METHOD STATEMENT FOR GYPSUM PARTITIONS, …

Document No : RTS/QAQC/OO1. Revision No : 02. ROCHANA TECHNICAL Date : 18TH MARCH 2010. Page No :1/9. SERVICES L L C. METHOD STATEMENT . Title: METHOD STATEMENT FOR GYPSUM partitions , LINING AND. CEILINGS. REVISION STATUS. Prepared by Revision Revision Date No Description GYPSUM 00 partitions SW. and lining. Document No : RTS/QAQC/OO1. Revision No : 02. ROCHANA TECHNICAL Date : 18TH MARCH 2010. Page No :2/9. SERVICES L L C. CONTENTS. 1. Purpose 2. Principles 3. References 4. Personnel and Responsibilties 5. METHOD of Construction 6. Codes and Standards related to this section 7. Pre Construction Activities 8. Delivery, Storage and Handling 9. Construction & Handing over works for Partition and lining works conduits, AC duct Openings, Grills etc ,Equipment and Plant to be used Arrangement works ,safety and envioronment requirement Arrangement Approvals & other documentations to be produced safety Engineers approval Document No : RTS/QAQC/OO1.

ROCHANA TECHNICAL SERVICES Page No : L L C Document No : RTS/QAQC/OO1 Revision No : 02 Date : 18TH MARCH 2010 2 / 9 CONTENTS 1. Purpose

Tags:

  Methods, Testament, Gypsum, Partitions, Method statement for gypsum partitions

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of METHOD STATEMENT FOR GYPSUM PARTITIONS, …

1 Document No : RTS/QAQC/OO1. Revision No : 02. ROCHANA TECHNICAL Date : 18TH MARCH 2010. Page No :1/9. SERVICES L L C. METHOD STATEMENT . Title: METHOD STATEMENT FOR GYPSUM partitions , LINING AND. CEILINGS. REVISION STATUS. Prepared by Revision Revision Date No Description GYPSUM 00 partitions SW. and lining. Document No : RTS/QAQC/OO1. Revision No : 02. ROCHANA TECHNICAL Date : 18TH MARCH 2010. Page No :2/9. SERVICES L L C. CONTENTS. 1. Purpose 2. Principles 3. References 4. Personnel and Responsibilties 5. METHOD of Construction 6. Codes and Standards related to this section 7. Pre Construction Activities 8. Delivery, Storage and Handling 9. Construction & Handing over works for Partition and lining works conduits, AC duct Openings, Grills etc ,Equipment and Plant to be used Arrangement works ,safety and envioronment requirement Arrangement Approvals & other documentations to be produced safety Engineers approval Document No : RTS/QAQC/OO1.

2 Revision No : 02. ROCHANA TECHNICAL Date : 18TH MARCH 2010. Page No :3/9. SERVICES L L C. Purpose:- This METHOD STATEMENT provides the control sequence and methodology that will be used for the construction of GYPSUM Partition, Lining and Ceiling in order to achieve compliance with the Contract Specifications and Drawing. Principles:- The principle of this document is to ensure that all methods and stages for the construction of GYPSUM partition and ceiling is detailed for smoooth progress of the work. This METHOD STATEMENT is prepared in general for all types of GYPSUM partition, lining and ceiling as detailed on Contract Drawings and approved Shop Drawings encompassing: Materials Construction Inspection & Testing Final Approvals Risk Management References:- Contract specifications for GYPSUM partition and ceiling.

3 All related codes and standards referenced in the Contract specifications. Contract drawings. Approved workshop drawings. Approved MEP builders work drawings. Approved material submittals. Program of works. Project Quality Plan Approved project safety plan and procedures. Responsibilities Preparation of Procedure - QA/QC Engineer Review of Procedure - Construction Manager Review of Procedure - Safety Engineer Approval Of Procedure - Project Director Implementation - As described in the procedure The Construction Manager will be responsible for the delegation to designate persons as well as the QA/QC department the responsibility for the inspection and acceptance of any work. METHOD of Construction Document No : RTS/QAQC/OO1.

