HIRE CHARGES. ALL RATES IN THIS FILE ARE LINKED WITH THE RATES IN BASIC DATA FILE TO THE. EXTENT THEY ARE RELEVANT. IN THE DIALOG BOX THAT APPEARS ON THE MONITOR. ON OPENING THIS FILE CLICK ' YES' AND SAVE THE FILE. CHANGES MADE IN THE. BASIC DATA FILE GET INCORPORATED IN THIS FILE AUTOMATICALLY. ALL DATA IN THIS FILE IS PROTECTED BY PASS WORD. GOVERNMENT OF KARNATAKA. WATER RESOURCES DEPARTMENT. SCHEDULE OF RATES . DATA FOR COMPUTATION OF. HIRE CHARGES. FOR. MACHINERY AND EQUIPMENTS. FOR THE YEAR : 2003-2004. 33. HIRE CHARGES. DATA PREPARED BY SCHEDULE OF RATES COMMITTEE.

hire charges all rates in this file are linked with the rates in basic data file to the extent they are relevant. in the dialog box that appears on the monitor

Tags:

  Schedule, Rates, Hier, Schedule of rates

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Transcription of SCHEDULE OF RATES - Kar

1 HIRE CHARGES. ALL RATES IN THIS FILE ARE LINKED WITH THE RATES IN BASIC DATA FILE TO THE. EXTENT THEY ARE RELEVANT. IN THE DIALOG BOX THAT APPEARS ON THE MONITOR. ON OPENING THIS FILE CLICK ' YES' AND SAVE THE FILE. CHANGES MADE IN THE. BASIC DATA FILE GET INCORPORATED IN THIS FILE AUTOMATICALLY. ALL DATA IN THIS FILE IS PROTECTED BY PASS WORD. GOVERNMENT OF KARNATAKA. WATER RESOURCES DEPARTMENT. SCHEDULE OF RATES . DATA FOR COMPUTATION OF. HIRE CHARGES. FOR. MACHINERY AND EQUIPMENTS. FOR THE YEAR : 2003-2004. 33. HIRE CHARGES. DATA PREPARED BY SCHEDULE OF RATES COMMITTEE.

2 JUNE, 2003. 43. HIRE CHARGES. HIRE CHARGES OF MACHINERY. FOR THE YEAR : 2003-2004. REFERENCE DATA ON CAPITAL COST & WAGES OF CREW. Sl Description of machinery Capital Wages of Wages of No. cost in Rs Operator Helper C Rs. / Day Rs. / Day 1 Agitator car / Transit mixer 2 cum 1380000 Tyres and tubes 6 sets 58800 --- --- 2 Air compressor 5 cmm ( electric ) 370000 3 Air compressor 7 cmm ( diesel ) 510000 4 Air compressor 7 cmm ( electric ) 472000 5 Air compressor cmm ( diesel ) 618000 6 Air compressor cmm ( electric ) 579000 7 Air compressor 15 cmm ( electric ) 875000 8 Angle Dozer 90 hp 3300000 9 Batching plant cum 895000 10 Batching plant 2 x cum 2550000 11 Batching plant 2 x cum 3850000 12 Bending machine 3000 x 12 mm 393000 13 Concrete bucket cum 25000 --- --- 14 Concrete hand mixer 45 / 30 ltr 22500 --- --- 15 Concrete mixer 300 / 200 ( diesel ) 91000 16 Concrete mixer 300 / 200 ltr ( electric ) 88000 17 Concrete mixer 600 / 400 ( diesel ) 183000 18 Concrete mixer 600 / 400 ltr ( electric )

