Transcription of INTRODUCTION TO ESTIMATING - Pearson
1 CHAPTER ONE. INTRODUCTION . TO ESTIMATING . 1 1 GENERAL INTRODUCTION The estimator is responsible for including everything con- tained in the drawings and the project manual in the submit- Building construction ESTIMATING is the determination of ted bid. Because of the complexity of the drawings and the probable construction costs of any given project. Many items project manual, coupled with the potential cost of an error, influence and contribute to the cost of a project; each item the estimator must read everything thoroughly and recheck must be analyzed, quantified, and priced. Because the esti- all items.
2 Initially, the plans and the project manual must be mate is prepared before the actual construction, much study checked to ensure that they are complete. Then the estimator and thought must be put into the construction documents. can begin the process of quantifying all of the materials pre- The estimator who can visualize the project and accurately sented. Every item included in the estimate must contain as determine its cost will become one of the most important much information as possible. The quantities determined for persons in any construction company. the estimate will ultimately be used to order and purchase For projects constructed with the design-bid-build de- the needed materials.
3 The estimated quantities and their as- livery system, it is necessary for contractors to submit a sociated projected costs will become the basis of project competitive cost estimate for the project. The competition controls ( , budget and baseline schedule ) in the field. in construction bidding is intense, with multiple firms vying ESTIMATING the ultimate cost of a project requires the in- for a single project. To stay in business, a contractor must be tegration of many variables. These variables fall into either the lowest-qualified bidder on a certain number of projects, direct field costs or indirect field costs.
4 The indirect field while maintaining an acceptable profit margin. This profit costs are also referred to as general conditions or project margin must provide the general contractor an acceptable overhead costs in building construction. The direct field rate of return and compensation for the risk associated with costs are the material, labor, equipment, or subcontracted the project. Because the estimate is prepared from the work- items that are permanently and physically integrated into the ing drawings and the project manual for a building, the abil- building. For example, the labor and materials for the foun- ity of the estimator to visualize all of the different phases dation of the building would be a direct field cost .
5 The indi- of the construction project becomes a prime ingredient in rect field costs are the costs for the items that are required successful bidding. to support the field construction efforts. For example, the The working drawings usually contain information rela- project site office would be an indirect field cost . In addi- tive to the design, location, dimensions, and construction of tion, factors such as weather, transportation, soil conditions, the project, while the project manual is a written supplement labor strikes, material availability, and subcontractor avail- to the drawings and includes information pertaining to ma- ability need to be integrated into the estimate.
6 Regardless of terials and workmanship, as well as information about the the variables involved, the estimator must strive to prepare bidding process. The project manual is often mistakenly re- as accurate an estimate as possible. Since subcontractors or ferred to as the specifications because it contains the techni- specialty contractors may perform much of the work in the cal specifications, but it contains much more. The working field, the estimator must be able to articulate the scope of drawings and the project manual constitute the majority of work in order for these companies to furnish a price quote.
7 The contract documents, define the scope of work, and must The complexity of an estimate requires organization, the be considered together when preparing an estimate. The estimator's best judgment, complete specialty contractors'. two complement each other, and they often overlap in the (subcontractors') bids, accurate quantity takeoffs, and accu- information they convey. The bid submitted must be based rate records of completed projects. on the scope of work provided by the owner or the architect. 1. 1 7/20/17 4:06 PM. 2 CHAPTER One The design-build and construction-manager/general- contractor (CM/GC) project delivery systems are gaining in &'6#+.
8 '&. popularity. In the design-build delivery system, the contrac- tor acts as both the designer and the general contractor. In #55'/$.;. 'UVKOCVG #EEWTCE[. the CM/GC delivery system, the contractor and some of the key subcontractors are involved in the design process, pro- /1&'. viding expertise in construction methods and costs, as well as managing the construction process. Integrated project 2#4#/'64+%. delivery (IPD), a relatively new delivery system, involves 537#4'. the owners, designers, contractor, and some of the key sub- (116. contractors in the design process. IPD differs from the CM/ 241,'%6.)]
9 GC delivery system in that the owners, designers, contractor, %1/2#4+510. and key subcontractors share governance, risk, contingency, and the profit on the project. All of these delivery systems 6 KOG VQ %QORNGVG. require the contractor to provide cost estimates for the pro- FIGURE ESTIMATING Time versus Accuracy. posed project throughout the design process. At the conceptual stage of the project, the contrac- tor prepares a cost estimate based on the project's concept. Each piece of work that is to be performed by the contractor This is known as a conceptual estimate. When performing a has a distinct labor requirement that must be estimated.
10 The conceptual estimate, typically, drawings are not available or items that are to be installed by others need to be defined and they are very limited. What exists is often verbal or written priced. Caution needs to be exercised to ensure that there is description of the project scope, which may be accompanied agreement between the contractor and the subcontractor as by a few sketches. When preparing this type of estimate, the to what they are to do and whether they are only to install or contractor makes assumptions about virtually every aspect both supply and install the items. In addition, there needs to of the project.