of the completed building. One of the first things that the project manager for this project should do is to write a: 1. Work breakdown structure. 2. Budget baseline. 3. Project charter. 4. Project plan. Answer: C Hint: PMBOK 5 Page 66 Sec 4.1 Develop Project Charter; Page 16, Sec 1.7 Role of the Project Manager