AMPLUS LTD METHOD STATEMENT - BOREHOLES - rotary METHOD OF EXCAVATION - MACHINE - FRASTE PL RIG PROJECT NO: 1 GENERAL All work will be carried out by experienced drillers trained to guidelines of the British Drilling Association and in accordance with BS5939: 1999. All operatives will have received training in Health and Safety, site activity/awareness and their individual tasks. Before the commencement of any site works, the drilling operatives will have received information on the site and the BOREHOLES , dynamic sampling and trial pits.

2.2 Rotary Drilling 1. The rig will be operated in accordance with the manufacturer's specification and BDA Code of Safe Drilling Practice. 2.

Tags:

  Methods, Testament, Rotary, Borehole, Ltd method statement boreholes

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of AMPLUS LTD METHOD STATEMENT - BOREHOLES …

1 AMPLUS LTD METHOD STATEMENT - BOREHOLES - rotary METHOD OF EXCAVATION - MACHINE - FRASTE PL RIG PROJECT NO: 1 GENERAL All work will be carried out by experienced drillers trained to guidelines of the British Drilling Association and in accordance with BS5939: 1999. All operatives will have received training in Health and Safety, site activity/awareness and their individual tasks. Before the commencement of any site works, the drilling operatives will have received information on the site and the BOREHOLES , dynamic sampling and trial pits.

2 This will include a Job Information Sheet for the site that will have been completed by the Project Engineer. The appropriate sheet for this site includes information on: 1. Access routes to the site that have been agreed with the Project Manager/engineer. 2. Confirmation that underground service location plans have been made available by the Client/Engineer and that services are not located below borehole and trial pit positions. (This is to be confirmed on the Permit to Dig Form).

3 3. The site designation in accordance with Appendix V of the Institution of Civil Engineers' Guidelines for the safe investigation by drilling of landfills and contaminated land and thereby the Personal Protective Equipment (PPE) that should be worn by site staff. 4. The specification for the site investigation, including borehole and trial pit depths, testing type and frequency, sampling frequency and reinstatement requirements. 5. The number of piezometer installations and their configuration.

4 6. The requirement or otherwise for inspection pits to check for services. 7. Restrictions on working hours. 8. Height limitations. 2 FIELDWORK ACTIVITIES The following section describes the activities associated with the investigation of a site. Mobilisation and set-up rotary Drilling Sub-sampling or coring and reinstatement of holes Date of Issue: 25/01/08 Page 1 of 4 AMPLUS Ltd Issue 1 - Revision 0 Mobilisation and set-up 1.

5 All operations will be undertaken by the Drilling Foreman and Assistant Driller, who are responsible for their own Health and Safety and that of any other people affected by site works. 2. All equipment and material required for site work will be loaded into a Landrover or similar vehicle to be transported to site. 3. Either a Landrover or similar will be used to tow the trailer carrying the Fraste PL Rig to site or a Hiab lorry will lift and carry the rig to site. 4. Heras fencing will be erected around the working area to provide a barrier between the works and the public.

6 Signs will be erected to indicate to members of the public that they must not enter the site without prior authorisation. 5. Before entering the site, all personnel will wear PPE appropriate to the site. This site can be categorised as 'yellow' under the Guidelines for the safe drilling of landfills and contaminated land. 6. At the locations marked out by the Client or the Engineer, a CAT scanner will be used to verify that no electric cables run below trial pit or borehole positions. If the CAT scanner indicates the presence of any electric cables, the Drilling Foreman will notify the Engineer immediately.

7 With the agreement of the Engineer, the investigation hole will then be displaced to the nearest position that there are no cables according to the CAT scanner. 7. After the CAT survey, any paving slabs will be lifted. Where possible, slabs will be preserved for reuse during reinstatement. 8. Given that there is uncertainty surrounding the accuracy or otherwise of the service drawings that exist for the site, an inspection pit will be excavated to for the borehole . Inspection pits will be excavated using hand tools such as picks and shovels.

8 9. Any other hand-dug trial pits will be excavated in the same manner as inspection pits. Samples will be taken at the rate specified on the Job Information Sheet. 10. If material that appears to be contaminated is encountered during pitting, the Drilling Foreman shall suspend work. Work shall only recommence when all workers are attired in the appropriate PPE for the contamination. Samples of any potentially contaminated material shall be taken for geochemical testing. 11. On completion of the inspection pit, the drilling rig is to be placed over the borehole position.

9 12. The rig will be erected in a safe manner in accordance with the operating manual, on a firm and level working surface, using timber baulking and taking precautions to prevent toppling and 'runaway'. Particular attention will be given to overhead cables, structures and parked cars. Date of Issue: 25/01/08 Page 2 of 4 AMPLUS Ltd Issue 1 - Revision 0 rotary Drilling 1. The rig will be operated in accordance with the manufacturer's specification and BDA Code of Safe Drilling Practice.

10 2. Working areas will be kept free as practicable from borehole arisings and equipment not actually in use. Particular attention to be paid to 'trip' hazards. 3. Dry drilling and rotary core drilling methods will be used to form open holes and obtain cores in superficial deposits and rock. 4. Dry Drilling The drilling rod is placed in the rotary drilling head of the rig. The chuck is then sufficiently tightened to grip rod, onto which the drilling barrel is then screwed by hand.