SECTION 01300 CONTRACTOR SUBMITTALSSTANDARD SPECIFICATIONS FOR CIVIL ENGINEERINGCONTRACTOR SUBMITTALSPROJECTS AND SUBDIVISION IMPROVEMENTSPage 01300 -1 December 2003 Includes changes listed in 1/15/04 Errata SheetPART 1 Submittals are required hereunder, all such Submittals shall be submitted to theENGINEER by the 14 Days after the date of commencement as stated in the Notice To Proceed, theCONTRACTOR shall submit the following items to the ENGINEER for preliminary schedule of Shop Drawings, sample, and proposed substitutes or or-equal list of all permits and licenses the CONTRACTOR shall obtain indicating theagency required to grant the permit and the expected date of submittal for thepermit and required date for receipt of the complete progress schedule for all phases of the Safety Data Sheets on products used on the traffic maintenance plan, as plan for temporary erosion control and pollution control, as letter designating the CONTRACTOR s Superintendent, defining that person sresponsibility and letter designating the CONTRACTOR s safety representative and the EqualEmployment Opportunity (EEO) Officer and that person s responsibility Mining Plan shall be submitted and approved, by CBJ Engineering,prior to any materials extraction from the CBJ/State Lemon Creek Gravel payments shal

section 01300 – contractor submittals standard specifications for civil engineering contractor submittals projects and subdivision improvements page 01300-1

Tags:

  Specification, Contractor, Submittal, 31000, 01300 contractor submittals

Information

Domain:

Source:

Link to this page:

Please notify us if you found a problem with this document:

Other abuse

Transcription of 01300 - CONTRACTOR Submittals - Juneau

1 SECTION 01300 CONTRACTOR SUBMITTALSSTANDARD SPECIFICATIONS FOR CIVIL ENGINEERINGCONTRACTOR SUBMITTALSPROJECTS AND SUBDIVISION IMPROVEMENTSPage 01300 -1 December 2003 Includes changes listed in 1/15/04 Errata SheetPART 1 Submittals are required hereunder, all such Submittals shall be submitted to theENGINEER by the 14 Days after the date of commencement as stated in the Notice To Proceed, theCONTRACTOR shall submit the following items to the ENGINEER for preliminary schedule of Shop Drawings, sample, and proposed substitutes or or-equal list of all permits and licenses the CONTRACTOR shall obtain indicating theagency required to grant the permit and the expected date of submittal for thepermit and required date for receipt of the complete progress schedule for all phases of the Safety Data Sheets on products used on the traffic maintenance plan, as plan for temporary erosion control and pollution control, as letter designating the CONTRACTOR s Superintendent, defining that person sresponsibility and letter designating the CONTRACTOR s safety representative and the EqualEmployment Opportunity (EEO) Officer and that person s responsibility Mining Plan shall be submitted and approved, by CBJ Engineering,prior to any materials extraction from the CBJ/State Lemon Creek Gravel payments shall be made to the CONTRACTOR until all of these items are submittedin their entirety, as determined by the DRAWING called for in the Contract Documents, or where required by the ENGINEER,the CONTRACTOR shall furnish to the ENGINEER, for review, eight (8) copies of eachShop Drawing submittal .

2 The term Shop Drawings as used herein shall be understoodto include detail design calculations, Shop Drawings, fabrication drawings, installationdrawings, erection drawings, lists, graphs, operating instructions, catalog sheets, datasheets, and similar Shop Drawing Submittals shall be accompanied by the CONTRACTOR s standardsubmittal transmittal form. Any submittal not accompanied by such a form, or where allapplicable items on the form are not completed, will be returned for , a separate transmittal form shall be used for each specific item or class ofmaterial or equipment for which a submittal is required. Transmittal of a submittal ofvarious items using a single transmittal form will be permitted only when the items takentogether constitute a manufacturer s package or are so functionally related thatexpediency indicates review of the group or package as a whole.

3 A multiple-pagesubmittal shall be collated into sets, and each set shall be stapled or bound, asappropriate, prior to transmittal to the 01300 CONTRACTOR SUBMITTALSSTANDARD SPECIFICATIONS FOR CIVIL ENGINEERINGCONTRACTOR SUBMITTALSPROJECTS AND SUBDIVISION IMPROVEMENTSPage 01300 -2 December 2003 Includes changes listed in 1/15/04 Errata as may otherwise be provided herein, the ENGINEER will return prints of eachsubmittal to the CONTRACTOR with its comments noted thereon, within 30 calendardays following receipt of them by the ENGINEER. It is considered reasonable that theCONTRACTOR shall make a complete and acceptable submittal to the ENGINEER bythe second submission of a submittal item. The OWNER reserves the right to withholdmonies due to the CONTRACTOR to cover additional costs of the ENGINEER s reviewbeyond the second submittal . The ENGINEER s maximum review period for eachsubmittal including all re- Submittals will be 30 days per submission.

4 In other works, fora submittal that requires two re- Submittals before it is complete, the maximum reviewperiod for that submittal could be 90 If three (3) copies of a submittal are returned to the CONTRACTOR marked "NOEXCEPTIONS TAKEN," formal revision and resubmission of said submittal will not If three (3) copies of a submittal are returned to the CONTRACTOR marked "MAKECORRECTIONS NOTED," formal revision and resubmission of said submittal is If one (1) copy of the submittal is returned to the CONTRACTOR marked "AMEND-RESUBMIT," the CONTRACTOR shall revise said submittal and shall resubmit therequired number of copies of said revised submittal to the If one (1) copy of the submittal is returned to the CONTRACTOR marked "REJECTED-RESUBMIT," the CONTRACTOR shall revise said submittal and shall resubmit therequired number of copies of said revised submittal to the Fabrication of an item may be commenced only after the ENGINEER has reviewed thepertinent submittal and returned copies to the CONTRACTOR marked either "NOEXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED.

