RICS Defining completion of construction works
www.rics.org2.3 Practical completion under the JCT forms of contract Under the JCT contracts, completion of the works is generally referred to as ‘practical completion’. Some have tried to interpret the phrase as allowing a state of less than full completion. In this context, the phrase ‘beneficial occupation’ was often used
Delay and Disruption - Completion - FIDIC
fidic.orgDOM/1) Form of SubContract. Clause 14.1 required the Sub-Contractor to give notice when he considered practical completion of the SubContract works had been achieved. The Form made provision for the parties to agree the date of Practical Completion, but in the event of disagreement practical completion was deemed
Certificate of Practical Completion - JBCC
www.jbcc.co.zaEmployer Contractor Works Site The principal agent certifies that practical completion for: (Clause 19) the works as a whole yes / no ? or (Clause 20) section # of 'Name' was achieved on … Date Date Date Certificate of Practical Completion Issued in terms of clause 19.0 or clause 20.0 of the
Why is Practical Completion Important - CICES
www.cices.org.hk1 Tim Hallworth, Associate Lighthouse Club Seminar on Contract Management "Complete or Not Complete, That is the Question" 19 June 2010 www.hoganlovells.com 2