Pocket Guidefor Road Construction and Maintenance

Part 1:Inspector s Job Guide for Highway and Street ConstructionPart 2: road and Highway Maintenance TablesPart 3:Asphalt Paving Inspection Check ListPart 4:Chip Seal Application Check ListPart 5:Concrete Paving Check ListPage 63:Bureau Contact Information PUB 372 (10-13)penndot > municipal servicesPocket Guidefor road Construction and 1 -PART 1 Inspector s Job Guidefor Highway & StreetConstructionPageDuties Before Beginning Inspection.. 2 Safety.. 2 Uniform Color Code.. 2 Wind Chill Equivalent Temperatures .. 3 Plant Mix Bituminous Paving.. 4 Aggregate Course and Truck Scale.. 5 Culvert Pipe Installation.. 6 Storm Sewer Installation .. 7 Grading.. 8 Seeding, Finishing, .. 9 Structures.. 10 Geotextiles.. 13 Bituminous Surface Treatment.. 14 IntroductionThese guides are intended to cover the very basicduties of inspection by reference to key guides must be supplemented by reference tocontract documents specifications, special provi-sions, instructional manuals, and guidance by theproject Before BeginningInspectionPA One Call, 1-800-242-1776, www.

Road Construction and Maintenance www.dot.state.pa.us - 1 - PART 1 Inspector’s Job Guide for Highway & Street Construction ... control dust and aid in obtaining compaction, and rolling to obtain density. 6. Obtain compaction of each lift before placing the ... Road and Highway

Tags:

  States, Road, Construction, Road construction

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of Pocket Guidefor Road Construction and Maintenance

1 Part 1:Inspector s Job Guide for Highway and Street ConstructionPart 2: road and Highway Maintenance TablesPart 3:Asphalt Paving Inspection Check ListPart 4:Chip Seal Application Check ListPart 5:Concrete Paving Check ListPage 63:Bureau Contact Information PUB 372 (10-13)penndot > municipal servicesPocket Guidefor road Construction and 1 -PART 1 Inspector s Job Guidefor Highway & StreetConstructionPageDuties Before Beginning Inspection.. 2 Safety.. 2 Uniform Color Code.. 2 Wind Chill Equivalent Temperatures .. 3 Plant Mix Bituminous Paving.. 4 Aggregate Course and Truck Scale.. 5 Culvert Pipe Installation.. 6 Storm Sewer Installation .. 7 Grading.. 8 Seeding, Finishing, .. 9 Structures.. 10 Geotextiles.. 13 Bituminous Surface Treatment.. 14 IntroductionThese guides are intended to cover the very basicduties of inspection by reference to key guides must be supplemented by reference tocontract documents specifications, special provi-sions, instructional manuals, and guidance by theproject Before BeginningInspectionPA One Call, 1-800-242-1776, www.

2 Plans, special provisions, Constructionand Materials Manual, and specifications thatapply to your assigned duties. Are all requiredpermits obtained and copies onsite? PA Onecall notified? E&S controls in place? your responsibility and authority withthe project engineer who has day-to-day the format and required content of yourinspection required testing procedure and the QC documents. notification, changes, corrections,delays, rejections, tolerances, and checks withthe project Ask Questions!If you are not 100% sure ofyour duties, go over them again with the all operating procedures to assure that activ-ities are performed in the safest manner. Safety iseveryone s responsibility! When performing dutiesin the presence of traffic, review necessary trafficcontrol Color Code(For Underground Utility Markings)American Public Works AssociationWhite:Proposed :Temporary Survey :Electric Power Lines, Cables, Conduit andLighting :Gas, Oil, Steam, Petroleum or :Communication, Alarm or Signal Lines, Cableor :Potable :Reclaimed Water, Irrigation and Slurry.

