1 dell EMC Data Domain DD6300, DD6800,and DD9300 SystemsVersion Overview and Installation Guide302-003-008 REV 08 Copyright 2016-2018 dell Inc. and its subsidiaries. All rights May 2018 dell believes the information in this publication is accurate as of its publication date. The information is subject to change without INFORMATION IN THIS PUBLICATION IS PROVIDED AS-IS. dell MAKES NO REPRESENTATIONS OR WARRANTIES OF ANY KINDWITH RESPECT TO THE INFORMATION IN THIS PUBLICATION, AND SPECIFICALLY DISCLAIMS IMPLIED WARRANTIES OFMERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. USE, COPYING, AND DISTRIBUTION OF ANY dell software DESCRIBEDIN THIS PUBLICATION REQUIRES AN APPLICABLE software , EMC, and other trademarks are trademarks of dell Inc. or its subsidiaries. Other trademarks may be the property of their respective in the EMCH opkinton, Massachusetts 01748-91031-508-435-1000 In North America Domain DD6300, DD6800, and DD9300 Systems Hardware Overview and Installation Guide57 Revision history9 Planning and Site Preparation11 Tools and supplies 12 Field-installed systems vs.
2 Factory-racked 13 Data Domain DD6300, DD6800, and DD9300 Hardware Overview15 Front front front front 17 Front LED 18 Back rear 19 Rear LED 22 Storage 26DD6300 storage 26DD6800 storage 26DD9300 storage 27DD6300 system 28DD6300 system 29 Internal system system 31DD6800 system 32 Internal system 33DD9300 system 34DD9300 system 35 Internal system the System in the Rack39 Unpack the 40 Rails and cable management 40 Identify the rack location to install the 41 Install the 41 Install the DD6300, DD6800, or DD9300 system into a 43 Installing the cable management assembly (CMA).. 45 FiguresTablesChapter 1 Chapter 2 Chapter 3 CONTENTSData Domain DD6300, DD6800, and DD9300 Systems Hardware Overview and Installation Guide3 Installing the expansion shelves into the Cables and Power on49 Connecting ES30 and DD9300 (single node, DD Cloud Tier, or ERSO).
3 52DD6800 and DD9300 (HA or HA with DD Cloud Tier)..54 Connecting DS60 58DD6800 and 59DD6800 and DD9300 with 61DD6800 with DD Cloud and with HA and DD Cloud with DD Cloud Tier or HA and DD Cloud 65DD6800 and DD9300 with the HA 69 Installing the front 70 Connect data 70 Power on all System for Use73 Enable administrative 74 Accepting the End User License Agreement (EULA).. 75 Run the configuration the 75 Configuring additional system 77 Configure 78 Chapter 4 Chapter 5 CONTENTS4 Data Domain DD6300, DD6800, and DD9300 Systems Hardware Overview and Installation GuideWarning about lifting the LED 18 Rear LED 19I/O module Power/Service LED network port 22I/O module slot 22 CPU and memory 30 CPU and memory and memory 36 Warning about lifting the 40 Cable management assembly (CMA).
4 41 Warning about lifting the 43 Service tag (components removed for clarity).. 45 Installing the CMA on the the CMA 46DD6300 with ES30 52DD6800 and DD9300 with ES30s, single node, DD Cloud Tier, or 54DD6800 and DD9300 with ES30s and HA or HA with DD Cloud 56HA 7012345678910111213141516171819 FIGURESData Domain DD6300, DD6800, and DD9300 Systems Hardware Overview and Installation Guide5 FIGURES6 Data Domain DD6300, DD6800, and DD9300 Systems Hardware Overview and Installation GuideDocument revision 9DD6300 AIO AIO 16DD6300 AIO expanded 16DD6800 DLH SSD DLH configuration drive 17DD6800 DLH expanded configuration drive 17DD9300 DLH SSD DLH configuration drive 17DD9300 DLH expanded configuration drive 17 Front 18DD6300 I/O slot module and DD9300 I/O module slot 23I/O module slot population 24DD6300 storage 26DD6800 storage 27DD9300 storage 27DD6300 system 28DD6300 system 29 System operating 29DD6300 memory DIMM 30 Memory locations - CPU 30 Memory locations - CPU 31DD6800 system system 32 System operating 32DD6800 memory DIMM 33 Memory locations - CPU 33 Memory locations - CPU 34DD9300 system 34DD9300 system 35 System operating
5 Memory DIMM 36 Memory locations - CPU 36 Memory locations - CPU 37 Cables for primary node to ES30 shelf for standby node to ES30 shelf 50ES30 to ES30 cable 51 Primary node cabling node cabling 55DS60 57 Primary node cabling 61 Standby node cabling node cabling node cabling 64 Primary node cabling node cabling 66 Communications Domain DD6300, DD6800, and DD9300 Systems Hardware Overview and Installation Guide7 TABLES8 Data Domain DD6300, DD6800, and DD9300 Systems Hardware Overview and Installation GuideRevision historyTable 1 Document revision historyRevisionDateDocument part # software versionDescription08 May referencesto documentationfor systemsshipped in a rackfrom the rackdimensions,corrected powerspecifications,and heatdissipation(BTU/hr) to history 9 Revision history10 Data Domain DD6300, DD6800, and DD9300 Systems Hardware Overview and Installation GuideCHAPTER 1 Planning and Site PreparationlTools and supplies 12lSafety 12lField-installed systems vs.
