudden loss ofsupply. The current standards are not carved in stone and may change over time. Forexample, the Entergy BA is currently participating in a proof-of-concept field trial thatmay lead to a replacement for CPS 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSS ources of Regulation Reserves Normally supplied by generators that have the ability to be dispatched up ordown by a remote computer. (Commonly referred to as automatic generationcontrol or AGC.) Need a flexible fuel supply. The amount a unit can contribute is limited by theramp rateand theroombetween its current dispatch level and its AGC max.

9 Or min. : 500 MWAGC Max: 480 MWAGC Min: 150 MWPMIN: 125 MWExampleGeneratorRegulation Range19 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSS ources of Contingency Reserves Can be supplied by generators that are online (spinning) and have room to move up. Can also be supplied by quick-start generators that can be started and turned up within 15minutes. Also need a flexible fuel supply. The amount generator can contribute is also limited byramp rateand theroombetween itscurrent dispatch level and its maximum capability. Can be supplied by demand response controlled by the system : 500 MWAGC Max: 480 MWAGC Min: 150 MWPMIN: 125 MWContingency Reserves20 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSC ontingency Reserves Today, the Entergy BA participates in the SPP Reserve Sharing Groupwhereby it shares contingency reserves with other member of thegroup.

10 If a large unit trips off-line in the Entergy BA, it receivesassistance from other BAs that are members of the RSG and viceversa. For an EAI BA, providing contingencyreserves to cover its singlelargest contingency would be difficult.(Approximately 1,000 MW in 15 minutes.) Continued participation in a contingency reserve sharing group canreduce the amount of contingency reserves EAI would need to carry byas much as 85%.21 MAY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESSWhat would an EAI BA look like?(based on the current general configuration) Peak load of approximately 6,000 MW. The demand will be mostly comprised of the customers of EAI andAECC. The Entergy OATT would have provision for load imbalance service forother wholesale customers that may be in the BA.


Related search queries