1 Miami University Yager StadiumWest Stands Restoration Phase IMay 6, 2011 THP # Manual and Drawing Index000010 - 1 DIVISION 1 AND TECHNICAL SPECIFICATIONINDEXDIVISION 1 general REQUIREMENTS011000 Summary of Work011000-1012100 Allowances012100-1012900 Payment Procedures012900-1013300 Submittals Procedures013300-1014000 Quality Requirements014000-1014216 Definitions and Standards014216-1015000 Temporary Facilities and Controls015000-1015600 Barriers015600-1017700 Closeout Procedures017000-1 DIVISION 3 CONCRETE030100 Concrete Repairs030100-1 DIVISION 5 METALS055000 Miscellaneous Metals055000-1 DIVISION 7 THERMAL AND MOISTURE PROTECTION071800 Pedestrian Membrane System071800-1079200 Sealants079200-1 DIVISION 32 SITE WORK321723 Markings321723-1 DRAWING INDEXD rawing NameDrawing NumberTitle Sheet001 West Stands Plan101 Concrete Repair Details102 Waterproofing Details103 Miami University Yager StadiumWest Stands
2 Restoration Phase IMay 6, 2011 THP # of Work011000 - 1 DIVISION 01 - general REQUIREMENTSSECTION 011000 SUMMARY OF WORKPART 1 INCLUDESA. Base Bid work efforts include (generally in South 1/3 of West Stands):1. Aluminum seating removal, temporary storing on site and Cut and coat existing seat anchors and install new stainless steel Concrete Supplemental steel assembly Epoxy/sand scaled surface Pedestrian membrane system Sealant replacement (coves, isolation, circumferential, and longitudinal).8. Handrail anchor Row tag indicator removal and Floor Base bid proposals for all the work will be received from the The Work will be performed under one general Contractor, or two GeneralContractors working separately, at the Owner s 'S DUTIESA. Assume all Contractor responsibilities and provide for the Work required by theContract Give required notices where and when Comply with codes, ordinances, rules, regulations, orders and other legalrequirements of public authorities which bear on the performance of the University Yager StadiumWest Stands Restoration Phase IMay 6, 2011 THP # of Work011000 - 2D.
3 Pay all legally required taxes. Refer to Bidding requirements , general Conditionsfor information relative to sales tax for which the Owner is Apply, secure and pay for all required local permits, fees, licenses and approvalsper the general Conditions of the TO CONTRACTORA. The DIVISION of the body of the Specifications into various Parts has been arrangedfor clarity in the delineation of the various parts of the whole Work. It is not theintent of such DIVISION to develop any secondary responsibilities for the satisfactorycompletion of the Work and all of its parts as required of the Contractor by theContract Documents, nor is the assignment of any parts of the Work to any tradeor craft to be inferred from the Contract DIVISION 01 Specifications typically address items in a general nature and theContractor must take notice that more specific requirements may be included inthe TECHNICAL COORDINATIONA.
4 The Contractor has full responsibility and authority regarding the scheduling andcoordination of the Work within the Contract time and within the requirements ofArticle The Contractor also has full responsibility for the completeness and quality of theWork as outlined in the Contract Documents, and must staff the project withqualified, competent personnel to the extent required for the The Contractor s Project Manager and Lead Project Superintendent are subject tothe review and approval of the Owner. Upon request at any portion of the project( pre-award, post-award and prior to project start, or during the project), theContractor shall produce a detailed resume, with references, documenting theexperience of the Project Manager and Lead Project Superintendent for theOwner s review and All subcontractors shall abide by the Project Schedule and coordination requestsmade by the If a subcontractor is substantially responsible for specific components of the Work( concrete repairs or new concrete placements, waterproofing efforts, electricalwork, painting, etc.)
5 , the Contractor must have a regular, periodic site presenceduring those efforts, not less than two separate days per week, nor less than 20percent of the total work week time, to provide a level of coordination and qualitycontrol consistent with that expected of a wholly self-performing Contractor Unless otherwise directed or allowed, the Owner (or the Owner's representative)Miami University Yager StadiumWest Stands Restoration Phase IMay 6, 2011 THP # of Work011000 - 3communicates directly with the Contractor. All dealings and decisions regardingexecution of the Work shall be from the Owner, (or Owner's representative,) to theContractor; and the reverse The Contractor communicates directly with the subcontractors, vendors The subcontractor shall coordinate with the Contractor who has the overallresponsibility for the Where Work of any one Section of the Specifications affects the Work of otherSections, successive Work shall not be installed until conditions have beeninspected by the Contractor and are satisfactory for successive Work.
