RELEASE SECTION 01 32 16 BART FACILITIES STANDARDS Issued: 10/01/2010 PAGE 1 OF 5 STANDARD SPECIFICATIONS SECTION 01 32 16 Construction Progress Schedule PART 1 GENERAL SECTION INCLUDES A. Scheduling format. B. Submittals C. Four-week work plan D. Monthly Progress status report. E. Review, updates, and revisions. F. Requests for time extensions. MEASUREMENT AND PAYMENT A. Separate measurement or payment will not be made for work required under this Section. All costs in connection with the work specified herein will be considered to be included with the related item of work in the Bid Schedule of the Bid Form, or incidental to the Work. GENERAL A. Progress schedules shall represent a practical plan to complete the Work within the Contract time(s) of completion indicated, and shall convey the Contractor s intent in the manner of prosecution and Progress of the Work.
construction progress schedule release – r2.1.1 section 01 32 16 bart facilities standards issued: 10/01/2010 page 2 of 5 st andard specifications
Domain:
Source:
Link to this page:
Please notify us if you found a problem with this document:
{{id}} {{{paragraph}}}
For choosing a Progress Residential home, Guidelines for Progress Notes rev, Columbia, GUIDELINES FOR PROGRESS NOTES, Progress, Conditional waiver and release, UNCONDITIONAL WAIVER AND RELEASE ON, Unconditional waiver and release on progress, Progress DataDirect: ® OpenAccess, Progress DataDirect OpenAccess, Progress Tables (Value Tables): Another Measure, Progress Monitoring the IEP: Putting Data, Progress Report