CALTRANS ENCROACHMENT PERMITS GUIDELINES AND SPECIFICATIONS FOR TRENCHLESS TECHNOLOGY PROJECTS AUGUST 2018 2 TABLE OF CONTENTS PROCEDURAL REQUIREMENTS FOR DESIGN AND CALCULATIONS OF STRUCTURAL AND SUB -STRUCTURAL PROJECTS .. 3 Structural Design and Calculations .. 3 Substructural Design and Calculations .. 3 Project Owner's Responsibilities .. 4 Contractor's Responsibilities .. 4 TUNNELING PROJECTS .. 5 Cal/Osha Requirements .. 5 Tunnel .. 6 Tunnel Shield .. 6 Tunnel Lining .. 6 Lagging .. 7 Construction of Shafts and Pits.
• The excavation face shall have a sufficient length to allow for the installation of one (1) complete ring of liner plates, or one (1) complete set of ribs and lagging before advancing. • The contractor shall submit details and design information of the shield.