Transcription of Method Statement Risk Assessment - Scottish Government
{{id}} {{{paragraph}}}
Name Method Statement Form SF 25 Rev: 05 Page 1 of 17 Method Statement & Risk Assessment Project Name: CRAIGENDORAN RISING MAIN Location of the Works: CRAIGENDORAN, HELENSBURGH. Title of Method Statement : ENVIRONMENTAL PROTECTION PROCEDURES DURING PIPE LAYING AT CRAIGENDORAN RISING MAIN. Scope of works The task involves the installation of HDPE Rising Main and includes the following works: Re-Fuelling. Fuel Storage. Plant Precaution. De-Watering Procedures. Reference: Date: 01-04-2016 Prepared By: D Fall Rev: 00 Name Method Statement Form SF 25 Rev: 05 Page 2 of 17 1.
Scope of works The task involves the installation of HDPE Rising Main and includes the following works: Re-Fuelling. ... necessary remedial works may be carried out to ... Approved code of practice for avoiding underground services and avoid danger from overhead services is