RISK ASSESSMENT & METHOD STATEMENT

RISK ASSESSMENT & METHOD STATEMENTRAMS No. Title: Rev No. 01 Water Treatment Building Demolition 01 Site Name & Number: Portobello Wastewater Pumping StationSite Location: A259 Telscombe Cliffs, Peacehaven, BN10 7BE Client: Document Revision / Authorisation Record Revision No# Prepared by Positon Date Authorised by Positon Date Details 01 L. BatchfordH&S Manager31/01/19 G. WilliamsContracts Manager 31/01/19 First Issue 02 03 Page 1 of 38 Doc Name: RAMS: Peacehaven Issue Date: 03/01/2019 Rev: 01 Location: Z-Drive: PeacehavenAuthor: LB Contents Section 01 Site Particulars Scope of Works House of Work Constraints to WorkSection 02 Access / Egress Site Access Workface AccessSection 03 Resources Labour Plant & Equipment MaterialsSection 04 Methodology METHOD Summary METHOD SequenceSection 05 PPE Section 06 Competency / Supervision Section 07 Permits Section 08 Emergency Arrangements Section 09 Risk Assessments Section 10 Briefing Sheet Page 2 of 38 Doc Name: RAMS: Peacehaven Issue Date: 03/01/2019 Rev: 01 Location: Z-Drive: PeacehavenAuthor: LB ParticularsScope of Works.

• Safety Signage is to be displayed before entering the Demolition Zone, with workplace Fire Points, Spill Kits, and COSHH Storage established before work. • A waste segregation area will be set out with appropriate signage. This area will be for the segregation of the different waste streams such as WEEE, metal, concrete, etc.

Loading..

Tags:

  Signage

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Spam in document Broken preview Other abuse

Transcription of RISK ASSESSMENT & METHOD STATEMENT

Related search queries