PROJECT PROFILE BWR Main Condenser Retubing

PROJECT Scope Complete Retubing of BWR main Condenser during refueling outage. In addition to Condenser Retubing , Williams performed all scaffolding work and built a conveyor system to support transport of materials into work DescriptionWilliams managed the overall PROJECT execution including materials, equipment, tools, labor, and supervision. The PROJECT included: Replacement of 36,860 admiralty brass and titanium main Condenser tubes and Retubing Rigging, removal and replacement of the four inlet waterboxes including new inlet circulating water expansion joints Removal and reinstallation of electrical, mechanical and structural interferences to facilitate tube replacement Repair of stem-side impingement protection and baffles; installation of tub

Project Scope Complete retubing of BWR Main Condenser during refueling outage. In addition to condenser retubing, Williams performed all scaffolding

Tags:

  Main, Condensers, Bwr main condenser retubing, Retubing, Bwr main condenser, Condenser retubing

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of PROJECT PROFILE BWR Main Condenser Retubing

1 PROJECT Scope Complete Retubing of BWR main Condenser during refueling outage. In addition to Condenser Retubing , Williams performed all scaffolding work and built a conveyor system to support transport of materials into work DescriptionWilliams managed the overall PROJECT execution including materials, equipment, tools, labor, and supervision. The PROJECT included: Replacement of 36,860 admiralty brass and titanium main Condenser tubes and Retubing Rigging, removal and replacement of the four inlet waterboxes including new inlet circulating water expansion joints Removal and reinstallation of electrical, mechanical and structural interferences to facilitate tube replacement Repair of stem-side impingement protection and baffles.

2 Installation of tube bundle protection items Fabrication of rail transportation system for tubesChallenges 10 x 10 Condenser bay egress was limited to access way. Large increase in quantity of stakes required. Once PROJECT commenced, an additional 42,000 stakes needed attention for a total of 72,000 stakes. Oversized hole issues. Tube sheets were found in bad condition. Large volume of scope increase. Contamination issues. Limited RP HighlightsWilliams was able to complete the PROJECT in just 39 days 5 days ahead of schedule by implementing innovative scheduling, execution and activity re-sequencing.

3 The record for similar scope projects prior to this outage was 56 days. Throughout the course of the PROJECT , Williams faced changes to the scope and plant delays which delayed the schedule by an additional 50 hours. Using Acumen Risk schedule modeling, Williams was able to overcome these challenges. We developed 3-point estimates for every critical path activity, established a risk register and tied the risks to the activities they affected before running the analysis. Using this technique is very unique to this industry and was a major contributor to our predictability.

4 PROJECT PROFILE100 Crescent Centre Parkway, Suite 1240 | Tucker, GA 30084 USA | office: | BWR main Condenser RetubingClient: EntergyLocation: FitzPatrick Nuclear Power PlantProject Duration: October 2014 (39 days) PROJECT Value: approx. $20M Contract Method: Firm Fixed PriceFish screen replacementTube sheet on the inlet sideConveyor build by Williams going into LSA box