Example: biology

Resource Levelling for a Construction Project

IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 4 Ver. IV (Jul. - Aug. 2015), PP 05-11 DOI: 5 | Page Resource Levelling for a Construction Project Anuj Dubey , Maharashtra Institute of Technology, Department of Civil, Pune-411039, Maharashtra, India Abstract: Resources are required to carry out specific tasks in a Project , but the availability of resources within a given firm is always limited.

Resource Levelling For A Construction Project DOI: 10.9790/1684-12440511 www.iosrjournals.org 6 | Page

Tags:

  Project, Construction, Resource, Levelling, Resource levelling for a construction project

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Advertisement

Transcription of Resource Levelling for a Construction Project

1 IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 4 Ver. IV (Jul. - Aug. 2015), PP 05-11 DOI: 5 | Page Resource Levelling for a Construction Project Anuj Dubey , Maharashtra Institute of Technology, Department of Civil, Pune-411039, Maharashtra, India Abstract: Resources are required to carry out specific tasks in a Project , but the availability of resources within a given firm is always limited.

2 While preparing the schedule structure, the Project Manager might schedule certain tasks in parallel. In such cases it might be possible that the same Resource is being used in both the parallel tasks, while its availability is limited. This paper emphasises how the Project Manager could resolve such conflicts by using Resource Levelling in modern softwares such as Microsoft Project and Oracle Primavera. Resource Levelling as defined by PMBOK is a technique in which start and finish dates are adjusted based on Resource constraints with the goal of balancing demand for resources with the available supply.

3 It basically refers to solving over-allocation of resources for the given Project . A Resource is over allocated when scheduled to perform more work than possible within the Resource s schedule. Resource Levelling may be simple in which the given tasks are delayed until the given resources are available or they can be complex where the given Resource might be deployed on multiple projects throughout the company, thus requiring Levelling to be done at the company level instead of the individual Project .

4 If Levelling is done on tasks which are not present on the critical path, the given Project will not be delayed, but if the given tasks are critical then the Project would be delayed. Hence, Resource Levelling is a complex issue which needs to be resolved in order to avoid delays in the Project . This paper uses a case study in order to portray how Resource Levelling could be done using Microsoft Project and what its effects are on the duration of the entire Project . Key Words: Resource , Levelling , Schedule, Over-allocation, Critical I.

5 Introduction Resource Levelling The network technique focuses on time element and assumes that unlimited resources are available for assigning to the activities to satisfy the time schedule. But when resources are limited, the critical path and slack lose their significance. Activity may be delayed due to non-availability of resources as well as due to change in the sequence of tasks. The process of distribution of available resources to meet the objectives of various activities constituting a Project is called Resource Allocation or Resource Loading.

6 This is done in a way so that the Project completion schedule is least affected. The act of taking a Project with people assigned to a bunch of tasks and making it so that they don't have to work overtime is called Resource Levelling . Step 1: Allocate resources serially in time. That is, start with the first time-period ( 1st day, 1st week etc.) and schedule all activities possible with the available resources. Then move on to the next time-period and repeat the same. Step 2: When several activities are assigned for the same resources, give preference to the activities with least slack.

7 Step 3: Reschedule non-critical activities if possible so as to free resources for the critical activities. In this process, originally non-critical activities may become critical and the completion time of the Project may be stretched. Critical path, a path comprising of activities with zero slack may not remain critical in strict sense of the term. After completing Resource leveling, Resource smoothing may be carried out for further optimization of the problem. Resource smoothing does not change the duration of the Project ; it only works on the non critical activities.

8 Types of Resource leveling Delaying the task If a Resource is not available for a given task, the given task would be delayed. The software would first perform the activity which is given higher priority in the software. By default the softwares give the same priority to all tasks. The priority for all the tasks may be assigned at the time of preparation of the schedule structure. To control which tasks take precedence over other tasks, user can set Project priorities, so that if the user is working with a common pool of resources among multiple projects, the right projects and tasks take precedence.

9 Resource Levelling For A Construction Project DOI: 6 | Page Splitting Certain types of work may be interrupted in between execution, instead of listing these tasks as two separate activities; the given task may be split in two or more segments. But it is a well-known fact that when resources have to switch tasks or projects mid-stream, they lose time as they have to re-orient themselves to the work. Overtime The given resources may have to work overtime in order to complete the given work.

10 They are paid more wages than that for the standard work hours which is specified by Work Overtime factor. This can level the resources only up to a certain extent and not beyond that. Levelling This may be done in two ways, that is automatic Levelling or manual Levelling . Manual Leveling is always preferred over automatic leveling as it gives much more control in decision making. Automatic leveling gives no control to the user and the software levels all the resources.


Related search queries