CEE 536 CRITICAL PATH METHODS Example Problems Photios G. Ioannou, PhD, PE Professor of Civil and Environmental Engineering Chachrist Srisuwanrat, Former Graduate Student Instructor University of Michigan Ann Arbor, Michigan 48109-2125 TABLE OF CONTENTS 1. network CONSTRUCTION---------------------------- ---------------------------------------- 3 ACTIVITY ON ACTIVITY ON 2. ACTIVITY-ON-ARROW SCHEDULING------------------------------ -------------------------13 EVENT MISSING FLOATS ..13 3. ACTIVITY-ON-NODE SCHEDULING------------------------------ ----------------------------32 4. SCHEDULING USING A LINK MATRIX---------------------------------- ---------------------46 5. PROJECT UPDATING-------------------------------- ---------------------------------------- -----52 6. PERT PNET------------------------------------ ---------------------------------------- ------------54 7. TIME-COST TRADEOFF TABLES---------------------------------- ----------------------------67 8.
a) Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. b) Construct a precedence network based on the same activity descriptions below.
Domain:
Source:
Link to this page:
Please notify us if you found a problem with this document:
{{id}} {{{paragraph}}}