Example: marketing

SQAR SUPPLEMENT FOR NONDESTRUCTIVE TEST …

Only the online system has the current version. Verify hard copy against online system before use. Aerospace Systems SQAR SUPPLEMENT FOR NONDESTRUCTIVE TEST (NDT)/ TECHNIQUE SUBMITTAL SQARSUP-0120 Revision Date: 7/22/13 Joseph F. Jackson Director, Supplier Quality Northrop Grumman Aerospace Systems Only the online system has the current version. Verify hard copy against online system before use. 2 Revision Record Revision Date Revision Date Revision Date New 11/21/05 H 08/14/08 A 12/13/05 I 09/24/09 B 02/09/06 J 4/4/12 C 02/27/06 - 8/1/12 D 03/21/06 - 8/30/12 E 05/09/06 7/22/13 F 12/08/06 G 11/15/08 Note: Revisions Are in Blue font. Primary Change Summary Changed to new prefix for a SUPPLEMENT to SQAR and new number Guide removed Only the online system has the current version. Verify hard copy against online system before use. 3 Table of Contents Section Title Page General 4 Scope 4 Table 1 NDT Submittal Requirement by Program 5, 6, 7 Only the online system has the current version.

Only the online system has the current version. Verify hard copy against online system before use. Aerospace Systems SQAR SUPPLEMENT FOR NONDESTRUCTIVE TEST (NDT)/

Tags:

  Supplement, Tests, Nondestructive, Asqr, Sqar supplement for nondestructive test

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Transcription of SQAR SUPPLEMENT FOR NONDESTRUCTIVE TEST …

1 Only the online system has the current version. Verify hard copy against online system before use. Aerospace Systems SQAR SUPPLEMENT FOR NONDESTRUCTIVE TEST (NDT)/ TECHNIQUE SUBMITTAL SQARSUP-0120 Revision Date: 7/22/13 Joseph F. Jackson Director, Supplier Quality Northrop Grumman Aerospace Systems Only the online system has the current version. Verify hard copy against online system before use. 2 Revision Record Revision Date Revision Date Revision Date New 11/21/05 H 08/14/08 A 12/13/05 I 09/24/09 B 02/09/06 J 4/4/12 C 02/27/06 - 8/1/12 D 03/21/06 - 8/30/12 E 05/09/06 7/22/13 F 12/08/06 G 11/15/08 Note: Revisions Are in Blue font. Primary Change Summary Changed to new prefix for a SUPPLEMENT to SQAR and new number Guide removed Only the online system has the current version. Verify hard copy against online system before use. 3 Table of Contents Section Title Page General 4 Scope 4 Table 1 NDT Submittal Requirement by Program 5, 6, 7 Only the online system has the current version.

2 Verify hard copy against online system before use. 4 NONDESTRUCTIVE Test (NDT) Submittal Guide GENERAL The supplier, who intends to perform any NONDESTRUCTIVE tests for Northrop Grumman Aerospace Systems (NGAS), is required to obtain two approvals prior to performing the required NDT. The first step requires the NDT suppliers facility be approved by either NGAS or NGAS s customer and shall be listed on NGAS s OASIS website under Approved Special Processor List (ASPL) or our customer s website ( D1-4426 for F/A-18 and QCS-001 for F-35). The second step requires all NDT techniques be approved by NGAS s Supplier Quality (SQ) NDT Level III per the Table 1. Supplier shall submit the NDT Techniques and Procedures to the responsible NGAS buyer along with X-ray films or any electronic data, as applicable. The approved NDT techniques shall be posted on the NGAS OASIS website under ASPL. SCOPE Supplier shall review the purchase order and associated drawings/drawing notes and related documents to determine if NDT is required.

3 Submittal of NDT general procedures and part-specific techniques to NGAS is required prior to production testing. Requirements for the minimum content of general procedures/ techniques are provided in the respective NDT process specification. After initial approval, any changes to the documents must be re-submitted to NGAS for approval. An EO change or specification revision change requires re-submittal of a letter of compliance or a revised procedure/technique. The letter must contain procedure or technique number, re-submittal date and supplier s NDT Level III signature. On-site validation of procedures/ techniques to verify specification compliance may be performed at the discretion of NGAS SQ NDT Level III. A general procedure may include multiple part numbers. These part numbers will appear on OASIS. A part number specific technique is unique to the part number and will be listed on OASIS. The requirement for a general procedure may be waived if all the minimum requirements required by specification are contained in a part number specific technique.

