Example: bachelor of science

Project Descriptions and Justifications - …

March 6, 2018 RE: Hillsborough County Aviation Authority s public notice prior to submitting a new application to impose and use a passenger facility charge (PFC) at Tampa International Airport (TPA); PFC Application No. 18-11-C-00-TPA The Hillsborough County Aviation Authority (Authority) is posting this public notice as part of the PFC Application process under Title 14 Code of Federal Regulations (CFR) The Authority will be accepting public comments on the proposed new PFC Application through April 5, 2018.

Red Rental Car Garage Demolition The existing RRCG is a post tensioned structure situated on the north side of the Terminal. The structure is bounded by George Bean Parkway to the north, Red Arrivals

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of Project Descriptions and Justifications - …

1 March 6, 2018 RE: Hillsborough County Aviation Authority s public notice prior to submitting a new application to impose and use a passenger facility charge (PFC) at Tampa International Airport (TPA); PFC Application No. 18-11-C-00-TPA The Hillsborough County Aviation Authority (Authority) is posting this public notice as part of the PFC Application process under Title 14 Code of Federal Regulations (CFR) The Authority will be accepting public comments on the proposed new PFC Application through April 5, 2018.

2 As part of the process, the following information is being provided: (1) Project Descriptions and brief Project Justifications , (2) PFC collection level, estimated PFC revenue, proposed charge effective date, estimated PFC charge expiration date, and comingling with PFC No. 15-10-C-00-TPA, and (3) Authority point of contact. 1) Project Descriptions and Justifications a) Demolition of the Red Side Garage Project Amount (excluding PFC Bond Financing & Interest Costs): $10,631,000 PFC PAYGO: $0 PFC Bond Capital: $6,408,673 PFC Bond Financing & Interest: $9,886,412 Federal Grants: $0 State Grants: $0 Local Funds: $4,222,327 PFC Collection Level: $ Start Date: September 2018 End Date: May 2019 Description.

3 This Project consists of the demolition of two existing facilities which are in direct conflict with future Phase 2 and Phase 3 expansion projects. Those projects include the construction of an additional Red Side Curbside and an APM for the future Airside D. Additionally, the existing facilities conflict the future identified site for the FAA Air Traffic Control Tower (ATCT) and the Terminal Radar Approach Control (TRACON) building when the ATCT and TRACON become unserviceable as determined by the FAA.

4 The facilities to be demolished include the Red Side Rental Car Garage (RRCG) as well as the remaining segment of the old Airside D Automatic People Mover (APM) guideway infrastructure. Per the 2012 Master Plan Update, the existing facilities are incompatible with future airport use. Red Rental Car Garage Demolition The existing RRCG is a post tensioned structure situated on the north side of the Terminal. The structure is bounded by George Bean Parkway to the north, Red Arrivals Drive on the west and south and the TPA Service Road to the east.

5 Demolition of the RRCG includes the following: a. Demolition of seven levels and three levels. of Post Tensioned parking structure of the RRCG on the east and west side, respectively, of the old Airside D Guideway b. Demolition of the elevated exit ramp over the George Bean Parkway c. Demolition of the concrete and steel canopy between the RRCG and Administration Service Building d. Demolition of the pile caps and approximately top eight feet of piles for the RRCG to reduce the potential impact caused by the existing piles to future utilities e.

6 Fill, regrade and sod to a level site Airside D Automatic People Mover (APM) Guideway (A/S D APM Guideway) Demolition The existing A/S D APM Guideway consists of a cast-in-place concrete foundations and pier structure that support precast decks that span between the piers. The A/S D APM Guideway runs from the Main Terminal Building through the RRCG and ends at the Airside D Hardstand. Demolition of the A/S D APM Guideway includes the following: a. Demolition of 800 linear feet of steel and precast concrete guideway bridge b.

7 Demolition of 12 concrete guideway bridge supports c. Demolition of pile caps and top 8 feet of piles. d. Fill, regrade and sod to a level site Project Need/Justification. The demolition of these facilities is necessary because they are directly in conflict with future expansion including the construction of an additional Red Side Curbside, an APM for the future Airside D and the future identified site for the FAA Air Traffic Control Tower (ATCT) and the Terminal Radar Approach Control (TRACON) building.

8 The RRCG was constructed in 2005 to allow customer pick-up of rental cars on the Red Side of the Main Terminal. The garage has a capacity of 696 vehicles and sits on approximately 2 acres of land and includes seven levels on the east side of the A/S D APM Guideway and three levels on the west side of the A/S D APM Guideway. With the construction of the new Consolidated Rental Car Facility (ConRAC) in the South Terminal Support Area (STSA) which opened on February 14th, 2018, the existing garage is not needed and is incompatible with the 2012 Master Plan Update s future terminal area development.

9 Additionally, the existing segment of the old A/S D APM Guideway is also deemed incompatible for future use as the 2012 Master Plan Update has identified a new alignment for the future Airside D APM. In 2016, the Authority revalidated the 2012 Master Plan Update. Since March 2012, TPA has experienced 85% peak hour growth which has increased congestion on the airport s curbsides. The current curbsides can handle approximately 20 million annual passengers (MAP) at a Service Level C which is an average level of service.

10 Based on the current passenger projections, the existing curbsides will need to be expanded to be able to handle the projected traffic levels of up to 34 million annual passengers. In addition, this Project is also an enabling Project for the future addition of a new Airside D. Once a new Airside D is constructed it will be connected to the Main Terminal facility via an Automated People Mover system and the existing Red Side Garage is in the way of that conveyance. b) Design and Construct Central Energy Plant Replacement Project Amount (excluding PFC Bond Financing & Interest Costs): $109,992,000 PFC PAYGO: $0 PFC Bond Capital: $32,828,000 PFC Bond Financing & Interest: $50,642,484 Federal Grants: $0 State Grants: $0 Local Funds: $77,164,000 PFC Collection Level: $ Start Date: May 2019 End Date: May 2021 Description.


Related search queries