5 " Corrections indicatedon Submittals shall be considered as changes necessary to meet the requirements of theContract Documents and shall not be taken as the basis for changes to the Contractrequirements only a Change Order can alter the Contract Price, Contract Time, All CONTRACTOR Shop Drawing Submittals shall be carefully reviewed by anauthorized representative of the CONTRACTOR , prior to submission to the submittal shall be dated, signed, and certified by the CONTRACTOR , as beingcorrect and in strict conformance with the Contract Documents. In the case of ShopDrawings, each sheet shall be dated, signed, and certified. No consideration for reviewby the ENGINEER of any CONTRACTOR submittal will be made for any items whichhave not been so certified by the CONTRACTOR . All non-certified Submittals will bereturned to the CONTRACTOR without action taken by the ENGINEER, and any delayscaused by thereby shall be the total responsibility of the The ENGINEER's review of CONTRACTOR Shop Drawing Submittals shall not relievethe CONTRACTOR of the entire responsibility for the correctness of details anddimensions.

6 The CONTRACTOR shall assume all responsibility and risk for any misfitsSECTION 01300 CONTRACTOR SUBMITTALSSTANDARD SPECIFICATIONS FOR CIVIL ENGINEERINGCONTRACTOR SUBMITTALSPROJECTS AND SUBDIVISION IMPROVEMENTSPage 01300 -3 December 2003 Includes changes listed in 1/15/04 Errata Sheetdue to any errors in CONTRACTOR Submittals . The CONTRACTOR shall beresponsible for the dimensions and the design of adequate connections and SAMPLES SUBMITTALA. Whenever in the Specifications samples are required, the CONTRACTOR shall submitnot less than three (3) samples of each item or material to the ENGINEER for acceptanceat not additional cost to the Samples, as required herein, shall be submitted for acceptance a minimum of 21 daysprior to ordering such material for delivery to the job site, and shall be submitted in anorderly sequence so that dependent materials or equipment can be assembled andreviewed without causing delays in the All samples shall be individually and indelibly labeled or tagged indicating thereon allspecified physical characteristics and supplier's names for identification and submitted tothe ENGINEER for acceptance.

7 Upon receiving acceptance of the ENGINEER, one (1)set of the samples will be stamped and dated by the ENGINEER and returned to theCONTRACTOR, and one (1) set of samples will be retained by the ENGINEER, and one(1) set of samples shall remain at the job site until completion of the Unless clearly stated otherwise, it is assumed that all colors and textures of specifieditems presented in sample submittal are from the manufacturer's standard colors andstandard materials, products, or equipment lines. If the samples represent non-standardcolors, materials, products or equipment lines, and their selection will require an increasein Contract Time or Contract Price, the CONTRACTOR will clearly indicate this on thetransmittal page of the OPERATIONS AND MAINTENANCE MANUAL CONTRACTOR shall include in the Operations and Maintenance Manuals for eachitem of mechanical, electrical, and instrumentation equipment, the following:1.

8 Complete operating instructions, including location of controls, special tools orother equipment required, related instrumentation, and other equipment neededfor Lubrication schedules, including the lubricant SAE grade and type, temperaturerange of lubricants, and including frequency of required Preventive maintenance procedures and Parts lists, by generic title and identification number, complete, with explodedviews of each Disassembly and reassembly Name and location of nearest supplier and spare parts Recommended troubleshooting and startup Reproducible prints of the record Drawings, including diagrams and schematics,as required under the electrical and instrumentation portions of Tabulation of proper settings for all pressure relief valves, (low/high) pressureswitches and other related equipment protection Detailed test procedures to determine performance efficiency of 01300 CONTRACTOR SUBMITTALSSTANDARD SPECIFICATIONS FOR CIVIL ENGINEERINGCONTRACTOR SUBMITTALSPROJECTS AND SUBDIVISION IMPROVEMENTSPage 01300 -4 December 2003 Includes changes listed in 1/15/04 Errata Sheet11.

9 List of all electrical relay settings including alarm and contract The CONTRACTOR shall furnish to the ENGINEER five identical sets of technicalmanuals. Each set shall consist of one or more volumes, each of which shall be bound ina standard size, 3-ring, loose-leaf vinyl plastic hard cover binder suitable for bookshelfstorage. Binder ring size shall not exceed inches. A table of contents shall be providedwhich indicates all equipment in the technical All technical manuals shall be submitted complete and in final form to the ENGINEER prior to the requests for final Incomplete or unacceptable Operations and Maintenance Manuals shall constitutesufficient justification to withhold payment for WORK SPARE PARTS LIST SUBMITTALA. The CONTRACTOR shall furnish to the ENGINEER five (5) identical sets of spare partsinformation for all mechanical, electrical, and instrumentation equipment.

10 The spareparts list shall include the current list price of each spare part. The spare parts list shallbe limited to those spare parts which each manufacturer recommends be maintained bythe OWNER in the inventory at the plant site. Each manufacturer or supplier shallindicate the name, address, and telephone number of its nearest outlet of spare parts tofacilitate the OWNER in ordering. The CONTRACTOR shall cross-reference all spareparts lists to the equipment numbers designated in the Contract Documents. The spareparts lists shall be bound in standard size, 3-ring, loose leaf, vinyl plastic hard coverbinders suitable for bookshelf storage. Binder ring size shall not exceed RECORD DRAWINGS SUBMITTALSA. The CONTRACTOR shall keep and maintain, at the job site, one record set of these, it shall mark all project conditions, locations, configurations, and any otherchanges or deviations which may vary from the details represented on the originalContract Drawings, including buried or concealed construction and utility features whichare revealed during the course of construction.