3 177000 19 Concrete paver 100 sqm / hr 1500000 20 Convey mucker 2620000 Tyres and tubes 6 sets 58800 --- --- 21 Core drilling machine 650000 22 Diesel generating set 30 KVA 350000 23 Diesel generating set 50 KVA 550000 24 Diesel Loco 45 hp 1025000 25 Dewatering pump 5 hp ( diesel ) 20800 --- 26 Dewatering pump 5 hp ( electric ) 18500 --- 27 Dewatering pump 10 hp ( diesel ) 35000 --- 28 Dewatering pump 10 hp ( electric ) 32300 --- 29 Dewatering pump 20 hp ( diesel ) 84000 --- 30 Dewatering pump 20 hp ( electric ) 73000 --- 31 Drifter 550000 32 Drilling jumbo 800000 Tyres and tubes 6 sets 58800 --- --- 33 Dumper cum 837000 Tyres and tubes 6 sets 67620 --- --- 34 Geophysical Electric resistivity meter 250000 --- --- 35 Grouting pump 65000 36 Guniting / sand blast equipment 172000 53.

4 HIRE CHARGES. 37 Ice plant & accessories 30 t / day 1380000 38 Jack hammer 36100 39 Needle vibrator 40 mm ( petrol ) 15800 40 Needle vibrator 40 mm ( electric ) 14800 41 Needle vibrator 60 mm ( petrol ) 17800 42 Needle vibrator 60 mm ( electric ) 16700 43 Planing machine 4 m stroke 450000 44 Plate shearing machine upto 12 mm 485000 45 Pneumatic placer cum 350000 --- 46 Pneumatic tamper 37500 47 Pug cutting machine 32000 --- --- 48 Pusher leg 25000 --- --- 49 Road roller diesel 10 t 738000 50 Shovel cum 75 hp 2025000 51 Shovel cum 110 hp 3350000 52 Stationery derric crane 388000 --- --- 53 Tipper 5 cum 792000 Tyres and tubes 6 sets 58800 --- --- 54 Tipping tub cum 90000 --- --- 55 Tower crane 5 tonne 6583000 56 Transformer 250 KVA 160000 --- --- 57 Truck 10 t 787500 Tyres and tubes 6 sets 58800 --- --- 58

5 Truck mounted derric crane 5 t 892000 Tyres and tubes 6 sets 58800 --- --- 59 Upright drilling machine 37700 --- 60 Ventilation fan 20 hp 107000 --- 61 Vibratory pad foot roller 8 t 1886000 62 Waggon drill 580000 63 Water tanker 8000 ltr 780000 Tyres and tubes 6 sets 58800 --- --- 64 Welding set 28900 --- --- 65 Winch 35 hp ( electric ) 225000 OTHER DATA FOR WORKING OUT HIRE CHARGES. Rate of interest : % per annum 11. Road tax : per annum. Rs: 8000. Insurance : % per annum. 1. Diesel : per litre Rs: Petrol : per litre Rs: 36. Lubricating oil : per litre Rs: 90. Tyres & tubes for lorry : per set Rs: 9800.

6 Electric energy (Category:HT-2B) : per kwhr Rs: Salvage value ( as percentage of capital cost ) : % 10. 63. HIRE CHARGES. HIRE / FUEL / CREW CHARGES OF MACHINERY. FOR THE YEAR : 2003-2004. Sl Description of machinery Unit Hire Fuel Crew No. charge charge Charge in Rs in Rs in Rs. 1 2 3 4 5 6. 1 Agitator car / Transit mixer 2 cum ( including tyres ) Hour 2 Air compressor 5 cmm ( electric ) Hour 3 Air compressor 7 cmm ( diesel ) Hour 4 Air compressor 7 cmm ( electric ) Hour 5 Air compressor cmm ( diesel ) Hour 6 Air compressor cmm ( electric ) Hour 7 Air compressor 15 cmm ( electric ) Hour 8 Angle Dozer 90 hp Hour 9 Batching plant cum Hour 10 Batching plant 2 x cum Hour 11 Batching plant 2 x cum Hour 12 Bending machine Hour 13 Concrete bucket cum Hour --- 14 Concrete hand mixer 45 / 30 ltr Hour --- 15 Concrete mixer 300 / 200 ltr ( diesel )

