EXCAVATION AND BACKFILL FOR STRUCTURES
ITEM 400. EXCAVATION AND BACKFILL FOR STRUCTURES . Description. Excavate for placement and construction of STRUCTURES and BACKFILL STRUCTURES . Cut and restore pavement. Materials. Use materials that meet the requirements of the following Items: Item 401, Flowable BACKFILL . Item 421, Hydraulic Cement Concrete . DMS-4600, Hydraulic Cement . Construction. A. EXCAVATION . 1. General. Excavate to the lines and grades shown on the plans or as directed. Provide slopes, benching, sheeting, bracing, pumping, and bailing as necessary to maintain the stability and safety of excavations up to 5 ft. deep. EXCAVATION protection for excavations deeper than 5 ft.
ITEM 400 EXCAVATION AND BACKFILL FOR STRUCTURES 400.1. Description. Excavate for placement and construction of structures and backfill structures.