3 Sewers and Drain 2-- 3-Wind Chill EquivalentTemperatureWind Velocity ( )4510 15 20 25 30 35 40 4545 45 43 34 29 26 23 21 20 19 1840 40 37 28 23 19 16 13 12 11 1035 35 32 22 16 128643230 30 27 1694-1 -2 -4 -5 -625 25 22 10 2 -3 -7 -10 -12 -13 -1420 20 16 3 -5 -10 -15 -18 -20 -21 -2215 15 11 -3 -11 -17 -22 -25 -27 -29 -3010 10 6 -9 -19 -24 -29 -33 -35 -37 -38550-15 -25 -31 -36 -41 -43 -45 -4600-5 -22 -31 -39 -44 -49 -52 -53 -54-5 -5 -10 -27 -38 -46 -51 -56 -58 -60 -62-10 -10 -15 -34 -45 -53 -59 -64 -67 -69 -70-15 -15 -21 -40 -51 -60 -66 -71-74 -76 -78-20 -20 -25 -46 -58 -67-74 -79 -82 -84 -85-25 -25 -31 -52 -65-74 -81 -86 -89 -92 -93-30 -30 -36 -58 -72-81 -88 -93 -97 -100 -102-35 -35 -42 -64-78 -88 -96 -101 -105 -107 -109-40 -40 -47 -71-85 -95 -103 -109 -113 -115 -117-45 -45 -52-77 -92 -103 -110 -116 -120 -123 -125 INCREASING GREATDANGERDANGERF lesh may freeze Flesh may freeze within 1 30 Bulb Temperature ( F)

4 - 4-Plant Mix Bituminous Paving1. Check equipment for specification compliance, anddiscuss paving and rolling sequence with all QC documents. Is a Pre-Pave meetingrequired?2. Check that the surface is smooth, firmly compacted and atcorrect cross section, grade, and alignment. Existingbituminous and concrete bases are to be clean and free ofloose material, and tacked. Excessive joint and cracksealing material should be removed. Pre-level all Ensure that truck boxes are clean to prevent build-up (donot use kerosene, diesel fuel or fuel oil). Loads must Check temperature frequently and be aware of theacceptable temperature range of Insure that scale inspector verifies and initials eachdelivery ticket, unless automated printer is Check that paving inspector collects, checks, and initialseach delivery Observe loads for proper size and shape.

5 Materialsshould have consistent color, complete aggregate coating,and a minimum of Check that paver maintains a speed which will minimizestop and start Check that paver maintains correct line, grade and crossslope, and has the automatic controls adjusted tominimize screed bounce or drift. 10. Check mat width, thickness, and Check that Construction joints are tight and flush withadjacent Insure that mat has a uniform appearance and is free oflongitudinal Check that rolling is as continuous as possible and atproper speed with drive wheel nearest paver. Discussrolling pattern with project engineer, paving foreman Cease vibratory rolling when checking or cracking occurs,or at a specified minimum Finish rolling to remove all marks and Monitor density tests to ensure adequate Check surface with a rolling straightedge for ride Daily records include: workers, hours, equipment, lengthspaved, course, depth, width, tonnage, yield, weather,temperatures, and problems 5-Aggregate Courseand Truck to placing base, verify that grade is true tocorrect cross-section and alignment.

6 Check thatsubgrade or subbase is free of ruts, large stones,and excess Observe loads for proper size and Generally, begin placement near the source of sup-ply. Lifts should not exceed 8 of thickness unlessotherwise approved by the Check depth and yield (tons per linear feet) toassure uniform Monitor base preparation needs: mixing by graderto eliminate segregation and hauling ruts, water tocontrol dust and aid in obtaining compaction, androlling to obtain Obtain compaction of each lift before placing thenext Collect, check, and initial the weigh ticket for eachload as it arrives at the Daily records include: workers, hours, equipment,location, lift thickness, quantity, and 6-Culvert Pipe Installation1. Review plans and specifications for culvertinstallation. PA One call complete?2. Verify size, type, and length of pipe versus certi-fication Check pipe for approval stamp and inspect forany subsequent damage or Review control stakes and adjacent terrain forproper Check trench for proper width and shoringneeds, follow OSHA safety Check bed for proper grade and shape of bed with Place tongue end of concrete pipe in direction offlow and lap in metal pipe so that flow is Check that concrete pipe joints are snug and liftholes plugged.