7 Hour 16 Concrete mixer 300 / 200 ltr ( electric ) Hour 17 Concrete mixer 600 / 400 ltr ( diesel ) Hour 18 Concrete mixer 600 / 400 ltr ( electric ) Hour 19 Concrete paver 100 sqm / hr Hour 20 Convey mucker ( including tyres ) Hour 21 Core drilling machine Hour 22 Diesel generating set 30 KVA Hour 23 Diesel generating set 50 KVA Hour 24 Diesel loco 45 hp Hour 25 Dewatering pump 5 hp ( diesel ) Hour 26 Dewatering pump 5 hp ( electric ) Hour 27 Dewatering pump 10 hp ( diesel ) Hour 28 Dewatering pump 10 hp ( electric ) Hour 29 Dewatering pump 20 hp ( diesel ) Hour 30 Dewatering pump 20 hp ( electric ) Hour 31 Drifter Hour 32 Drilling jumbo ( including tyres ) Hour 33 Dumper cum ( including tyres ) Hour 34 Geophysical Electric resistivity meter Hour --- 35 Grouting pump Hour 36 Guniting / sand blasting equipment Hour 37 Ice plant with accessories 30 t / day Hour 38 Jack hammer Hour 39 Needle vibrator 40 mm ( petrol ) Hour 40 Needle vibrator 40 mm ( electric ) Hour 41 Needle vibrator 60 mm ( petrol ) Hour 42 Needle vibrator 60 mm ( electric )

8 Hour 43 Planing machine 4 m stroke Hour 44 Plate shearing machine upto 12 mm Hour 45 Pneumatic placer cum Hour 46 Pneumatic tamper Hour 73. HIRE CHARGES. HIRE / FUEL / CREW CHARGES OF MACHINERY ( CONTD ). Sl Description of machinery Unit Hire Fuel Crew No. charge charge Charge in Rs in Rs in Rs. 1 2 3 4 5 6. 47 Pug cutting machine Hour --- 48 Pusher leg Hour --- 49 Road roller diesel 10 t Hour 50 Shovel cum 75 hp Hour 51 Shovel cum 110 hp Hour 52 Stationery derric crane 5 t Hour --- 53 Tipper 5 cum ( including tyres ) Hour 54 Tipping tub cum Hour --- 55 Tower crane 5 tonne Hour 56 Transformer 250 KVA Month --- --- 57 Truck 10 t ( including tyres ) Hour 58 Truck mounted derric crane 5 t ( including tyres ) Hour 59 Upright drilling machine Hour 60 Ventilation fan 20 hp ( twin )

9 Hour 61 Vibratory pad foot roller 8 t Hour 62 Waggon drill Hour 63 Water tanker 8000 ltr ( including tyres ) Hour 64 Welding set Hour --- 65 Winch 35 hp ( electric ) Hour Notes: 1. Hire charges include depriciation, interest, repair charge, miscellaneous charge, insurance, road tax wherever applicable. 2. Fuel charges include cost of diesel / petrol / electric power as applicable and oil / lubricants and other miscellaneous charges. 3. Crew charges include wages of operator and helper on hourly basis. 4. For batching plants and mechanical concrete paver 2 Operators and 2 Helpers are considered for working out hourly Crew charges.

10 5. Hire / Fuel / Crew charges are exclusive of provisions towards small T & P, profit, overheads and hidden cost on operating crew. Profit shall be considered only on fuel charges and operating crew charges. 83. HIRE CHARGES. STANDARD DATA FOR MACHINERY. ( FOR WORKING OUT HIRE CHARGES ). Note:: Life and repair charges are as per CWC guide lines except for truck, tipper and road roller. For truck, tipper and road roller the life is considered as per the prevailing norms in the Water Resources Department and repair charges are as per CWC guide lines. Sl Description of machinery Life in Life in Repair Type Duty No.