6 Installationof successive Work shall serve as the Contractor s acceptance and confidencewith the conditions being covered by subsequent work. The performance ofsuccessive Work shall be the responsibility of the Contractor to Contractor is required to be on site to conduct regular, weekly job progressmeetings with the Owner. Contractor shall include Engineer via telephone for saidprogress meetings and shall distribute written meeting minutes as directed The Owner reserves the right to hold additional job progress and coordinationmeetings on an as-needed basis as determined by the Owner. The Contractorshall be given 48 hours notice (when possible) to said A preconstruction project meeting shall be held by the Owner prior to the start CODESA. The Contractor shall comply with all Federal, State and Municipal laws, codes,ordinances and regulations applicable to the Work in this Contract and also withall requirements of the National Fire Protection Association and the NationalElectric If the above laws, codes or ordinances conflict with this SPECIFICATION , then thelaws, codes or ordinances shall govern, except in such cases where theSpecification exceeds them in quality of materials or labor, then the Specificationsshall be SCHEDULE AND SEQUENCINGA.
7 The Contractor shall submit to the Owner a complete itemized time schedule anddetail program for construction, purchasing of critical materials, and forsubmission of shop drawings and samples. This schedule is required within sevencalendar days after Notice of Award. The schedule shall indicate the duration oftime required for the performance of all work. All construction activities and eachphase of work must be clearly indicated on the schedule. The schedule must beMiami University Yager StadiumWest Stands Restoration Phase IMay 6, 2011 THP # of Work011000 - 4signed by an official of the firm. It must be realistic as its faithful execution will beconsidered a commitment, not an Normal working hours are 7:00 AM to 3:30 PM, Monday through Friday. Work isalso permitted and encouraged for some efforts after closure of adjacent buildingsand businesses, from 10:30 PM to 8:00 AM, Sunday/Monday Work requested by the Contractor to be performed outside of normal workinghours must be coordinated through the Owner.
8 Provide the Owner a minimum of4 working days notice prior to the requested time to perform work outside normalworking hours. Such request shall include type of work to be performed andexpected Odor or fume producing work performed in the vicinity of fresh air intakes (orsimilar occupied building access points) must be performed at night after theshutdown of fresh air intakes. At the Contractor s option, and if approved inadvance by the Owner, work may begin prior to air intake shutdown. If work iselected to begin prior to intake shutdown, the Contractor shall at their expense,employ measures to draw fresh air from areas beyond the work activities thatproduce odors/fumes. All methods or procedures must be approved by, and meetthe satisfaction of the Work performed outside of normal business/working hours shall be performed atno additional cost to the Owner.
9 Additional cost incurred for testing and inspection,including services of the Engineer or Owner's representative shall be solely bornein full by the Work Phasing:1. The Contractor shall capture the entire Work Area (south 1/3 of West Stands)for the duration of the Site Restrictions1. When work is performed which may create a hazard to persons or propertyabove, below or in the proximity of the work, those areas shall be blocked orotherwise protected to eliminate the All work at entry/exits is to be performed in such a manner to allow traffic flowin and out without significantly constricting the Change order work that is to be performed on a time and materials basis shall bebilled as if performed during normal work hours. In the event that work isrequired to be performed outside normal work hours due to schedule or siterestrictions, the Contractor shall be compensated at their standard overtime Should the Contractor fall behind the approved or adjusted schedule in theperformance of his Work and, in the judgment of the Owner, it appears that theContractor cannot complete his Work within the time established by the Contract,Miami University Yager StadiumWest Stands Restoration Phase IMay 6, 2011 THP # of Work011000 - 5then the Contractor shall work overtime, additional shifts or adopt such otherprocedures with the Owner's approval, as may be necessary to restoreadherence to the schedule while maintaining the required level of quality control,testing and inspection.
10 The full cost of such work or procedures shall be borneby the Contractor, including the cost of additional services of the Owner orOwner's Work rejected by the Owner as not meeting the intent or requirements of theContract Documents shall be replaced by the Contractor and shall not result inadditional costs to the Owner. Rejected work will not be cause for an extension tothe Contract The Contractor is responsible for securing work area for performance of the Project Schedule and Sequence:1. The Contractor shall deliver submittals to the Engineer at least 7 days prior The Contractor shall mobilize and begin work not later than two weeks fromreceiving a formal Notice to Proceed or executed Contract. Work shall followthe sequence and phasing as outlined in Contract Documents or Pre-Construction The anticipated Substantial Completion Date for all Work, including ChangeOrder is 12 weeks from date of Final completion of all Work (only work that does not adversely impact the useof the Stadium for events) shall be 28 days beyond specified SubstantialCompletion date.