Transcription of Certificate of Practical Completion - JBCC
1 EmployerContractorWorksSiteThe principal agent certifies that Practical Completion for:(Clause 19)the works as a wholeyes / no ?or(Clause 20)section # of'Name'was achieved on ..DateDateDateCertificate of Practical CompletionIssued in terms of clause or clause of the Principal Building Agreement Edition March 2014 JBCC PBA Edition Certificate OF Practical Completion March 2014 Where Practical Completion has been certified the Defects Liability Period ends ninety (90) calendar days from the date of Practical Completion subject to clause 21 (final Completion )
2 Name and address of the principal agent's practiceSigned by the principal agent who, as agent for the employer, certifies that the works has been completed in accordance with the specified criteria for Practical Completion on the date stated, irrespective of the date of signature of this Certificate