4 Submittal of general procedures or part number specific techniques is not required to NGAS for parts processed per Mil-Std-2154, ASTM E-1417 or ASTM E-1444. Part number specific techniques are not required for Penetrant Inspection on all programs. Instead, a general PT procedure shall be submitted for all critical parts. NDT Procedure/ Technique submittal requirements are listed in Table 1 by Program, Project ID, NDT category, and procedure type and process specification. Only the online system has the current version. Verify hard copy against online system before use. 5 Table 1 NDT Submittal Requirements PROGRAM PROJECT ID NDT CATEGORY GENERAL PROCEDURE P/N SPECIFIC TECHNIQUE PROCESS SPECIFICATION F/A-18 NM, NN, TF Penetrant All Parts Not required PS 21202 Magnetic Particle MC, FC, FCT PS 21201 Ultrasonic MC, FC, FCT PS 21211 PS PS PS Ultrasonic Composites & Adhesive Bonded Assy s (All Parts) PS PS PS 21255 PS 21244 Radiography MC, FC, FCT PS 21206 Radiography Class 1, 2 & 3 Castings PS 21206 PS 23001 ASTM E-1742 AMS-STD-2175 Radiography/Neutron Radiography Pyrotechnics PS 21206 PS 21222 PS 21237 Radiography Composites & Adhesive Bonded Assy s (All Parts) PS 21206 PS PS Microwave Testing Microwave Testing (All Parts) PS 21266 PS PS PS PS Nital Etch Nital Etch MC, FC, FCT PS 21205 Leak Testing Leak Test MC, FC, FCT PS 21241 PS PS Eddy Current MC, FC, FCT PS 21219 PS Only the online system has the current version.

5 Verify hard copy against online system before use. 6 Table 1 NDT Submittal Requirements (Cont d) PROGRAM PROJECT ID NDT CATEGORY GENERAL PROCEDURE P/N SPECIFIC TECHNIQUE PROCESS SPECIFICATION B-2 / B-2 Spares BS, HH All All Parts All Parts except for Penetrant Reference Note 2. T-101, T-102, T-103, T-104, T-106, T-107, T-111, T-113, T-117, T-121, T-123, T-132, T-133, T-135, T-169, T-170, T-171 Global Hawk/ BAMS* GH, BM* Penetrant All Parts Not required 367-1200-1495, 29259-18 Magnetic Particle All Parts 29259-24 Ultrasonic Composites ACS-PRS-7001 Eddy Current Critical Parts T-113, T-132 Radiography Composites & Welded Parts T-102, T-106 F-35 JF Penetrant Note 1 All Parts Not Required LMA-PC201 Magnetic Particle All Parts LMA-PC007 Radiography All Parts LMA-PC301 Ultrasonic All Composites & Adhesive Bonded Assy s. LMA-PC001 Eddy Current All Parts LMA-PC002 Ultrasonic Inspection of raw materials Not Required Not required except for final parts and intermediate configuration LMA-PC008 F-5/ T-38 AA, AB Penetrant All Parts Not Required IT-60 Magnetic Particle Critical Parts IT-61 Radiography All Parts , IT-90 Ultrasonic All Parts IT-89, IT-103 Nital Etch Critical Parts IT-69 Leak Testing Plastic Parts IT-75 Only the online system has the current version.

6 Verify hard copy against online system before use. 7 Table 1 NDT Submittal Requirements (Cont d) PROGRAM PROJECT ID NDT CATEGORY GENERAL PROCEDURE P/N SPECIFIC TECHNIQUE PROCESS SPECIFICATION J-UCAS & ATDC See note 3. JU All All Parts All Parts except for Penetrant Reference Note 3 ACS-PRS-7001, ACS-PRS-7002, ACS-PRS-7004, ACS-PRS-7005, ACS-PRS-7006, ACS-PRS-7007, ACS-PRS-7009, ACS-PRS-7010 ACS-PRS-7012 ACS-PRS-7013, ACS-PRS-7014, ACS-PRS-7015, Note 1: F-35 Program Penetrant Inspection (LMA-PC 201) --- Suppliers, listed on QCS-001 as Lockheed Martin approved sources, are not required to obtain NGAS approval for their general procedure. However, suppliers, listed on NGAS ASPL, are required to submit their Penetrant general procedure to NGAS. Note 2: T103, part specific techniques are required per for Fracture and Durability Critical parts. Note 3: Any NGAS program referencing ACS 7000 series of NDT specs require part number specific and/or general procedures approved by NGAS.