4 Revision No : 02. ROCHANA TECHNICAL Date : 18TH MARCH 2010. Page No :4/9. SERVICES L L C. Preliminary Activities/ Approvals Submit to the Engineer for approval, samples of the required components and related accessories of the partition framing material, ceiling framing material and different types of GYPSUM boards and insulation. Submit for approval of shop drawings detailing sections of different types of partitions , lining and ceiling with junction details, floor and soffit fixing deatil etc. Build sample partition , ceiling and mock ups to a minimum size 3000mmx3000mm and provide a schedule of materials used in the samples/mock up for approval of the Engineer. Submit METHOD STATEMENT , Inspection & Test Plan to the Engineer for approval.

5 Prepare and submit for approval Temporary Works shop. Codes and Standards related to this section As per specifications Pre Construction Activities Ensure all required document and material approvals have been obtained. Inspect and ascertain conformance of existing base structures and preceding trade works done by others. Ensure materials have been obtained from approved suppliers . Ensure MEP co ordination function takes place and all relevant personnel are aware of requirements prior to commencing of work in each work zone. Ensure work area is clear and safe. Ensure all constraints on operations have been identified and precautions are taken. Ensure QC and HSE monitoring documents and procedures are established and approved.

6 Arrange all necessary personnel, equipment and services as required for the works and ensure adequate water, lighting, power and access arrangements are in place. Where further information/ clarification in respect of Contract drawings are required the matter shall be referred to the Engineer by means of a request for information. (RFI). Implement Employee induction procedures and Tool Box Talks for ongoing risk assessment and identification of hazards. Ensure the structure is not overloaded when materials are distributed within the structure. Erect scaffold and access platforms in accordance with approved temporary works documents and safety procedures. DELIVERY,STORAGE AND HANDLING.

7 GYPSUM Partition and lining material ( GYPSUM boards, insulation and framing components). accompanied by delivery notes, to be delivered to site palletized, and stored in fully enclosed, conditioned space, protected against damage from moisture, humidity, temperature extremes, direct sunlight, surface contamination, and other causes. Document No : RTS/QAQC/OO1. Revision No : 02. ROCHANA TECHNICAL Date : 18TH MARCH 2010. Page No :5/9. SERVICES L L C. Construction Layout marking or setting out A team of surveyors and his gang allocated specifically for layout marking are given an orientation about the site requirement by Site Engineer. This team will carry out layout marking as per approved drawing in concurrence with the schedule of work.

8 The layout would be marked with chalk line on the floor. These lines will get transferred to the slab with the help of Laser/plumb to maintain the verticality of Partition. Once the setting out is completed the end points will be marked with permanent markers. The type of partition as per wall key will be marked alongside the marking, for easy reference. The level and line for setting out would be taken from the authenticated bench mark and grid lines given by the Main Contractor at site. The layout will be cross-checked by Site Supervisor before proceeding with installation. Frame work for partitions and lining Top tracks will be fixed onto the soffit as per the particular wall type.

9 The tracks will be fixed securely with wall plug & self taping screws, at a maximum spacing of 600mm centre in staggered manner. The floor tracks will also be fixed in the same manner with same hardware. The studs will be installed as per approved shop drawing between the top and bottom tracks. The frame work will be inspected by ROCHANA TECHNICAL SERVICES supervisor and Site Engineer against shop drawing details and discrepancy, if any will be rectified prior to proceeding further. Frame work for ceilings All hangers are fixed to the soffit of slab with the help of anchor nails at a maximum spacing of 1200 mm centre to centre. After hangers are fixed then the wall angles are fixed to the walls at the perimeter of ceiling the main channels are fixed to these hangers also at a maximu spacing of 1200 mm centre to centre with the help of channel screws.

10 After fixing main channels then the furring channels (Hat Sections) are fixed to the bottom of main channels in perpendicular direction at a maximum spacing of 600 mm centre to centre with the help of channel screws. The frame work will be inspected by ROCHANA TECHNICAL SERVICES. supervisor and Site Engineer against shop drawing details and discrepancy, if any will be rectified prior to proceeding further. Boarding for partitions After the inspection of frame work by ROCHANA TECHNICAL SERVICES Site Engineer, one side boarding will be done. Boards will be installed along the stud direction with plaster board screws at 3000mm C/C distance in the middle and 200 mm c/c at ends. The screw heads will be driven 2-3mm from the external face to allow for the filling of screw heads.