7 Banding for corrugated metalpipe shall be installed in accordance with Determine pay length while installing pipe bymultiplying the number of sections by their nom-inal Ensure that backfill material is free of large rocksand Check that backfill is placed in accordance withspecifications or as directed by When complete, verify that pipe is in properalignment and Daily records include: trenching, placement andbackfilling information, item, pay length, loca-tion, heat numbers, crew, equipment, and prob-lems 7-Storm SewerInstallation1. Review items 1 thru 6, 9 & 10 of Culvert Pipe and the guidelines Check for potential conflicts with existing andproposed underground Check that excavation and sewer installationbegins at the outlet of proposed sewer and pro-ceeds upstream. If existing underground utilitiesare in the area, the trench excavation shouldnormally be complete between drainage struc-tures before beginning installation of sewer Ensure that joints and liftholes are sealed inaccordance with the Check invert elevation and alignment of eachsection of pipe as installed from string line orlaser Check that backfill material is granular backfill unless otherwise indicated in the Generally, determine pay length by measure-ment of storm sewer in place prior to or duringbackfilling.

8 Adjust for end cut-offs after struc-tures are in Insure that bricks and concrete blocks are wet-ted before Check that mortar is 3 parts sand and 1 partcement Check contract requirements for mortar, back-plastering, and Check that castings sit on a full bed of mortar orare poured Check contract requirements for cleaning Daily records include: trenching, placement andbackfilling information, item, pay length, loca-tion, structure numbers, crew, equipment, andproblems 8-Grading1. Review grading and erosion and control Inspect clearing and grubbing limits, and measurequantities. Check contract for disposal of firewoodand Monitor salvaging of topsoil to ensure properdrainage and erosion Insure unstable material below subgrade is undercutand measured for final pay. Check with project engi-neer to establish the need for Ensure that all rock at subgrade elevation is under-cut 6.

9 6. Check that masonry walls, floors, and foundations;and pavement near subgrade elevation is brokendown and removed to the depth specified below Intermix large stones, rock, and broken concrete withsoil to prevent Ensure that the embankment is placed and com-pacted full width in layers normally not exceeding 8 .9. Check for compaction and stability by visual obser-vation of subgrade and the embankment under earthmoving equipment or per the contract Route hauling and leveling equipment over the fullwidth of the If required, enlist water and special Consideration must be given to continued drainageand erosion control throughout Check that culverts are bridged , as per specifica-tions, with sufficient embankment to prevent damagefrom hauling Check with engineer prior to permitting hauling Daily records include: location, type of work, work-ers, hours, equipment, quantities, soil types, layerthickness, relative moisture, degree of compaction,information on rutting or displacement, weather con-ditions and problems 9-Seeding, Finishing, Ensure the topsoil is placed on cut and fill slopesto the depth and locations designated in Check that topsoil is relatively free of clumps,rocks, roots, etc.

10 , and is prepared suitably Check composition of delivered fertilizer andseed, and verify that requirements of contractare Check that fertilizer and seed is applied at a ratedependent upon composition of supplied Check that fertilizer is applied according to man-ufacturer s Ensure that seed is applied according to Count, record, and dispose of empty fertilizerand seed bags daily. Collect all weigh and Check that mulching, where specified, followsseeding within specified times. Verify that mulchmaterial and application methods meet Ensure that areas to be sodded are properlyprepared. Sod shall consist of healthy, Check that all sod is keyed in, rolled, or lightlytamped. If placed in ditches or on steep slopes,it shall be pegged. Water as necessary for 10days or as Check erosion mat for conformance with speci-fication. Place as required, staple in full contact,bury all edges, and restore disturbed Monitor final finishing including: removal of all lit-ter and debris, repair of damaged areas, andcleaning of all drainage Daily records include: location, type of work,estimated or final quantities, and material 10-StructuresGENERAL1.