1 Reprinted January 2019[March 2017] Guide toFULL- depth RECLAMATION (FDR) with CementInjection of waterMilling drumDistressed asphaltUnderlying base materialDeep recycled layerOperating direction1. Report Government Accession Recipient s Catalog Title and SubtitleGuide to FULL-DEPTH RECLAMATION (FDR) with Cement5. Report Date[March 2017] January 20196. Performing Organization Code7. Author(s)Garret D. Reeder, Dale S. Harrington, Michael E. Ayers, Wayne Adaska8. Performing Organization Report Performing Organization Name and AddressNational Concrete Pavement Technology CenterInstitute for Transportation, Iowa State University2711 South Loop Drive, Suite 4700 Ames, IA 50010-866410.
2 Work Unit No. (TRAIS)11. Contract or Grant Sponsoring Organization Name and AddressPortland Cement Association5420 Old Orchard RoadSkokie, IL 60077-108313. Type of Report and Period CoveredGuide/Manual14. Sponsoring Agency Code15. Supplementary NotesReprinted with minor amendments16. AbstractAs the nation s infrastructure ages, agencies at all levels are tasked with maintaining and rehabilitating their infrastructure. Sustainable engineering technologies in pavement rehabilitation, such as FULL-DEPTH RECLAMATION (FDR), could be the answer for agencies in their quest to provide taxpayers with high-quality infrastructure while being good stewards of public funds.
3 FULL-DEPTH RECLAMATION of asphalt pavement is a rehabilitation method that involves recycling an existing asphalt pavement and its underlying layer(s) into a new base layer. The FDR process begins with using a road reclaimer to pulverize an existing asphalt pavement and a portion of the underlying base, subbase, and/or subgrade. Usually the pulverized material is uniformly blended with an additional stabilizing material such as portland cement to provide an upgraded, homogeneous material. Finally, the stabilized material is compacted in place with rollers.
4 The result is a stiff, stabilized base that is ready for a new rigid or flexible surface course. This Guide introduces the FDR with cement process and discusses issues related to project selection, design, construction , and testing/quality Key Wordsasphalt pavement recycling FULL-DEPTH RECLAMATION with cement pavement base pavement rehabilitation 18. Distribution Statement19. Security Classification (of this report) Security Classification (of this page) No. of Pages10222. PriceNAForm DOT F (8-72) Reproduction of completed page authorizedTechnical Report Documentation PageAuthorsGarret D.
5 Reeder, , Snyder & Associates, S. Harrington, , Snyder & Associates, E. Ayers, PhD, Global Pavement Consultants, Inc. Wayne Adaska, , Portland Cement AssociationProgram managerGabriel A. Nelson, , Snyder & Associates, staffMarcia Brink, Managing EditorStephen Post, Graphic Designer and Layout EditorGUIDE TO FULL-DEPTH RECLAMATION (FDR) WITH CEMENT[March 2017]January 2019viGuide to FULL-DEPTH RECLAMATION with CementAbout This GuideThis Guide to FULL-DEPTH RECLAMATION (FDR) with Cement is a product of the National Concrete Pavement Technology Center (CP Tech Center) at Iowa State University s Institute for Transportation, with fund-ing from the Portland Cement Association.
6 The Guide provides a concise discussion of all aspects of selecting, designing, and constructing a reclaimed, cement- stabilized asphalt base in preparation for a new pavement surface layer. Photo CreditsUnless otherwise credited in the text, the photographs and illustrations in this Guide were provided by, and used with the permission of, the following individuals and organizations:Brigham Young UniversityFigure Estrada, Pavement Recycling SystemsFigures , asphalt Paving IndustryFigure Concrete Pavement Technology CenterFigures , , , , , , , , , Cement AssociationFigures , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , and Associates, , , , , , , , , Stokes, The Miller Group, , , , , , , , , More InformationFor technical assistance regarding cement-based concrete paving.
7 Contact the Portland Cement Association or the CP Tech Center:Wayne Adaska Director, Pavements and Geotechnical MarketsPortland Cement Association5420 Old Orchard , IL 60077847-972-9056, Taylor, DirectorMarcia Brink, Managing EditorNational Concrete Pavement Technology CenterInstitute for Transportation, Iowa State University2711 S. Loop Drive, Suite 4700 Ames, IA 50010-8664515-294-9480, Iowa State University nor the Portland Cement Association nor this document s authors, editors, design-ers, illustrators, distributors, or technical advisors make any representations or warranties, expressed or implied, as to the accuracy of information herein and disclaim liability for any State University does not discriminate on the basis of race, color, age, ethnicity, religion, national origin, sexual orientation, gender identity, genetic information, sex.
8 Marital status, disability, or status as a veteran. Inquiries regarding non-discrimination policies may be directed to the Office of Equal Opportunity, Iowa State University, 3410 Beardshear Hall, 515 Morrill Road, Ames, IA 50011; tel 515-294-7612, hotline 515-294-1222, email to FULL-DEPTH RECLAMATION with CementAcknowledgmentsNote that much of the information in this document is based on two excellent resources: the Portland Cement Association s Guide to FULL-DEPTH RECLAMATION (FDR) with Cement (Luhr et al. 2014) and the asphalt Recycling and Reclaiming Association s Basic asphalt Recycling Manual (ARRA 2015).
9 The CP Tech Center gratefully acknowledges the support of the Portland Cement Association (PCA) in the devel-opment and production of this Guide . In addition, the center and authors are grateful to the knowledgeable and experienced professionals, public and private, who served on the technical advisory committee for this project. While the authors generated the overall content, it was the committee s careful reviews of drafts and thoughtful suggestions that make this Guide a useful resource. Thank you to the committee members:Wayne Adaska, PCAStan Bland, PCA Southeast RegionDavid Cannon, PCA Northeast RegionMarco Estrada, Pavement Recycling SystemsDavid Faust, Blount construction Company, Hourani, Summit CompaniesAndy Johnson, PCA Southeast RegionJamie Johnson, PCA Rocky Mountain RegionJim Render, EssrocDavid Rettner, American Engineering Testing, Redinger, Resource International, Ryan, Mt.
10 Carmel Stabilization Group, Schellhammer, Midstate RECLAMATION and Trucking, Singel, Cement Council of TexasKimbel Stokes, The Miller Group, Stowell, Slurry Pavers, Syed, Soil and Land Use Technology, Wykoff, California Nevada Cement AssociationviiiGuide to FULL-DEPTH RECLAMATION with CementChapter 1 Introduction 1 What is FDR? 2 Benefits of FDR 2 Why Add a Stabilizing Agent? 4 Types of FDR Stabilization 5 When is FDR Applicable? 6 Are There Limitations to Using FDR? 6 How is FDR Constructed? 7 Sustainability of FDR 8 Common FDR Projects 9 Primary State and Rural Highways 9 Arterials 10 Local Streets 10 Parking Lots 11 Airports 11 Life Expectancy of FDR 11 Chapter 2 Properties and Materials 13 Density 14 Strength 14 Flexural Strength 15 Unconfined Compressive Strength.