Transcription of September 2013 - INOGATE
{{id}} {{{paragraph}}}
September 2013 1 Contents Commissioning of pipeline Activities 2 Commissioning Procedures These Procedures covers the following: Pre-commissioning, which covers all activities and approvals necessary to allow purging with gas and pressurizing to normal operating pressure to commence. Pipeline preservation , in case gas-initiation of the pipeline is performed later than six months after the installations are completed the pipeline is preserved. Commissioning of dry pipelines. The criteria for being considered a dry pipeline are as follows: Dew point temperature must be < - 20 C measured at atmospheric pressure . Over- pressure following sealing of the lines must be at least I barg. The acceptable minimum standard during the whole period of preservation is a dew point temperature of - I0 C. Commissioning of wet pipelines. Wet pipelines are considered those that are not met the previous criteria 3 PRE-COMMISSIONING ACTIVITIES On substantial completion of construction activities, Contractor mobilizes its commissioning team to initiate pre-commissioning activities in a phased manner.
Commissioning Procedures These Procedures covers the following: Pre-commissioning, which covers all activities and approvals necessary to allow purging with gas and pressurizing to normal operating pressure to commence. Pipeline preservation, in case gas-initiation of the pipeline is performed later than six months after the installations …
Domain:
Source:
Link to this page:
Please notify us if you found a problem with this document:
{{id}} {{{paragraph}}}
3. FOOD PRESERVATION AND PROCESSING, Preservation, Of Vessels: Practical Considerations, Of Vessels: Practical Considerations . Introduction, Connecticut, Method 1312, Vessels, 20 Posterior Flap Hemipelvectomy, AFDXXX(X)AC Series Operators Manual, AFDXXX(X)AC Series . Operators Manual, Industrial Safety Laws in , Gujarat, Industrial Safety Laws in Gujarat