DESIGN-BUILD REQUEST FOR PROPOSAL

DESIGN-BUILD . REQUEST FOR PROPOSAL . 1063 Block Replacement project State of Washington Capitol Campus Olympia, WA. Department of Enterprise Services PROPOSAL Deadline: February 20, 2014 @ 3:00pm 1063 Block Replacement project DESIGN-BUILD REQUEST for PROPOSAL I. DESIGN-BUILD PROPOSAL REQUIREMENTS. I. Introduction The State of Washington Department of Enterprise Services (DES) is soliciting Proposals from prequalified teams to provide DESIGN-BUILD services for the 1063 Block Replacement project on the Capitol Campus in Olympia, Washington. The completed project will serve as a general purpose office building with tenants that include the Washington State Patrol (WSP) offices, Office of Financial Management (OFM) and certain Legislative support groups.

1063 Block Replacement Project Design-Build Request for Proposal November 27, 2013 SECTION 1 - REQUEST FOR PROPOSAL Page 3 of 21 A. Procurement Process 1. The Project will be completed using the design-build delivery method, as specified in

Tags:

  Design, Project, Proposal, Request, Build, Design build request for proposal, Project design build request for proposal

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Transcription of DESIGN-BUILD REQUEST FOR PROPOSAL

1 DESIGN-BUILD . REQUEST FOR PROPOSAL . 1063 Block Replacement project State of Washington Capitol Campus Olympia, WA. Department of Enterprise Services PROPOSAL Deadline: February 20, 2014 @ 3:00pm 1063 Block Replacement project DESIGN-BUILD REQUEST for PROPOSAL I. DESIGN-BUILD PROPOSAL REQUIREMENTS. I. Introduction The State of Washington Department of Enterprise Services (DES) is soliciting Proposals from prequalified teams to provide DESIGN-BUILD services for the 1063 Block Replacement project on the Capitol Campus in Olympia, Washington. The completed project will serve as a general purpose office building with tenants that include the Washington State Patrol (WSP) offices, Office of Financial Management (OFM) and certain Legislative support groups.

2 The successful proposer will deliver an innovative, highly-efficient design in keeping with the campus aesthetics that best meets the needs of tenants without sacrificing quality and durability of material systems. Energy, operations, and maintenance performance guarantees will be made part of the final DESIGN-BUILD Contract. DES is a certified public body using the DESIGN-BUILD alternative public works contracting procedures authorized under Chapter RCW and the Washington State Capital Projects Advisory Review Board's project Review Committee. DES expects a collaborative, creative, and productive DESIGN-BUILD process involving the design -builder, DES as owner, tenant agencies, and DES consultants.

3 The following DESIGN-BUILD teams have been pre-qualified through a previously published REQUEST for Qualifications. Proposals will only be accepted from the following DESIGN-BUILD Teams: Hoffman Construction Mortenson Construction Sellen Construction II. project Description and RFP Information The project is planned to consist of a general purpose, modern, resource-efficient office building located at the site bounded by Capitol Way S, Columbia Street SW, Union Avenue SW and 11th Ave SW. Size: 200,000 to 225,000 Gross Square Feet. (Not including tenant parking). See Section V, design Programming Space, Data Sheets for specific programming and square footage requirements.

4 Budget: The maximum allowable design and construction cost ( MADCC ) for the project , which cost is inclusive of the design , construction and all other services to be performed under the DESIGN-BUILD contract, is $62,530,000. The total project budget is $82,000,000. The budgets quoted do not include funds for tenant parking (see RFP parking add alternate) and does not include tenant supplied furnishings and equipment. Proposers will provide a design that maximizes DES's overall goals for the project within the MADCC. See Appendix, Section II, j. design -Builder Owner Responsibility Matrix. Schedule: Substantial Completion of the project is to be achieved no later than October 1, 2016.

5 Performance Guarantee: There will be a five-year guarantee for energy, operations, and maintenance performance. See Appendix, Section II, c. Energy Life Cycle Cost Spreadsheet. Contract Form: DESIGN-BUILD Contract between State of Washington Department of Enterprise Services (Owner) and design -Builder Cost Plus Fee with a Guaranteed Maximum Price. See Appendix, Section II, f. Price PROPOSAL Cost Estimate form. November 27, 2013 SECTION 1 - REQUEST FOR PROPOSAL . Page 2 of 21. 1063 Block Replacement project DESIGN-BUILD REQUEST for PROPOSAL A. Procurement Process 1. The project will be completed using the DESIGN-BUILD delivery method, as specified in Chapter RCW and enabling legislation.

6 DES has obtained agency certification to use DESIGN-BUILD delivery. 2. This RFP is the second step in a two-step procurement process for the selection of the design -Builder. Previously Submitted Statements of Qualification were evaluated by the Evaluation Committee and the three most qualified proposers have been selected for this phase. Those proposers who have been invited to proceed to the second step of the procurement process ( Proposers ) will submit a design and Price PROPOSAL in response to this RFP. Proposers are advised that this RFP may contain criteria not identified in the RFQ or different from what was identified in the RFQ. In the event of any conflict between the RFQ and the RFP Documents, the RFP Documents shall govern.

7 3. Proposers are reminded that while the evaluation process under this RFP constitutes a new and different evaluation from that conducted under the RFQ, DES does intend to refer to the Statements of Qualification to evaluate Proposer's qualifications as addressed more specifically in Article IV. Proposers are expressly advised that to the extent they desire to make a change in their organizational structure, Key Personnel or designated Specialty Subcontractors from what was submitted in the Preliminary PROPOSAL , they must notify DES no later than forty-five (45) days prior to the PROPOSAL Due Date. DES will review such requests and provide a response within fourteen (14).

8 Days of its receipt of such proposed changes, provided, however, that DES shall have no obligation to approve such proposed changes and may approve or disapprove of such changes in its sole discretion. 4. Award of a DESIGN-BUILD Contract ( Contract ) will be made to the Proposer in accordance with the processes and requirements set forth in this RFP. 5. Proposers shall provide the best overall design within the MADCC funds available. No preference will be given to proposers submitting a price PROPOSAL below the allocated MADCC. DES reserves the right to negotiate design details with the successful proposer during the post-award design phase. B. Milestone Schedule DES currently anticipates conducting the procurement of the project in accordance with the following list of milestones leading to award of the Contract.

9 This schedule is subject to revision and DES reserves the right to modify this schedule as it finds necessary, in its sole discretion. Issue RFP to the Finalists November 27, 2013. Issue RFP Addenda December 2013. General Meeting / Site Visit December 9, 2013. Proprietary Meetings Proprietary Meeting #1 December 18, 2013. Proprietary Meeting #2 January 8, 9, 2014. Proprietary Meeting #3 January 30, 31, 2014. design and Price PROPOSAL Due February 20, 2014. Presentations by the Proposers March 5, 6, 2014. November 27, 2013 SECTION 1 - REQUEST FOR PROPOSAL . Page 3 of 21. 1063 Block Replacement project DESIGN-BUILD REQUEST for PROPOSAL Evaluation of Proposals by DES/Team March 2014.

10 Contract Awarded/Notice to Proceed May - June 2014. Substantial Completion October 2016. C. DES's Point of Contact and project Reference The DES's sole point of contact for this project shall be Rick Browning, AIA, project Director ( DES's Point of Contact ). Mr. Browning is the only individual authorized to discuss this RFP. with any interested parties, including Proposers. All communications with Mr. Browning about the project or this RFP shall be via email, as required by applicable provisions of this RFP. Proposers contacting other DES officials, consultants or tenants regarding this solicitation may be disqualified from competition. Rick Browning, AIA.