DIVISION 1 GENERAL DATA 01010 -1 section 01010 summary of work PART 1 GENERAL section INCLUDES A. Description of Existing Facilities B. GENERAL Scope of work C. Contractor s Responsibilities D. System Operations E. work Sequence F. Owner Occupancy G. Contract Documents DESCRIPTION OF EXISTING FACILITIES The existing Rosedale Wastewater Treatment facility consists of a 122,000 gpd (average) extended aeration package plant, chlorination (chlorine gas), dechlorination (sulfur dioxide), parshall flume metering structure and post aeration. The existing site also includes sludge drying beds, sludge holding tank, sludge transfer station, lab building and chemical building.

01010-1 SECTION 01010 SUMMARY OF WORK PART 1 GENERAL 1.1 SECTION INCLUDES A. Description of Existing Facilities B. General Scope of Work

Tags:

  General, Section, Summary, Work, General 1, 01010, Of work, Section 01010 summary of work

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of DIVISION 1 GENERAL DATA - …

1 DIVISION 1 GENERAL DATA 01010 -1 section 01010 summary of work PART 1 GENERAL section INCLUDES A. Description of Existing Facilities B. GENERAL Scope of work C. Contractor s Responsibilities D. System Operations E. work Sequence F. Owner Occupancy G. Contract Documents DESCRIPTION OF EXISTING FACILITIES The existing Rosedale Wastewater Treatment facility consists of a 122,000 gpd (average) extended aeration package plant, chlorination (chlorine gas), dechlorination (sulfur dioxide), parshall flume metering structure and post aeration. The existing site also includes sludge drying beds, sludge holding tank, sludge transfer station, lab building and chemical building.

2 GENERAL SCOPE of work A. The work is as described herein, as shown on the plans, and as specified in the bid/specifications documents. Construction shall be performed in a workmanlike manner and to the satisfaction of the Engineer. B. The scope of work expected under this contract includes: Base Bid: The base bid project includes the construction of new 150,000 gallon earthen flow equalization basin (HDPE liner), new FEB drain lift station, new influent structure with channel macerator and overflow weir to the FEB, rehabilitation of the WWTF drain lift station and valve vault, demolition of the existing lab/chemical building, new pre-engineered chemical building, new emergency generator, installation of VFD s on the existing main lift station and all related grading, piping, electrical, controls and site restoration.

3 The Base bid also includes the removal and disposal of the exposed insulation inside the treatment facility building, the application of a coating system to the inside of the building and the complete cleaning and painting of the existing package plant steel tank. Mandatory Alternate #1: Mandatory Alternate #1 consists of replacing the existing steel entrance doors (3) and the overhead doors (2) at the existing WWTF building. Mandatory Alternate #2: Mandatory Alternate #2 consist of removing and replacing the existing blowers within the WWTF building with new blowers and check valves. 01010 -02 C.

4 All of the above items including site work , piping, electrical, demolition and all other incidental work necessary for construction of the project as described in the project documents, whether explicitly indicated or not. The Contractor shall provide all resources needed to complete the work in a quality manner according to the specified schedule. CONTRACTOR S RESPONSIBILITIES: A. The Contractor shall provide all labor, material equipment, supervision, management, and transportation necessary to complete the scope of work intended and required by these project documents. SYSTEM OPERATION A.

5 It is imperative that the entire system be maintained in operation during the construction, insofar as is practical. Downtime on any system is to be at the convenience of the Owner. The successful bidder shall submit a detailed construction schedule that specifically addresses maintaining normal system operation at the pre-construction conference. Special schedules shall be developed for any system shut downs exceeding 8 hours. work SEQUENCE A. Contractor shall submit a detailed construction schedule to the Engineer for approval at the pre-construction meeting. Schedule must be submitted and approved prior to approval of first pay request from Contractor.

6 B. Coordinate construction schedule and operations with Owner and Engineer. C. Sequence shall be determined by the contract within the time constraints established in the project documents. OWNER OCCUPANCY A. The Owner retains the right to occupy adjacent facilities throughout construction. The Contractor shall minimize disturbances to the Owner s operations. CONTRACT DOCUMENTS A. The contract documents for this project shall consist of this project manual plus the accompanying set of 24 x36 plans entitled Town of Rosedale, Indiana Wastewater Treatment Facility Improvements.

7 END OF section 01039-1 section 01039 COORDINATION AND MEETINGS PART 1 GENERAL section INCLUDES A. Coordination. B. Preconstruction Conference C. Progress Meetings D. Pre-installation Conference COORDINATION A. Coordinate scheduling, submittals, and work of the various Sections of specifications to assure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later. B. Verify that utility requirement characteristics of operating equipment are compatible with building utilities. Coordinate work of various Sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

8 C. Coordinate space requirements and installation of mechanical and electrical work , which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs. D. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements. E. Coordinate completion and clean up of work of separate Sections in preparation for Substantial Completion and for portions of work designated for Owners partial occupancy.

9 F. After Owner occupancy of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of Owner's activities. PRECONSTRUCTION CONFERENCE A. Engineer will schedule a conference after Notice of Award. B. Attendance Required: Owner, Engineer, and Contractors. C. Agenda: 1. Execution of Owner-Contractor Agreement. 2. Contract Completion Dates. 3. Need for additional plans and specifications. 01039-2 4. Submission of list of Subcontractors, list of products, Schedule of Values, and progress schedule. 5. Designation of personnel representing the parties in Contract, and the Engineer.

10 6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders and Contract closeout procedures. 7. Scheduling. 8. Scheduling activities of contractor. PROGRESS MEETINGS A. Engineer shall schedule and administer meetings throughout progress of the work at minimum of monthly intervals. B. Engineer shall make arrangements for meetings, prepare agenda with copies for participants, preside at meetings, record minutes, and distribute copies within two days to Owner, Contractor, and those affected by decisions made. D. Attendance Required: Job superintendent, major Subcontractors and suppliers, Owner, Engineer, as appropriate to agenda topics for each meeting.