Transcription of WINDSOR PARKWAY – ROSWELL ROAD INTERSECTION RE …
1 July 16, 2013 WINDSOR PARKWAY ROSWELL road INTERSECTION RE-ALIGNMENT RECOMMENDATION Background November 6, 2012 Assistant City Manager Bryant Poole conducted brief individual discussions with affected District Council members related to the City proposed response to the DRI Suggestions presented regarding recommendations staff needed to present to GRTA. January 30, 2013 GRTA issues the Notice of Decision for the DRI 2290 (JLB property) Mid-February, 2013 Small Group Council Briefings Presented to affected District Council members regarding alignment options March 5, 2013 Executive Session Council reviewed proposed options and potential property acquisition Consensus of Council to further refine plans for the auction site alignment Proposed options were authorized for release to the public 2 Background (continued) March 28, 2013 Community Briefing at City Hall, hosted by Public Works Director Garrin Coleman, regarding potential roadway alignments Associations/Neighborhoods Represented: Hedden Townhomes WINDSOR Park Place.
2 WINDSOR Place May 10, 2013 Community Meeting regarding potential roadway alignments held at North Fulton Annex, facilitated by Trisha Thompson Fox on behalf of Council of Neighborhoods. City and GDOT representatives were present to answer questions Associations/Neighborhoods Represented: Sandy Springs Council of Neighborhoods High Point Civic Association North Buckhead Civic Association Buckhead Neighborhood Planning Unit B 3 Hedden Townhomes Meadowbrook Neighborhood Franklin road Townhomes WINDSOR Park Place High Point Civic Association Brooks Cowles: Community Funeral Service Background (continued) May 20, 2013 Discussion facilitated by Chastain Park Civic Association with Assistant City Manager Bryant Poole and Public Works CIP Unit Manager Marty Martin Council member McEnerny in attendance June 18, 2013 City Council, Work Session - Full Presentation of WINDSOR Park alignment options Council requested more detail on funding options Council heard public comment as part of general public comment period Presentation posted on the City s website June 19 4 Background (continued) July 2, 2013 Community Meeting, hosted by Public Works Director Garrin Coleman, held at City Hall Presentation with alignment options discussed Associations/Neighborhoods Represented.
3 Hedden Townhomes High Point Civic Association Sandy Springs Council of Neighborhoods July 12, 2013 Council Member Monthly Zoning Briefing Council provided updates on the identified options for WINDSOR PARKWAY and staff s recommended alignment Presentation provided to Council posted on the City s website as part of the information packet for the July 16 Council meeting July 16, 2013 City Council Public Presentation & Public Input 5 WINDSOR PARKWAY INTERSECTION Relocation Overview Project Background INTERSECTION Improvement Project has been identified in the following publicly vetted documents: ROSWELL road Corridor LCI (2008) Transportation Master Plan (2008) 2027 Comprehensive Plan (2007) Zoning application triggered reviews by: Georgia Regional Transportation Authority (GRTA) as a development of regional impact (DRI): January 30, 2013: Notice of Decision (NOD) issued Based on report, if JLB project is approved, the City must construct offsite transportation improvements or risk losing state and/or federal funding associated with transportation projects as noted in the NOD Attachment C section Input into DRI NOD solicited from regional and local entities such as: Atlanta Regional Commission (ARC) Georgia Department of Transportation City of Atlanta Initial DRI comments recommended Hedden St.
4 As full signalized INTERSECTION -- significant staff concerns on negative impact to neighborhoods 6 WINDSOR PARKWAY INTERSECTION Relocation Overview Staff Actions Engaged with GDOT and GRTA to register concerns and seek a more neighborhood-friendly alternative Acquired services of transportation engineering consultant, Michael Baker Corp., to study alternative alignments for WINDSOR PARKWAY / ROSWELL road INTERSECTION Acquired services of real estate consultants to prepare cost studies of potential business and property acquisition of properties involved Communicated study efforts to neighborhoods and adjacent property owners to seek input Neighborhood and affected property owner meetings June 18, 2013 Council presentation 7 WINDSOR PARKWAY INTERSECTION Relocation Overview Accident Summary High Accident INTERSECTION 103 reported accidents from January 2009 to May 2013 47 of these are head on, angle.
5 Or opposite side swipe 8 27 21 22 21 12 0102030 Number ofCrashesComparison of Years 2009-Present 2013201220112010200939 41 16 1 1 4 1 Summary of Crashes by Type Rear EndAngleSide Swipe SameSide Swipe OppositeHead OnPedestrianSingle INTERSECTION Overview Operational Summary Intersections are rated on the Level of Service scale with grades ranging from A to F. Grade A represents free-flow condition and F represents grid-lock Summary of the Average INTERSECTION Levels of Service for Existing and Future Conditions Peak Hour Existing Future(2027) INTERSECTION Improvement AM PM AM PM ROSWELL Rd. @ WINDSOR Pkwy Realigned WINDSOR PARKWAY D D C C ROSWELL Rd. @ W. Wieuca WB left turn lane A A A B W. Wieuca @ Driveway 3 EB left turn lane A A A A Source: * Foresite Group and City of Sandy Springs 9 WINDSOR PARKWAY INTERSECTION Operational Illustration Existing Condition LOS D Future Condition LOS C 10 WINDSOR PARKWAY INTERSECTION Overview Operational Summary Existing Condition Level of Service for the WINDSOR PARKWAY Approach is LOS E & F (overall INTERSECTION rating is LOS D).