6 Factory-racked 13 Planning and Site Preparation 11 Tools and supplies neededThese tools and supplies may be helpful for the Installation and setup tasks for DataDomain modem cable (DB-9 female to female), plus sparelUSB-to-DB-9 serial (male connector) converter cable if the laptop does not have aserial port, plus sparelPower adapter, C13 to NEMA 5 15 (if based in North America), or a power cordfor your laptop power adapter with a C13 plug, so that you can power your laptopfrom a rack PDUlAntistatic wrist strap and conductive foam padlScrewdrivers:nPhillips #2 with a 12 in. or longer bladenPhillips #2 (standard-length blade)nPhillips #1nFlat head 3/16 head 1/4 T10lFlashlightlNeedle nose plierslDiagonal wire cutters (for cutting tie wraps)l2 GB or greater USB flash memory drivelTie wraps (4 in.)
7 And 8 in.)l(recommended) Roll of 5/8 inch Velcro cable tie material (3M ScotchmateSJ-3401 or similar)Safety informationCAUTIONlIf the system is used in a manner that is not specified by the manufacturer,the protection that is provided by the equipment may be RJ45 sockets on the motherboard, PCI cards, or I/O modules are forEthernet connection only and must not be connected to atelecommunications this list of important safety plug-in modules and blank plates are part of the fire enclosure and must beremoved only when a replacement can be added immediately. The system mustnot be run without all parts in , DD6800, and DD9300 systems must be operated only from a powersupply input voltage range of 100 240 VAC and 50 60 Hz. The ES30 and FS15 Planning and Site Preparation12 Data Domain DD6300, DD6800, and DD9300 Systems Hardware Overview and Installation Guideshelves use 100 240 VAC and 50 60 Hz.
8 DS60 shelves use 200 240 VAC and50 60 component is intended to operate with all working power supplies a suitable power source with electrical overload safe electrical earth connection must be provided to each power cord. Checkthe grounding of the power sources before applying plug on each power supply cord is used as the main device to disconnectpower from the system. Ensure that the socket outlets are located near theequipment and are easily unplug the unit if you think it is damaged in any way and beforemoving the system. DD6300, DD6800, and DD9300 systems include two powersupplies. To remove system power completely, disconnect both power power connections must always be disconnected before removal orreplacement of a power supply module from the faulty power supply module must be replaced within 24 not lift system components by yourself.
9 DD6300, DD6800, and DD9300systems weigh up to 80 lbs ( kg) and an ES30 expansion shelf weighs up to68 lbs ( kg). A DS60 shelf weighs up to 225 lbs (102 KG)CAUTIONData Domain systems are heavy. Use at least two people or a mechanical liftto move any not lift an expansion shelf by the front handles on any modules. The handles arenot designed to support the weight of the populated comply with applicable safety, emission, and thermal requirements, coversmust not be removed and all bays must be fitted with plug-in removed from the shipping box, it is ok to lift the system or the chassisFigure 1 Warning about lifting the systemlTo prevent the rack from becoming top-heavy, load the rack with storage shelvesbeginning at the bottom and the system in the designated Domain recommends that you wear a suitable antistatic wrist or ankle strapfor ESD protection.
10 Observe all conventional ESD precautions when handling plug-in modules and systems vs. factory-racked systemsData Domain systems are available from the factory as components to install in anexisting rack on site, or pre-installed in a rack. The following sections provideadditional information about each type of and Site PreparationField-installed systems vs. factory-racked systems 13 Field-installed systemsThis Installation Guide is primarily intended for systems shipped as components to beinstalled in an existing rack on site. Follow all the instructions in this document to rack,cable, and configure the systemsFactory-racked systems are pre-installed in the rack, with the cables alreadyconnected. Follow the instructions in the chapter Configure System For Use toconfigure the factory-racked following documents, available from the Online Support website at , provide additional information about the factory rack.