6 Skew Angle - WINDSOR Pkwy intersects ROSWELL Rd at a 57 angle (90 is ideal) Split-Phase - As a result of the skew angle, the signal cannot allow the east and west movements to occur at the same time for safety reasons and green time is reduced Turn Lanes - WINDSOR PARKWAY is a 2 lane approach with a left thru and a right turn lane Separation and Queuing are not Desirable: Signal separation between the ROSWELL road with WINDSOR Pkwy and W. Wieuca Rd is 700 (GDOT criteria currently requires 1,000 minimum) Substandard separation creates vehicle stacking and weaving movements that degrade operations The vehicle queue northbound on ROSWELL road often blocks the INTERSECTION with Meadowbrook road and spills back through West Wieuca and often Wieuca Roads Traffic Volumes: Existing volume of left turns from westbound WINDSOR Pkwy to southbound ROSWELL road are at the threshold volume to warrant a dual left turn lane Traffic volumes on ROSWELL road are heavy and demand the majority of signal green time creating longer delays on WINDSOR Pkwy 11 WINDSOR PARKWAY INTERSECTION Overview Operational Summary Future Condition Level of Service (LOS) C Projected: Skew Angle: Corrected to a 90 Split-Phase.
7 Signal can run without split phase allowing improved operation (frees up an estimated 25 seconds of green time per cycle) Turn Lanes: WINDSOR Pkwy configured with 2 left turn lanes in all current options under consideration Separation and Queuing are more Desirable: Future options result in additional stacking and queuing length on ROSWELL Rd. of approximately 300 between West Wieuca and new WINDSOR PARKWAY re-alignment. This meets City and GDOT criteria requiring 1,000 minimum spacing between traffic signals Traffic Volumes: The new design does not reduce traffic volumes; however, it provides additional turn lanes and improved signal operation to improve the level of service at the INTERSECTION 12 Related Actions West Wieuca Turn Lane (City of Atlanta) Level of Service (LOS) A for the Existing and Future Conditions 13 DRIVE #3 NORTH WINDSOR PARKWAY INTERSECTION Relocation Option #1A (Auction site) 14 WINDSOR PARKWAY INTERSECTION Relocation Option #1A Pros: Greatest level of service provides for dual left turns, dedicated through and right turn lanes Provides a 50 buffer from WINDSOR PARKWAY to the townhomes Increases queuing length Cons.
8 Impact to the buffer/backyards of adjacent townhomes Largest footprint (five lanes) and largest number of parcels impacted Second highest projected construction cost Greatest impact on auction site 15 WINDSOR PARKWAY INTERSECTION Relocation Option #1B (Auction site) 16 WINDSOR PARKWAY INTERSECTION Relocation Option #1B Pros: Reduces total lanes at INTERSECTION to four Provides a 50 buffer from WINDSOR PARKWAY to the townhomes Reduces impact to auction site Lowest project construction cost Cons: Impact to the buffer/backyards of adjacent townhomes Reduced level of service of overall INTERSECTION due to lack of dedicated right turn lane onto ROSWELL road 17 WINDSOR PARKWAY INTERSECTION Relocation Option #2 (Restaurant site) 18 WINDSOR PARKWAY INTERSECTION Relocation Option #2 Pros: This option will not impact the auction site Projected construction cost similar to Option #1B Least amount of impact to homes on Hedden Street Cons.
9 Highest total construction cost Displaces active restaurant Least amount of queuing length along ROSWELL road Reduced level of service of overall INTERSECTION due to lack of dedicated right turn lane onto ROSWELL road 19 WINDSOR PARKWAY INTERSECTION Relocation Cost Estimating Methodology Construction Cost Estimates Prepared by Michael Baker Corp. using GDOT Mean Item Summary construction cost database. 10% contingency applied due to concept stage of design Property Valuations Prepared by Carr, Lawson, Cantrell and Associates Real estate using Sales Comparison Approach for parcels under consideration Business Impact Market range formula provided by HDH Advisors to assess business enterprise value 20 WINDSOR PARKWAY INTERSECTION Relocation Options Planning Level Cost Comparison Option #1A (Auction site) - $ Option #1B (Auction site) - $ Option #2 (Restaurant site) - $ 21 WINDSOR PARKWAY INTERSECTION Relocation Funding Options Impact Fees (CIE)
10 $1,424,028 Development Authority Bond Financing* $2,000,000 Capital Contingency $500,000 T-0019 ROSWELL Streetscape $2,300,000 (reallocation) T-0034 Morgan Falls road $1,500,000 (reallocation) *Subject to availability 22 WINDSOR PARKWAY INTERSECTION Relocation Conclusion Staff recommends that Council endorse the selection of Option 1-B due to the following: Safety Enhancement Traffic Operation Improvements Cost effectiveness to the City 23 QUESTIONS